Change Order and Variation Template (FIDIC, NEC4, AIA)
Construction change order or variation: instruction, cause, valuation build-up, time impact, approvals, running contract sum
Anleitung: Use it for each change to a construction contract, from instruction or notice to approval. Fill the notice dates and contract mechanism first, then the valuation and time impact. The main pitfall is missing a contractual time bar because notice dates were not recorded.
Vorschau
Change Order / Variation: [Variation number and title]
A record of one change to a construction contract: the instruction or request, the reason, the valuation, the time impact and the approvals, with a running summary of the contract sum. The fields map to the change mechanisms of three widely used contract families: FIDIC 2017 second editions (Clause 13, Variations and Adjustments, reprinted with amendments in 2022), NEC4 Engineering and Construction Contract compensation events (core clause 6), and the AIA change order form G701-2017 in the US. Replace every
[bracketed]value and every row marked Example. This is a documentation format, not legal or contractual advice: your signed contract, its particular conditions and amendments govern, so check them and a qualified professional.
Document control
| Field | Value |
|---|---|
| Change number | [VO-007] |
| Title | [Two additional rooflights over the reading room] |
| Project and contract | [Project name; contract form and edition, for example FIDIC Red Book 2017 2nd ed. 2022 reprint / NEC4 ECC Option A / AIA A201-2017] |
| Contract term used | [Variation / compensation event / change order / construction change directive] |
| Version | [1.0] |
| Status | [Raised / Priced / Under review / Approved / Rejected / Withdrawn] |
| Owner | [Contract administrator or project manager, @name] |
| Last updated | YYYY-MM-DD |
| Classification | [Commercial in confidence] |
Revision history
| Version | Date | Author | Change summary |
|---|---|---|---|
| 0.1 | YYYY-MM-DD | [@name] | Raised from client request |
| 1.0 | YYYY-MM-DD | [@name] | Example: Priced, time impact assessed, approved |
1. Origin and instruction
| Field | Value |
|---|---|
| Initiated by | Example: Client, to improve daylight in the reading room |
| Route | [Instruction / request for proposal / contractor's notice / directive] |
| Contract mechanism | Example: FIDIC 2017 Red Book Sub-Clause 13.3.1, Variation by Instruction |
| Instruction or notice reference | Example: EI-031 |
| Date of instruction or event | YYYY-MM-DD |
| Date contractor became aware | YYYY-MM-DD |
| Date of contractor's notice or response | YYYY-MM-DD |
| Linked RFI or drawing revision | Example: RFI-042; drawing FHL-MPA-01-R1-DR-A-00410 rev C02 |
1.1 Description of the change
Example: Add two rooflights, 1.2 m by 2.4 m, over the reading room (grid C-D/4-5), with steel trimmers to the roof structure. Omit the standard roof deck at those openings, 2 x 1.2 m x 2.4 m = 5.76 m2.
1.2 Mechanism by contract family
| Contract family | How a change is started | How it is priced and agreed | Main clauses (numbers only) |
|---|---|---|---|
| FIDIC 2017 (Red, Yellow, Silver) | Engineer's (or Employer's) instruction, or request for a proposal first | Contractor submits particulars; valued under the measurement and valuation rules; Engineer agrees or determines | 13.1 right to vary, 13.2 value engineering, 13.3.1 by instruction, 13.3.2 by request for proposal, 12.3 valuation (Red Book), 3.7 agreement or determination, 20.2 claims |
| NEC4 ECC | Project Manager's instruction changing the Scope (clause 14.3), giving a compensation event under 60.1(1); other events under 60.1 | Contractor's quotation of changes to Prices and Completion Date; assessed on Defined Cost plus Fee and the Accepted Programme; Project Manager accepts or assesses | 60.1, 61, 62, 63, 64, 65, 66 |
| AIA (US) | Owner, contractor and architect agree a change order; or the owner directs a construction change directive when price or time is not yet agreed | Change order states agreed adjustment to contract sum and time; directive is later converted to a change order | A201-2017 Article 7; forms G701-2017 (change order), G714-2017 (construction change directive) |
2. Reason and classification
| Field | Value |
|---|---|
| Cause | [Client request / design development / design error or omission / unforeseen ground or existing conditions / regulatory change / contractor proposal] |
| Responsible party (contractual view) | [Client / contractor / shared, with clause reference] |
| Scope effect | [Addition / omission / substitution / change of sequence or method] |
| Affects health and safety? | Example: Yes, new roof openings; RAMS-FHL-011 and the construction phase plan updated |
| Affects the BIM or design model? | Example: Yes, architecture and structure models revised |
3. Valuation
| Ref | Item | Basis | Quantity | Unit | Rate | Amount |
|---|---|---|---|---|---|---|
| V1 (Example) | Labour, roof trades | Daywork or cost | 96 | h | 32.50 | 3,120.00 |
| V2 (Example) | Rooflight units, 1.2 x 2.4 m | Supplier quotation | 2 | nr | 2,850.00 | 5,700.00 |
| V3 (Example) | Steel trimmers and fixings | Supplier quotation | 1 | item | 1,240.00 | 1,240.00 |
| V4 (Example) | Mobile elevating work platform | Plant hire | 4 | day | 145.00 | 580.00 |
| V5 (Example) | Roofing subcontractor, upstands and flashings | Subcontract quotation | 1 | item | 3,600.00 | 3,600.00 |
| Subtotal additions | 14,240.00 | |||||
| V6 (Example) | Overheads and profit at 8% | Contract percentage | 1,139.20 | |||
| Total additions | 15,379.20 | |||||
| O1 (Example) | Omit standard roof deck | Contract rate | 5.76 | m2 | 68.00 | -391.68 |
| O2 (Example) | Overheads and profit at 8% on omission | Contract percentage | -31.33 | |||
| Total omissions | -423.01 | |||||
| Net value of this change | 14,956.19 |
Labour V1: 3 operatives, 4 days, 8 hours a day, 96 hours in total.
4. Time impact
| Field | Value |
|---|---|
| Programme used | Example: Accepted programme rev 6, updated to the date of instruction |
| Activities affected | Example: Roof deck zone 2, roof membrane zone 2, internal ceiling reading room |
| Gross delay to the affected path | Example: 3 working days |
| Mitigation | Example: Rooflight install resequenced with membrane works; 1 day recovered |
| Net effect on completion date | Example: 2 working days |
| Extension of time requested | Example: 2 working days (FIDIC Sub-Clause 8.5 / NEC4 change to Completion Date / AIA contract time adjustment) |
| Effect on key dates or sectional completion | [None / detail] |
5. Review and approval
| Role | Name | Decision | Value approved | Time approved | Date |
|---|---|---|---|---|---|
| Contractor's commercial manager | [@name] | Submitted | 14,956.19 | 2 days | YYYY-MM-DD |
| Cost consultant | [@name] | Example: Recommended | 14,956.19 | 2 days | YYYY-MM-DD |
| Contract administrator / Engineer / Project Manager | [@name] | Example: Agreed | 14,956.19 | 2 days | YYYY-MM-DD |
| Client | [@name] | Example: Approved | 14,956.19 | 2 days | YYYY-MM-DD |
Approval limits: [state who may approve changes up to which value, from the client's delegation of authority].
6. Contract sum summary
| Item | Amount |
|---|---|
| Original contract sum | Example: 8,400,000.00 |
| Approved changes before this one (VO-001 to VO-006) | Example: 126,450.00 |
| This change (VO-007) | 14,956.19 |
| Approved changes to date | 141,406.19 |
| Revised contract sum | 8,541,406.19 |
| Approved changes as a share of the original sum | 1.68% |
| Pending changes not yet approved | [Amount and count] |
7. Attachments and links
- Instruction or directive: [reference]
- Contractor's quotation or particulars: [reference]
- Marked-up drawings and model revision: [references]
- Programme extract showing the time impact: [reference]
- Related records: request for information (
construction/rfi-log), change register (project/change-control), daily site reports (construction/daily-site-report) for any daywork records.
Standard and licence note
Based on the publicly described structure of the FIDIC 2017 second editions (reprinted with amendments in November 2022) Clause 13 and Sub-Clause 20.2, the NEC4 Engineering and Construction Contract core clause 6 (compensation events), and AIA documents A201-2017, G701-2017 and G714-2017, as checked in October 2026. These contracts are copyrighted: this template names clause numbers and uses original wording only. Official text: FIDIC, purchase or licensed access at fidic.org/bookshop; NEC, at neccontract.com; AIA, at aiacontracts.com. Check your signed contract, particular conditions and amendments; this is not legal or contractual advice. Template licence: MIT.
Ähnliche Vorlagen
BIM Execution Plan Template (ISO 19650)
ISO 19650 BIM execution plan: roles, EIR response, CDE workflow, naming and status codes, level of information need, TIDP and MIDP
BauwesenConstruction Phase Plan Template (CDM 2015, OSHA 1926)
Construction phase plan: dutyholders, site rules, significant hazards, Schedule 3 risks, welfare, emergency, incident reporting, inspections
BauwesenDaily Site Report Template (Construction)
Construction daily report: weather, labour and hours, plant, progress against programme, deliveries, inspections, safety events, delays