Integration plan: thesis, IMO, gantt, gun-jumping rules, Day 1 checklist, TSA exits, finance, people, customers, synergy tracking, 100-day review

Finanzen, Anlage & RechnungswesenVollständigIntegration practice; EU Merger Regulation, HSR Act; IFRS 3 and ASC 805 (names only)andintegration100dayplan

Anleitung: Use it from signing to Day 100 after completion to run the integration of an acquired business. Fill the deal thesis, integration approach by function and the Day 1 readiness checklist first, then the TSA exit plans and the synergy baseline. The main pitfall is acting as owner before clearance (gun-jumping) or reporting synergies as achieved when only a plan is approved.

Vorschau

M&A Integration 100-Day Plan: [Acquirer] and [Target]

A post-merger integration plan covering the period from signing to Day 100 after completion: deal thesis and synergy targets, integration approach, governance through an integration management office, the timeline, pre-completion rules, Day 1 readiness, transitional services, finance integration, people, customers, operations and IT, synergy tracking, risks, communications and the 100-day review. It follows common integration practice; merger control and acquisition accounting are referenced by law and standard name only. The worked example completes "Project Heron": Corvid Commerce Group plc (fictional) acquires Tallow Lane Logistics GmbH (fictional) from Marlow Ridge Holdings AG (fictional); every figure is invented. Replace every [bracketed] value and every row marked Example. This is a document format, not financial, investment, tax, legal or accounting advice. Obtain the standard or law for the normative text.

Document control

FieldValue
Document ID[PMI-2027-001]
Project code name[Project name]
Acquirer[Legal name]
Target[Legal name and entities]
Seller[Legal name]
Signing dateYYYY-MM-DD
Completion date (Day 1)YYYY-MM-DD
Day 100YYYY-MM-DD
Version[0.1]
Status[Draft / Approved by steering committee / Active / Closed]
Owner (integration lead)[@integration-lead]
Executive sponsor[@sponsor]
Approvers/reviewers[@ceo], [@cfo], [@target-managing-director]
Last updatedYYYY-MM-DD
Classification[Confidential; clean team restrictions apply before completion]

Approvals

RoleNameDecisionDate
Integration lead[@integration-lead][Prepared]YYYY-MM-DD
Executive sponsor[@sponsor][Approved]YYYY-MM-DD
Integration steering committee[@ceo] (chair)[Approved Day 1 plan and 100-day targets]YYYY-MM-DD

Revision history

VersionDateAuthorChange
0.1YYYY-MM-DD[@integration-lead]First draft at signing
0.5YYYY-MM-DD[@integration-lead]Day 1 readiness checklist complete after clearance
1.0YYYY-MM-DD[@integration-lead]Approved at completion
1.1YYYY-MM-DD[@integration-lead]Day 30 update

Contents

1. Deal thesis, objectives and synergy targets

ItemProject Heron (Example)
Deal thesisAdd warehouse management software and fulfilment services to Corvid's commerce platform, so Corvid's merchants can buy storefront, checkout and fulfilment from one provider
PriceEnterprise value EUR 22.0m (11.6x diligence adjusted EBITDA of EUR 1.90m)
FundingEUR 12.0m drawn under Corvid's existing EUR 20,000k RCF (maturing 2028-06-30) plus EUR 9.6m cash on hand; pro forma leverage 1.64x against the 3.00x covenant (QoE section 11.1); liquidity headroom EUR 26.85m, below the EUR 35,000k treasury minimum under a board-approved exception to 2027-06-30; FY2027 budget, which excludes Heron, reset in FIN-010
What must not breakService to Tallow Lane's top 20 customers; the warehouse operations in Hamburg and Coventry; key product engineers
What must changeExit from seller group systems within the TSA periods; Corvid financial controls and reporting from the first month
Cost synergiesRun-rate EUR 0.8m a year by end of 2028
Revenue synergiesRun-rate revenue EUR 1.0m (contribution EUR 0.525m) by end of 2028
One-off integration costsEUR 1.125m over 2027 and 2028, excluding TSA fees (EUR 216k), retention (EUR 150k, PPL-001) and deferred maintenance capex (EUR 100k, OPS-007), which are tracked separately

Integration objectives for the first 100 days (Example):

  1. Complete Day 1 with no loss of service, payments or payroll.
  2. Keep every top 20 customer and every one of the 6 named key people.
  3. Put Corvid's financial controls, delegation of authority and reporting calendar in place by the second month-end close.
  4. Approve exit plans for every TSA service, with dates inside the TSA terms.
  5. Action EUR 0.2m of run-rate cost synergies (25% of target) and launch the first cross-sell offer.

2. Integration approach and scope

FunctionApproachTarget stateTiming
Product and engineering (Example)PreserveTallow Lane product team stays intact; roadmap integration with Corvid checkoutJoint roadmap by Day 90
Sales (Example)PartialSeparate sales teams; joint account plans for shared merchants; cross-sell incentivesFrom Day 30
Warehouse operations (Example)Preserve, then consolidate UK siteCoventry site merged into a shared third-party logistics site serving Corvid's UK merchantsDecision by Day 100; move in 2028
Finance (Example)AbsorbCorvid ledger, close calendar, controls, treasuryReporting from January close; ledger migration by 2027-10
HR and payroll (Example)AbsorbCorvid HR system and payroll providersPayroll off seller system by 2027-10
IT infrastructure (Example)AbsorbCorvid identity, email, endpoint and networkWithin TSA-002 term
Legal entity structure (Example)Preserve for nowTallow Lane Logistics GmbH and Tallow Lane UK Ltd remain separate subsidiariesReview in 2028

The degree of integration follows the thesis. Here the value lies in the product and its customers, so the product team and customer-facing operations are preserved, while support functions that do not differentiate the business are absorbed into Corvid's. A different thesis, such as cost consolidation in a mature market, would integrate far more deeply and quickly.

3. Governance and the integration management office

BodyMembersCadenceDecides
Steering committee (Example)Corvid CEO (chair), CFO, CTO, Tallow Lane MD, integration leadWeekly to Day 30, then fortnightlyScope, budget, organisation, synergy targets, red risks
IMO (Example)Integration lead, PMO, finance analystDaily stand-up to Day 10, then weeklyPlan changes within budget, interdependencies, reporting
Workstreams (Example)Joint leads from both companiesWeeklyTasks and milestones within their scope

Rules for the IMO:

  • Each workstream has one lead from Corvid and one from Tallow Lane. Joint ownership signals respect for the acquired business and gives access to knowledge that is not written down.
  • Workstreams report weekly on milestones, risks and synergy actions, using red, amber and green against dates, not against effort.
  • The IMO keeps one RAID log (project/raid-log) and one decision log. Decisions made in workstream meetings that affect another workstream go to the IMO before they take effect.
  • Integration costs are tracked against a separate budget so that the business-as-usual forecast of the target stays clean and the post-investment review can compare costs with the approved case.

4. Timeline

MilestoneDate (Example)Day count
Signing2026-11-20Before completion
Conditions satisfied (larger customer's change-of-control consent; no merger filing required and NSI assessment closed, per counsel)2026-12-18Before completion
Completion (Day 1)2027-01-04Day 1
Day 302027-02-02Day 30
Day 602027-03-04Day 60
Completion accounts delivered by buyer (60 days under the SPA)2027-03-05Day 61
Day 902027-04-03Day 90
Day 100 review2027-04-13Day 100
TSA-002 ends (IT service desk, network, identity)2027-07-036 months
TSA-001 ends (ERP and payroll)2027-10-039 months
TSA-003 ends (Hamburg office space)2028-01-0312 months

Day counts start at completion as Day 1: Day 30 is 29 days after 2027-01-04, which is 2027-02-02; Day 100 is 99 days after, which is 2027-04-13.

5. Rules before completion

Integration planning between signing and completion must respect merger control rules. Under the EU Merger Regulation (Council Regulation (EC) No 139/2004), a notifiable concentration may not be implemented before notification and clearance, and national regimes and the US Hart-Scott-Rodino Act (15 U.S.C. 18a) impose similar waiting periods. Breaching them (gun-jumping) can lead to fines. Counsel should approve the planning protocol, and the IMO should apply it.

Example: Project Heron needs no merger filing. The parties' turnover is far below the EU Merger Regulation thresholds and the German GWB section 35 thresholds (see the Due Diligence Request List (finance/due-diligence-request-list), section 11), UK merger control is voluntary and its thresholds are not met, and there is no US nexus. The rules below still apply: until completion Corvid and Tallow Lane are independent competitors for some merchants, so general competition law on information exchange and coordination continues to bind both.

Allowed before completionNot allowed before completion
Planning Day 1 and the 100-day plan using public and clean team informationDirecting the target's pricing, customers, suppliers or hiring
Interviewing target managers about their organisation with counsel's protocolJoint sales calls or coordinated bids
Preparing systems, bank accounts and contracts that take effect at completionMoving staff, merging teams or sharing systems
SPA covenants that protect value (ordinary course of business, consent for material decisions as agreed with counsel)Exchanging customer-level pricing, margins or pipelines outside the clean team

Where foreign investment screening applies, for example under the UK National Security and Investment Act 2021 or national regimes in EU member states, completion must also wait for that approval. The clearance dates set Day 1; do not commit external dates, such as customer announcements, until all conditions are satisfied.

6. Day 1 readiness

IDItemOwnerTest before Day 1Status
D1-001 (Example)Seller cash pool terminated and balances settled at completion from the price[@treasury-lead]Funds flow memorandum agreed with seller and banks[Ready]
D1-002 (Example)New bank accounts for both target entities opened at Corvid's banks, with payment mandates and signatories[@treasury-lead]Test payment and receipt on each account[Ready]
D1-003 (Example)Customers informed of new bank details with call-back verification to prevent payment fraud[@commercial-lead]Letter approved; call-back script tested[Ready]
D1-004 (Example)Payroll for January runs on the seller system under TSA-001[@hr-lead]Parallel run of December payroll[Ready]
D1-005 (Example)Insurance cover from Corvid's programme from completion, including cyber and directors and officers[@legal-lead]Broker confirmation of cover and run-off of seller policies[Ready]
D1-006 (Example)Delegation of authority for target managers effective at completion[@cfo]Matrix approved by Corvid board[Ready]
D1-007 (Example)Board changes and register filings for both entities[@legal-lead]Resolutions signed in escrow[Ready]
D1-008 (Example)Controlled access between networks: no direct connection until cyber assessment complete[@it-lead]Access via managed collaboration tenant only[Ready]
D1-009 (Example)Day 1 communications to employees, customers, suppliers and media[@comms-lead]Messages approved; spokespeople briefed[Ready]
D1-010 (Example)Key person retention letters signed[@hr-lead]6 of 6 signed[Ready]
D1-011 (Example)Opening balance sheet cut-off procedures at the completion date[@group-controller]Cut-off instructions issued; stock count scheduled[Ready]
D1-012 (Example)Seller trade marks and domains used by the target: licence or transfer in place[@legal-lead]Signed agreement[Ready]

How to run Day 1 readiness:

  • Hold a go or no-go review with all workstream leads two business days before completion. Every item is either ready, has a workaround approved by the IMO, or blocks completion.
  • Staff a Day 1 command centre with named contacts for payments, payroll, IT access and customer questions, and keep it open for at least the first two weeks. The Hypercare Plan (ops/hypercare-plan) gives a structure.
  • Treat the change of bank details as a fraud risk. Criminals exploit acquisitions to send false payment instructions; tell customers how changes will be confirmed and never accept changes by email alone.

7. Transitional services

IDService from Marlow RidgeTermMonthly fee (EUR k)Total (EUR k)Exit planExit owner
TSA-001 (Example)ERP, finance ledger hosting and payroll processing9 months to 2027-10-0312108Migrate ledger to Corvid ERP; move payroll to Corvid providers in DE and UK[@finance-systems-lead]
TSA-002 (Example)IT service desk, network, identity and email6 months to 2027-07-03848Move users to Corvid identity and email; new network contracts[@it-lead]
TSA-003 (Example)Office space in the Hamburg head office12 months to 2028-01-03560Move to a Corvid office or a new lease[@facilities-lead]
Total (Example)216

Check: 9 x 12 = 108; 6 x 8 = 48; 12 x 5 = 60; total 216.

IDReverse service to Marlow RidgeTermMonthly fee (EUR k)Total (EUR k)
RTSA-001 (Example)Warehouse software and support for the seller's retail division6 months424

TSA management rules:

  • Each service has a description, service levels, a fee basis, a term, an extension option with notice period and price, and named contacts on both sides. Ambiguous scope is the main cause of disputes.
  • Review TSA performance and exit progress at each steering committee. Start migration work in the first month; data extraction and testing usually take longer than planned.
  • Agree data handling: the seller processes the target's personal and financial data under the TSA and must return or delete it at exit. Record the data processing terms with counsel.
  • Track TSA fees in the integration budget, separate from synergy costs, so that extensions are visible.

8. Finance integration

IDActivityOwnerDeadline (Example)Status
FIN-001 (Example)Opening balance sheet at the completion date with cut-off procedures[@group-controller]Day 20[Open]
FIN-002 (Example)Report January results in the Corvid group reporting pack, using a mapping from the seller ledger[@group-controller]February close, working day 8[Open]
FIN-003 (Example)Corvid close calendar from the February close: target reports by working day 5[@group-controller]March close[Open]
FIN-004 (Example)Completion accounts and working capital adjustment against the peg of EUR 750k[@fin-lead]2027-03-05[Open]
FIN-005 (Example)Purchase price allocation: identify and value intangible assets (customer relationships, technology, brand), provisional at the half-year[@technical-accounting-lead]Half-year report 2027[Open]
FIN-006 (Example)Align accounting policies (development cost capitalisation, revenue recognition for annual licences)[@technical-accounting-lead]Day 60[Open]
FIN-007 (Example)Map target processes to Corvid key controls; remediate gaps found in diligence[@internal-control-lead]Day 90[Open]
FIN-008 (Example)Treasury: target included in Corvid cash management and FX hedging policy[@treasury-lead]Day 30[Open]
FIN-009 (Example)Intercompany agreements between Corvid entities and the target, with transfer pricing support[@tax-lead]Day 90[Open]
FIN-010 (Example)Add the target to the rolling forecast and reset the FY2027 outlook (the approved budget excludes Heron), including the RCF drawing, interest, covenant forecast and liquidity against the treasury minimum[@fpa-lead]Day 30[Open]
FIN-011 (Example)Allocate goodwill to cash-generating units for the annual impairment test[@technical-accounting-lead]Before year end 2027[Open]

Points to note:

  • Acquisition accounting under IFRS 3 Business Combinations (or FASB ASC Topic 805 for US GAAP reporters) allows provisional amounts that are finalised within a measurement period of up to one year from the acquisition date. Use that period to complete the valuation of acquired intangibles; do not use it to correct errors in the opening balance sheet that could have been avoided at Day 1.
  • The policy alignment items mirror the QoE adjustments QOE-ADJ-003 and QOE-ADJ-004. Applying Corvid's policies may change the target's reported results compared with the seller's figures; explain this in the first management report so readers do not mistake a policy change for underperformance.
  • Use the working capital peg and net debt definitions from the SPA exactly as agreed. The QoE schedules (finance/quality-of-earnings-scope) are the starting point for the completion accounts.
  • Related templates: Delegation of Authority Matrix (finance/delegation-of-authority-matrix), Treasury Policy (finance/treasury-policy), Month-End Close Checklist (finance/month-end-close-checklist), Rolling Forecast (finance/rolling-forecast), Impairment Test Memo (finance/impairment-test-memo), Transfer Pricing Local File (finance/transfer-pricing-local-file).

9. People and organisation

IDActivityOwnerDeadline (Example)
PPL-001 (Example)Retention arrangements for 6 named key people: EUR 150k in total, half paid at 6 months and half at 12 months after completion[@hr-lead]Signed before Day 1
PPL-002 (Example)Leadership structure for the target announced on Day 1; second-level roles confirmed by Day 30[@sponsor]Day 30
PPL-003 (Example)Map Tallow Lane grades and benefits to Corvid frameworks; no changes to terms in the first 100 days[@hr-lead]Day 90
PPL-004 (Example)Inform and consult the Hamburg works council before any operational change that requires it[@hr-lead]Before each change
PPL-005 (Example)Culture assessment and joint team sessions for product, sales and warehouse teams[@hr-lead]Day 60
PPL-006 (Example)Pulse survey of target employees[@hr-lead]Day 45 and Day 90

Retention payments are a cost of the acquisition. Under acquisition accounting, payments for future service are usually treated as post-combination expense rather than part of the price; confirm the treatment with the technical accounting lead.

Consultation duties vary by country. In Germany, the Works Constitution Act (Betriebsverfassungsgesetz) section 111 requires information and consultation with the works council on significant operational changes in undertakings with, as a rule, more than 20 employees eligible to vote. In the UK and other countries, collective consultation and information rules apply to redundancies and transfers. The UK site consolidation in SYN-001 needs a consultation plan approved by counsel before any announcement. Check local law for each change.

10. Customers and commercial

IDActivityOwnerDeadline (Example)
COM-001 (Example)Personal calls from senior leaders to the top 20 customers on Day 1 and Day 2[@commercial-lead]Day 2
COM-002 (Example)Change-of-control consent obtained from the two top-10 customers identified in diligence (DDF-003)[@commercial-lead]Larger contract before completion (SPA condition); smaller by Day 30
COM-003 (Example)No changes to account managers, price lists or service levels before Day 100[@commercial-lead]Day 100
COM-004 (Example)Joint offer: Tallow Lane fulfilment for Corvid merchants (SYN-101), piloted with 15 merchants[@commercial-lead]Launch Day 60
COM-005 (Example)Joint offer: Corvid checkout for Tallow Lane customers (SYN-102)[@commercial-lead]Design by Day 100
COM-006 (Example)Monitor churn, renewals and support tickets weekly against the pre-deal baseline[@commercial-lead]Weekly

Customer messages should answer the questions customers actually ask: will my contract, contact person, price and service change, and whom do I call? Answer "no change" where that is true and give dates where it is not. The QoE revenue analysis provides the renewal dates and concentration figures that set the priority of calls.

11. Operations and IT

IDActivityOwnerDeadline (Example)
OPS-001 (Example)Cyber security assessment of the target estate, closing the open critical penetration test finding[@it-lead]Day 30
OPS-002 (Example)Identity and email migration design and pilot (TSA-002 exit)[@it-lead]Design Day 60; pilot Day 100
OPS-003 (Example)ERP migration plan and data migration rules (TSA-001 exit)[@finance-systems-lead]Approved Day 90
OPS-004 (Example)Hosting consolidation of the Tallow Lane product onto Corvid cloud contracts (SYN-002)[@it-lead]First workloads by Day 100
OPS-005 (Example)Carrier procurement: combined volumes tendered (SYN-003)[@ops-lead]Contracts signed Day 90
OPS-006 (Example)Coventry site consolidation business case (SYN-001)[@ops-lead]Decision Day 100
OPS-007 (Example)Deferred maintenance found in diligence: conveyor replacements in Hamburg[@ops-lead]Ordered Day 60
OPS-008 (Example)Business continuity plans updated for new contacts and suppliers[@ops-lead]Day 30

Use the Cutover Plan (project/cutover-plan) and the Data Migration Strategy (architecture/data-migration-strategy) for the ERP and identity moves. Plan each migration with a rehearsal and a rollback point, and schedule finance migrations away from month-end and year-end closes.

12. Synergy tracking

Stages: Identified (in the deal case), Validated (owner agrees value and plan), Actioned (decision implemented, for example a contract signed or a role removed), Realised (visible in the ledger against the baseline).

IDSynergyTypeRun-rate target (EUR k)Actioned by Day 100 (EUR k)One-off cost (EUR k)OwnerStage
SYN-001 (Example)Consolidate Coventry warehouse into a shared third-party UK logistics siteCost2250400[@ops-lead]Validated
SYN-002 (Example)Hosting consolidation on Corvid cloud contractsCost15050175[@it-lead]Actioned (part)
SYN-003 (Example)Combined carrier procurementCost1756525[@ops-lead]Actioned (part)
SYN-004 (Example)Corvid shared finance and HR absorb the finance and HR standalone roles assumed in the QoE (105 + 60)Cost1650225[@cfo]Validated
SYN-005 (Example)Software licences: duplicate tools cancelledCost858510[@it-lead]Actioned
Cost total (Example)800200835
SYN-101 (Example)Tallow Lane fulfilment sold to Corvid merchants: revenue 625 at 60% contributionRevenue3750175[@commercial-lead]Validated
SYN-102 (Example)Corvid checkout sold to Tallow Lane customers: revenue 375 at 40% contributionRevenue1500115[@commercial-lead]Identified
Revenue total (contribution) (Example)5250290

Checks: cost run-rate 225 + 150 + 175 + 165 + 85 = 800; actioned 50 + 65 + 85 = 200, which is 25% of 800; one-off costs 400 + 175 + 25 + 225 + 10 + 175 + 115 = 1,125, the integration budget in section 1. Revenue synergies: 625 + 375 = 1,000 revenue; contribution 625 x 60% + 375 x 40% = 375 + 150 = 525. SYN-004 removes the standalone roles the QoE added to adjusted EBITDA (QOE-ADJ-008), so it is a genuine synergy against the deal case rather than a reversal of a diligence finding.

Value of the synergy case, for comparison with the price premium:

NPVsynergies=∑t=1TSt×(1−τ)−Ct(1+r)t\text{NPV}_{\text{synergies}} = \sum_{t=1}^{T} \frac{S_t \times (1 - \tau) - C_t}{(1 + r)^t}

where StS_t is the synergy benefit in year tt, τ\tau the tax rate, CtC_t the one-off cost after tax in year tt and rr the discount rate used in the valuation. Use the same phasing and discount rate as the valuation report; the integration plan should not create a second, different synergy value.

Tracking rules:

  • Fix the baseline before Day 1: the cost lines and volumes against which each synergy is measured. Without a baseline, every saving is arguable.
  • Report run-rate actioned and in-year realised separately. A saving actioned in month 9 delivers only a quarter of its run-rate in that year.
  • Finance validates realised amounts against the ledger. Workstream leads propose; finance confirms.
  • Keep dis-synergies visible, such as customers lost because of the deal or higher costs in a combined contract, and net them in the report.

13. Risks and dependencies

IDRiskLikelihoodImpactMitigationOwner
RISK-001 (Example)A top-10 customer terminates under its change-of-control clauseMediumHigh (EUR 0.725m revenue across two contracts)Consent before completion for the larger contract; executive sponsor per account[@commercial-lead]
RISK-002 (Example)ERP migration slips beyond the TSA-001 termMediumMedium (extension fees, control gaps)Start migration design in month 1; negotiate extension option price now[@finance-systems-lead]
RISK-003 (Example)Key engineers leave after the announcementMediumHigh (product roadmap)Retention letters (PPL-001); clear product leadership on Day 1[@hr-lead]
RISK-004 (Example)Cyber weakness in the target estate exploited during integrationLowHighControlled access (D1-008); assessment OPS-001 before any network connection[@it-lead]
RISK-005 (Example)UK site consolidation delayed by consultation and lease termsMediumMedium (SYN-001 timing)Consultation plan and landlord engagement started by Day 60[@ops-lead]
RISK-006 (Example)Integration absorbs target management and growth slowsMediumHighProduct and sales preserved (section 2); integration roles staffed by Corvid where possible[@sponsor]
DependencyFromToDate needed (Example)
Identity migration before ERP migrationOPS-002OPS-0032027-07
Completion accounts before opening balance sheet is finalFIN-004FIN-0052027-03
Consultation completed before SYN-001 announcementPPL-004OPS-006Before decision

How to keep the risk view useful:

  • Review the top risks at every steering committee and change the ratings only with evidence, such as a customer renewal signed or a key engineer resigning. A risk table that never changes is not being managed.
  • Link each risk to the diligence finding that raised it (for example RISK-001 to DDF-003 and RISK-002 to DDF-004), so the post-investment review can test whether diligence identified the right issues.
  • Quantify impact in the units of the deal case: EBITDA, revenue at risk or one-off cost. This lets the steering committee compare mitigation spend with the value it protects.
  • Escalate any dependency that slips past its date to the IMO the same week; most integration delays are dependency failures between workstreams rather than failures inside one workstream.

14. Communications

AudienceMessageChannelSenderWhen (Example)
Target employeesWhy Corvid acquired Tallow Lane, what changes and what does not, who leadsTown hall in Hamburg and Coventry, follow-up FAQCorvid CEO and Tallow Lane MDDay 1, 09:00 local
Corvid employeesDeal rationale and how teams will work togetherAll-hands and intranetCorvid CEODay 1
Top 20 customersContinuity of service and contacts; new bank details with verificationPersonal call, then letterTallow Lane MD, account managersDay 1 to Day 2
Other customersSame, by letter and emailEmail and website noticeCommercial leadDay 1
Suppliers and carriersNew invoicing details, continuityLetterProcurement leadDay 1 to Day 5
Works councilInformation on the transaction and planned stepsMeetingHR lead and MDDay 1 and before each change
Media and investorsCompletion announcementPress releaseCorvid communicationsDay 1

Use the Communication Plan (project/communication-plan) for the full calendar. Prepare a Q&A for managers and update it weekly with the questions employees actually ask.

15. Milestones, KPIs and the 100-day review

CheckpointOutcomes expected (Example)
Day 30 (2027-02-02)Day 1 issues closed; January results reported; second-level organisation confirmed; cyber assessment complete; treasury integrated
Day 60 (2027-03-04)Second close on Corvid calendar; policy alignment decided; first cross-sell pilot launched; completion accounts ready to issue on 2027-03-05
Day 90 (2027-04-03)Key controls mapped; TSA exit plans approved; carrier contracts signed
Day 100 (2027-04-13)Review held; plan for months 4 to 12 approved
KPITarget at Day 100 (Example)Actual
Top 20 customers retained20 of 20[n]
Key people retained6 of 6[n]
Cost synergies actioned (run-rate)EUR 200k[EUR k]
Integration spend against budget to dateWithin 10%[%]
TSA services with approved exit plan3 of 3[n]
Monthly reporting on time (working day 5)2 of 2 closes from February[n]
Employee pulse scoreAt or above pre-deal baseline[score]

The 100-day review report answers:

  1. Is the deal thesis still valid? What has changed since signing?
  2. Which objectives in section 1 were met, and which were not and why?
  3. What is the status of synergies by stage, and the forecast run-rate by year end and end of 2028?
  4. Which risks have materialised, and which new ones appeared?
  5. What changes to scope, organisation, budget or timeline are needed for months 4 to 12?
  6. Which lessons should the acquirer's M&A playbook record?

After the review, move from the IMO cadence to monthly steering committee meetings, and plan the formal Post-Investment Review (finance/post-investment-review) at 12 to 24 months to compare outcomes with the approved investment case.

16. Glossary and references

16.1 Glossary

TermMeaning
Day 1The completion date, when ownership transfers
IMOIntegration management office, the team that coordinates the integration
Gun-jumpingImplementing a transaction or exercising control before required clearances
TSATransitional services agreement: the seller provides services to the target for a limited period
Reverse TSAThe target provides services to the seller after completion
Run-rate synergyAnnual value of a synergy once fully in place
Realised synergySynergy visible in the accounts against the agreed baseline
Dis-synergyCost or revenue loss caused by the transaction
Measurement periodPeriod after an acquisition during which provisional acquisition accounting amounts can be finalised
Purchase price allocationAllocation of the consideration to identifiable assets and liabilities, with the residual as goodwill

16.2 References

ReferenceVersion or dateUse
Council Regulation (EC) No 139/2004 (EU Merger Regulation)Consolidated text on EUR-LexStandstill before clearance
Hart-Scott-Rodino Antitrust Improvements Act, 15 U.S.C. 18aCurrentUS waiting period
National Security and Investment Act 2021 (UK)GOV.UK guidance updated 2026-07-15UK investment screening
Betriebsverfassungsgesetz (Germany) section 111Current textWorks council consultation
Gesetz gegen Wettbewerbsbeschränkungen (GWB, Germany) section 35Current textWhy no German merger filing is needed in the example
IFRS 3 Business CombinationsName onlyAcquisition accounting and measurement period
FASB ASC Topic 805, Business CombinationsTopic number onlyUS GAAP equivalent
Valuation Report (finance/valuation-report)[VAL-2026-002]Synergy case and price
Quality of Earnings Scope (finance/quality-of-earnings-scope)[QOE-2026-001]Peg, net debt, standalone costs
Due Diligence Request List (finance/due-diligence-request-list)[DDR-2026-001]Findings DDF-001 to DDF-005
Post-Investment Review (finance/post-investment-review)RelatedBenefits review at 12 to 24 months

Standard and licence note

Based on public law cited by name and number (EU Merger Regulation, Hart-Scott-Rodino Act, UK National Security and Investment Act 2021, German Works Constitution Act) and on common integration practice, with IFRS 3 and FASB ASC Topic 805 cited by name and number only; no text from those standards, or from any adviser's integration methodology, is reproduced or paraphrased. IFRS is a trade mark of the IFRS Foundation. The structure, checklists, formulas and worked example are original. Corvid Commerce Group plc, Tallow Lane Logistics GmbH, Marlow Ridge Holdings AG and all figures are fictional. Check the current official texts and take advice in each jurisdiction before use. This is a document format, not financial, investment, tax, legal or accounting advice. Template licence: MIT.