Purpose and non-commitment, background, objectives, scope, timetable, capability, technical, security, delivery and commercial questions, rules, next steps

BusinessVollständigISO/IEC/IEEE 41062:2024 (software acquisition)rfi

Anleitung: Use it when you need to learn what the market offers, how it prices and what it would need from you before writing an RFP. Fill the objectives, indicative scope and the questions that will change your RFP first, then the rules and timetable. The main pitfall is scoring RFI answers as if they were bids, which is unfair and often challenged.

Vorschau

Request for Information: [Subject of the market enquiry]

Issuer-side Request for Information (RFI) for learning what the market can offer before writing a Request for Proposal: purpose and non-commitment statement, background, problem and objectives, indicative scope, process and timetable, instructions for respondents, questions on the respondent, capability, technology and integration, security and privacy, delivery and service, commercial indicators and market insight, the rules on confidentiality, costs and equal treatment, how responses will be used, the next steps toward the RFP, the response forms and an internal analysis plan. Structure aligned with the acquirer's preparation activities in ISO/IEC/IEEE 41062:2024 (software acquisition). Question IDs map to the requirement prefixes of the Request for Proposal (business/rfp) so findings flow straight into it. Replace every [bracketed] value and every row marked Example; the worked example is the market enquiry a regional transport authority runs before buying an account-based ticketing back office. This is a documentation format, not legal or procurement advice: public bodies must follow the procurement law that applies to them.

Document control

FieldValue
Document ID[RFI-001]
Version[1.0]
Status[Draft / Issued / Closed]
Owner[@procurement-lead]
Approvers/reviewers[@business-owner], [@solution-architect], [@legal-counsel], [@information-security]
Last updatedYYYY-MM-DD
Classification[Public / Issued to invited suppliers only]
Issuing organisation[Organisation name and address]
Single point of contact[Name, role, email or portal]
Issue date and response deadlineYYYY-MM-DD, YYYY-MM-DD [hh:mm, time zone]
Related procurement[Planned RFP name and expected date]

Approvals

RoleNameDecisionDate
Business owner[@name][Approve / Approve with changes]YYYY-MM-DD
Procurement[@name][Decision]YYYY-MM-DD
Legal[@name][Decision]YYYY-MM-DD
Information security[@name][Decision]YYYY-MM-DD

Revision history

VersionDateAuthorChange summary
0.1YYYY-MM-DD[@name]First draft
1.0YYYY-MM-DD[@name]Example: Issued to market
1.1YYYY-MM-DD[@name]Example: Addendum 1: deadline extended by five working days; Q-TEC-004 clarified

Contents

1. Introduction and purpose

[State the purpose in your own words.] Example: The Regional Transport Authority ("the Authority") is preparing to replace its smartcard ticketing back office with an account-based ticketing service that accepts contactless bank cards and mobile wallets. Before it writes a Request for Proposal, the Authority wants to understand the solutions, delivery models, timelines and indicative costs available in the market, and the risks suppliers see.

This RFI is a request for information only. It is not an invitation to tender, an offer or a commitment to buy anything. The Authority may use the information to shape a later procurement, may change its plans and may decide not to proceed. Responding to this RFI is not a condition for taking part in any later procurement, and not responding will not count against any supplier.

The information will be used to:

  1. Confirm whether the objectives in section 3 are achievable and within what time frame.
  2. Refine the scope, lots and requirements of the planned RFP.
  3. Set a realistic budget and choose a commercial model.
  4. Identify risks, dependencies and questions to resolve before the RFP.

2. Background

ItemValue
OrganisationExample: Public transport authority for a region of 2.1 million people; buses and trams run by three contracted operators
Current serviceExample: Closed-loop smartcard scheme with 140 retail top-up agents
VolumesExample: About 1.2 million journeys per day; 400 back-office users; 3,200 validators
Current systemsExample: Card management system (support ends in 18 months), finance ERP, customer portal, open data feed
Hosting and policiesExample: Cloud permitted in approved in-country regions; corporate identity provider mandatory
Known constraintsExample: Existing validators must be reused where possible; fare policy is set by the regional council
Strategy referenceExample: Regional mobility strategy 2026 to 2030, objective 3 (simpler fares)

3. Problem statement and objectives

3.1 Problem statement

[Describe the problem.] Example: Riders must buy and top up a proprietary card; fare changes take months because they need a vendor release; the back office reaches end of support in 18 months; revenue apportionment between operators is a manual monthly process.

3.2 Objectives

IDObjectiveIndicative measure
OBJ-01 (Example)Riders pay with a contactless bank card or mobile wallet on every bus and tram100 percent of validators accept open payments
OBJ-02 (Example)Daily and weekly fare capping across operatorsCap applied automatically to every account
OBJ-03 (Example)The Authority's staff change fares without a supplier releaseNew fare rule live within 10 working days
OBJ-04 (Example)Automated revenue apportionment to operatorsDaily apportionment posted to the ERP
OBJ-05 (Example)Service live before current support endsGo-live within 15 months of contract signature
[OBJ-NN][Objective][Measure]

4. Indicative scope and assumptions

AreaIndicatively in scopeOpen question for respondents
Account-based back office (Example)YesDelivered as software, managed service or both?
Payment acceptance and acquiring (Example)Possibly a separate lotShould acquiring be bought with the back office or separately?
Validator software update (Example)Yes, on existing hardwareWhich validator models can your solution support?
Rider app and web portal (Example)PossiblyStandard product or custom build?
Retail network for cash top-up (Example)Out of scope for nowIs cash access needed in an account-based scheme?
[Area][Yes / No / Possibly][Question]

Assumptions to test: Example: (1) the existing validators can be updated rather than replaced; (2) a managed service in in-country cloud regions is available from more than two suppliers; (3) a 15-month delivery is achievable for a scheme of this size.

5. Process and timetable

StepDateNotes
RFI issuedYYYY-MM-DDThrough [portal / email]
Clarification questions deadlineYYYY-MM-DDQuestions in writing to the single point of contact
Answers to clarifications publishedYYYY-MM-DDAnonymised, sent to all recipients
Optional supplier briefing (online)YYYY-MM-DDExample: 60 minutes, same content for all; recording shared
Response deadlineYYYY-MM-DD [hh:mm]Late responses may be disregarded
Optional follow-up conversationsYYYY-MM-DD to YYYY-MM-DDExample: Up to 60 minutes each, same agenda for every respondent invited
Summary of findings (if published)YYYY-MM-DDExample: Anonymised summary shared with the RFP
Planned RFP issue[Month YYYY, indicative]Subject to approval

6. Instructions for respondents

InstructionDetail
FormatExample: Answer in the response form (section 14), one row per question ID, plus at most 15 pages of supporting material in PDF
Language[Language]
LengthExample: At most 300 words per question unless stated otherwise
Marketing materialExample: Brochures may be attached but will not be read in place of answers
Partial responsesWelcome. Answer the questions relevant to your offering and say which areas you do not cover
Consortia and partnersName partners and which areas they would cover
SubmissionExample: Upload to [portal] before the deadline; email submissions are not accepted
ContactOnly through the single point of contact; do not contact other staff about this RFI
Confidential partsMark commercially sensitive content clearly and explain why (section 11)

7. Information about the respondent

IDQuestionFeeds RFP section
Q-ORG-001Company name, registered address, ownership and size (employees, revenue band)MAN-
Q-ORG-002Describe up to three comparable schemes you have delivered or operate, with scale, year live and whether you are the prime contractorMAN-, IMP-
Q-ORG-003Where would delivery and support staff be located?SEC-, IMP-
Q-ORG-004Which certifications relevant to this service do you hold (for example information security, payment card industry, quality)? Give scope and expiryMAN-, SEC-
Q-ORG-005Which partners or subcontractors would you use and for what?IMP-

8. Capability and solution questions

8.1 Functional capability

IDQuestionFeeds RFP section
Q-CAP-001 (Example)Describe how your solution prices taps and applies daily and weekly caps across several operators, including late or offline tapsFR-
Q-CAP-002 (Example)How do the Authority's staff define and test a new fare rule, and how long does it take from definition to live?FR-
Q-CAP-003 (Example)How are disputed charges and refunds handled by contact centre staff?FR-
Q-CAP-004 (Example)How is revenue apportioned between operators, and how is it reconciled with acquirer settlements?FR-
Q-CAP-005 (Example)Which functions are standard product, configurable, or would require custom development?FR-, COM-
[Q-CAP-NNN][Question][Prefix]

8.2 Technology, integration and data

IDQuestionFeeds RFP section
Q-TEC-001 (Example)Describe the deployment options (software, managed service, SaaS) and where data would be hostedNFR-, SEC-
Q-TEC-002 (Example)Which validator models and interfaces do you support today? What would be needed for other models?FR-, IMP-
Q-TEC-003 (Example)How do you integrate with a finance ERP and an open data feed? Name the interfaces and standards you useNFR-
Q-TEC-004 (Example)What availability, peak throughput and recovery objectives does your service meet for schemes of similar size?NFR-
Q-TEC-005 (Example)How would data be migrated from the current smartcard system, and what would you need from the Authority?IMP-
Q-TEC-006 (Example)How does the Authority get its data back at the end of the contract, in which formats?COM-
[Q-TEC-NNN][Question][Prefix]

8.3 Security, privacy and accessibility

IDQuestionFeeds RFP section
Q-SEC-001 (Example)Summarise your security management approach and independent assurance for this serviceSEC-
Q-SEC-002 (Example)How is cardholder data kept out of the Authority's environment, and which parties would be in scope for payment card compliance?SEC-
Q-SEC-003 (Example)Which personal data does the service process, where, and for how long by default?SEC-
Q-SEC-004 (Example)How do rider-facing channels meet accessibility requirements, and to which conformance level?NFR-, SEC-
[Q-SEC-NNN][Question][Prefix]

8.4 Delivery and service

IDQuestionFeeds RFP section
Q-DEL-001 (Example)Describe a realistic delivery plan from contract to go-live, with phases and the main dependencies on the AuthorityIMP-
Q-DEL-002 (Example)What roles and time would the Authority need to provide during delivery?IMP-
Q-DEL-003 (Example)Describe your service model after go-live: support hours, service levels, release cadenceIMP-, NFR-
Q-DEL-004 (Example)What are the main delivery risks for a scheme like this, and how would you reduce them?IMP-
[Q-DEL-NNN][Question][Prefix]

9. Commercial indicators

IDQuestionFeeds RFP section
Q-COM-001 (Example)Which pricing models do you offer (for example per transaction, per active account, fixed annual fee, licence plus support)?COM-
Q-COM-002 (Example)Give a rough order of magnitude for one-off and annual costs for the volumes in section 2, stating your assumptionsCOM-
Q-COM-003 (Example)Which factors most change the price (volumes, number of validator models, custom features, service levels)?COM-
Q-COM-004 (Example)What contract length and exit terms do you consider reasonable?COM-
Q-COM-005 (Example)Are there third-party costs the Authority should budget for separately (for example acquiring fees, hardware)?COM-

Price indications are for budgeting only and will not be treated as offers. They will not be used to exclude or rank respondents.

10. Market insight and innovation

IDQuestion
Q-MKT-001 (Example)What would you change in our objectives, scope or timetable to get a better result?
Q-MKT-002 (Example)How should the procurement be split into lots, if at all, and why?
Q-MKT-003 (Example)Which requirements typical in similar tenders drive cost without adding value?
Q-MKT-004 (Example)Which developments in the next three years (for example new payment methods, regulation) should the design allow for?
Q-MKT-005 (Example)What would you need from the Authority to propose a proof of concept on its own validators?

11. Rules of the RFI

RuleStatement
No commitmentThis RFI creates no contract, obligation or commitment to procure. The issuer may change or cancel its plans at any time
CostsRespondents bear their own costs of responding and of any follow-up
Confidentiality of the RFIExample: The RFI content may be shared only with staff and advisers who need it to respond
Confidentiality of responsesThe issuer will treat content marked as commercially sensitive as confidential, subject to [applicable law, for example freedom of information or public records law], and may share responses with its advisers under confidentiality
Equal treatmentAll recipients receive the same information at the same time; answers to clarification questions are shared anonymously with all
CommunicationsOnly through the single point of contact; canvassing staff or officials may lead to exclusion from later procurement
Conflicts of interestRespondents declare any relationship with the issuer's staff or advisers
Personal dataContact details in responses are processed only to run this RFI and the related procurement; [privacy notice link]
Intellectual propertyRespondents keep ownership of their material; the issuer may use general ideas in its own documents without attribution
Later procurementParticipation in this RFI gives no advantage or disadvantage in any later procurement
Public procurement lawExample: Public buyers run market engagement under their own law: in the EU, Directive 2014/24/EU Article 40 (preliminary market consultations) and Article 41 (prior involvement of candidates, which requires relevant information to be shared with all bidders and adequate time limits), as transposed nationally; in the UK, Procurement Act 2023 sections 16 and 17 (preliminary market engagement and its notice); for US federal buyers, the FAR rules on market research and exchanges with industry before proposals (check the current Revolutionary FAR Overhaul text). Check the consolidated text before use

12. How responses will be used

Responses will be read by a team of [business, technical, security and procurement] staff. They will not be formally scored. The team will compare answers question by question to identify common practice, differences in approach, realistic timelines and cost ranges, and risks. The findings will shape the RFP requirements, lots, evaluation criteria and budget. [If applicable: The issuer may invite some or all respondents to a follow-up conversation; the same agenda and time will be offered to each invited respondent.]

13. Next steps

StepWhat happens
AcknowledgementEvery respondent receives confirmation of receipt within [2] working days
Follow-upExample: Optional conversations in the weeks after the deadline
FindingsExample: A short anonymised summary of findings will be shared with all respondents and published with the RFP
RFPExample: A competitive RFP is planned for [month YYYY], published on [portal]. All interested suppliers may take part, whether or not they responded to this RFI

14. Response forms

14.1 Respondent declaration

ItemRespondent entry
Legal name of respondent[Name]
Contact person, role, email, phone[Details]
Areas of scope covered (section 4)[List]
Partners or subcontractors[Names and roles]
Conflicts of interest declared[None / details]
Parts marked commercially sensitive[Question IDs and reason]
Signed on behalf of the respondent[Name, role, date]

14.2 Answer sheet

Question IDAnswer (max words as stated)Supporting document referenceCovered by partner?
Q-ORG-001[Answer][Doc and page][Yes / No]
Q-CAP-001[Answer][Doc and page][Yes / No]
[Q-XXX-NNN][Answer][Reference][Yes / No]

15. Issuer analysis plan (internal, remove before issue)

15.1 Analysis team and method

ItemValue
Analysis teamExample: @business-owner, @solution-architect, @information-security, @procurement-lead
MethodExample: Each question read by two team members; findings recorded per question; disagreements discussed in a workshop
Conflict of interest declarationsCollected from every team member before responses are opened
OutputFindings report and the list of changes to the RFP

15.2 Findings register

Question IDFinding (Example)Respondents supportingDecision for the RFPRFP requirement affected
Q-COM-001Per-transaction pricing is the most common model; two respondents offer fixed fees4 of 6Ask for both models in the pricing schedulePricing schedule (RFP section 9)
Q-TEC-002Two of the five validator models in use are supported by only one respondent6 of 6 reported the same support patternMake validator replacement an option in the RFPMAN-, FR-, IMP-
Q-MKT-002Acquiring is usually bought separately5 of 6Buy acquiring in a separate procurement; the RFP keeps Lot 1 (platform and implementation) and Lot 2 (managed service) and names the acquirer as an interfaceScope section 3 and interface list of the RFP
Q-DEL-001Realistic delivery is 14 to 20 months6 of 6Keep 15-month target with a pilot milestone at month 7IMP-
[Q-ID][Finding][n of N][Decision][RFP ID]

15.3 Market sounding log

DateRespondentType of contactAttendeesNotes reference
YYYY-MM-DD (Example)Respondent AFollow-up conversation, 60 minutes@solution-architect, @procurement-leadNotes file RFI-NOTE-01
YYYY-MM-DD[Respondent][Type][Attendees][Reference]

Record every contact so that equal treatment can be shown later. Feed the findings into the Request for Proposal (business/rfp), the evaluation criteria of the Vendor Evaluation Scorecard (business/vendor-evaluation-scorecard), and the requirement IDs bidders will answer in the RFP Compliance Matrix (business/rfp-compliance-matrix).

16. Glossary and references

16.1 Glossary

TermMeaning in this RFI
RFIRequest for Information: a non-binding enquiry to learn about the market
RFPRequest for Proposal: a formal invitation to submit binding proposals that will be evaluated
RespondentAn organisation that answers this RFI
Rough order of magnitudeA cost range for budgeting, not an offer
LotA separately awarded part of a procurement
Single point of contactThe only person respondents may contact about the RFI

16.2 References

ReferenceVersion or dateUse
ISO/IEC/IEEE 41062, Software engineering: Life cycle processes: Software acquisition2024 (Edition 2), published 2024-10-10Acquirer preparation activities that the RFI supports
Directive 2014/24/EU on public procurement, EUR-LexArticles 40 and 41; consolidated text, check before useEU preliminary market consultation and prior involvement
Procurement Act 2023 (UK), legislation.gov.ukSections 16 and 17; check the revised textUK preliminary market engagement and notice
Federal Acquisition Regulation (US), acquisition.govMarket research and exchanges with industry; check the current FAR Overhaul textUS federal RFIs
[Applicable procurement law or internal procurement policy][Version]Rules for market consultation
[Organisation strategy or business case][Version]Objectives in section 3

Standard and licence note

Structure aligned with the acquirer's preparation and supplier identification activities in ISO/IEC/IEEE 41062:2024, Software engineering: Life cycle processes: Software acquisition. The standard is copyrighted and is referenced by name only; no text, tables or definitions from it are reproduced, and all wording, questions and the worked example are original. The EU, UK and US procurement pointers cite article, section and part numbers only. This is a documentation format, not legal or procurement advice: check the procurement law, rules and policies that apply to you, which take precedence, and the current official version of the standard. Template licence: MIT.