MBA Supply Chain Network Design Concept Card Template

Network design card: facility location MILP, Solver set-up, 15-network enumeration, price of a service promise, centre of gravity, pooling, landed cost

MBA und Business SchoolVollständigGeoffrion and Graves 1974; Hakimi 1964; Maister 1976; Eppen 1979; ICC Incoterms 2020networkdesigncardmath

Anleitung: Use it when a decision changes the number, place or role of warehouses, plants or depots, or compares near-shore and far-shore sources. Fill demand by region, lane costs and the service promise first, then compare every network and price the promise. The main pitfall is leaving inventory out, which opens too many sites.

Vorschau

Supply Chain Network Design Concept Card: [Your course or network]

A concept card for the supply chain elective: how many facilities a company needs, where to put them, which customers each one serves, and how the answer trades off fixed facility cost, inbound and outbound transport, inventory and delivery time. It covers the facility location model, the centre of gravity as a first screen, risk pooling and the square-root law, pipeline inventory and landed cost for near-shore versus far-shore sourcing. It builds on the core inventory card (safety stock, Little's Law): read mba/mba-inventory-card first, because this card uses its notation and does not re-teach it; the linear programming and Solver basics are in mba/mba-decision-analytics-guide. It is for MBA students in a supply chain elective and for managers in retail, distribution, manufacturing and service parts who face a network decision. One example is fully solved, one is half solved and one is left for you, and the self-test answers sit in a separate key. Source basis: Weber (1909) for location theory, Hakimi (1964) for the median problem, Geoffrion and Graves (1974) for the optimisation model, Maister (1976) and Eppen (1979) for inventory pooling, all written up in original words with fictional data (Northfield Outdoor Co. and Corvane Robotics are invented companies). Replace every [bracketed] value and every row marked Example.

Document control

FieldValue
Course or project[Supply chain elective, network design sessions / client project]
Learner or analyst[Your name]
Network analysed[Northfield distribution network, five regions, four candidate sites (fictional) / your network]
Demand data and year[Units by region, YYYY, forecast version]
Cost data[Freight rate cards dated YYYY-MM-DD, site cost quotes, holding cost rate approved by finance]
Service promise[Next-day within 450 road km / your promise]
Tool[Excel with Solver / Python with scipy / a network design package]
Reviewed by[Study group / tutor / mentor]
Last updatedYYYY-MM-DD
Version[0.1]

When to use it

One-sentence rule: use this card whenever you must decide how many stocking or production points to run, where, and which customers each serves, and the answer changes fixed cost, transport, inventory and delivery time together.

SituationModel on this cardKey output
First screen for a new warehouse or plant regionCentre of gravityA starting point on the map, not an answer
Choose among candidate sites with known costsFacility location model (enumeration or mixed-integer programme)Open sites, assignments, total cost
Consolidate or split stocking pointsRisk pooling and the square-root lawSafety stock change
Near-shore versus far-shore supplier or plantLanded cost with pipeline and safety stockCost per unit delivered
A new delivery promise (next-day, same-day)Location model with a service constraintThe cost of the promise
An acquisition with an overlapping networkLocation model on the combined sitesSites to close, synergy estimate
Use whenDo not use alone when
Demand by region and cost by lane can be estimatedDemand is shifting fast between channels (stores to online) without a forecast
The decision horizon is several yearsThe question is next week's truck routes (vehicle routing)
Candidate sites are a manageable listReal estate, labour availability or incentives dominate: add them as constraints or scores
Costs are roughly linear in volumeStrong economies of scale in a site (automation) need step costs

The idea in plain language

A distribution network is a set of trade-offs. Adding a facility brings stock closer to customers, so outbound freight per unit falls and delivery gets faster. But every facility has a fixed cost (rent, staff, systems), and every facility holds its own safety stock. Splitting one pool of stock into several separate pools raises the total buffer, because each pool must cover its own demand swings; the swings no longer cancel out (Eppen 1979). Inbound transport (from the port or factory to the facilities) usually rises a little with more sites, because full trucks must go to more places.

Total cost across the number of facilities is often flat near the optimum: in Worked example A the best one-, two-, three- and four-site networks differ by about 2% in cost (USD 7.537m to 7.690m). That is good news and a warning. Good news, because other criteria (delivery promise, risk, labour markets, expansion room) can decide among near-equal options. A warning, because a small error in a freight rate can flip the ranking, so the robustness check matters more than the optimum.

Location theory goes back to Weber (1909), who placed a plant to minimise weighted transport distance. Hakimi (1964) proved that, on a network, a location minimising total weighted distance can always be found among the nodes, a result he later extended to several facilities; that turned location into a combinatorial choice. Geoffrion and Graves (1974) built the mixed-integer model that modern network design software still descends from: open sites, assign flows, minimise fixed plus variable cost, subject to capacity and service.

The centre of gravity is the demand-weighted average location. It is quick and visual, but it minimises squared distance, not distance, and ignores roads, costs and real estate, so treat it as a screening tool. Landed cost extends the logic to sourcing: the cheapest factory price is not the cheapest delivered unit once freight, duties, pipeline inventory and safety stock for a long lead time are added.

Formulas and notation

Facility location model (uncapacitated form, after Geoffrion and Graves 1974). Open site jj (yj=1y_j = 1) at fixed cost fjf_j; serve region ii from site jj (xij=1x_{ij} = 1) at cost cijc_{ij} per unit:

min⁡∑jfj yj+∑i∑jdi cij xijs.t.∑jxij=1 ∀i,xij≤yj ∀i,j,yj∈{0,1}, xij≥0\min \sum_{j} f_j\,y_j + \sum_{i}\sum_{j} d_i\,c_{ij}\,x_{ij} \quad \text{s.t.} \quad \sum_{j} x_{ij} = 1 \ \forall i, \qquad x_{ij} \le y_j \ \forall i, j, \qquad y_j \in \{0, 1\}, \ x_{ij} \ge 0

With capacities KjK_j, add ∑idi xij≤Kj yj\sum_i d_i\,x_{ij} \le K_j\,y_j. With a service promise, set xij=0x_{ij} = 0 for every lane longer than the promised distance or time.

Centre of gravity (demand-weighted mean location):

xˉ=∑iwixi∑iwi,yˉ=∑iwiyi∑iwi\bar{x} = \frac{\sum_i w_i x_i}{\sum_i w_i}, \qquad \bar{y} = \frac{\sum_i w_i y_i}{\sum_i w_i}

The point that minimises total weighted straight-line distance ∑iwi∥(x,y)−(xi,yi)∥\sum_i w_i \lVert (x, y) - (x_i, y_i) \rVert is found by the iterative method of Weiszfeld (1937); it can differ from the centre of gravity and can sit on a heavy demand point.

Risk pooling. Serving regions with weekly demand standard deviations σi\sigma_i and pairwise correlation ρik\rho_{ik} from one facility, and the square-root law for nn equal, independent markets (Maister 1976):

σpooled=∑iσi2+2∑i<kρik σi σk,SS=z σpooledL,SSn=SS1n\sigma_{\text{pooled}} = \sqrt{\sum_i \sigma_i^2 + 2\sum_{i<k}\rho_{ik}\,\sigma_i\,\sigma_k}, \qquad SS = z\,\sigma_{\text{pooled}}\sqrt{L}, \qquad SS_n = SS_1\sqrt{n}

Pipeline inventory (Little's Law applied to goods in transit) and landed cost:

Ipipeline=D×T,Landed cost per unit=p (1+τ)+F+h (p Ipipeline+cL SS)DI_{\text{pipeline}} = D \times T, \qquad \text{Landed cost per unit} = p\,(1 + \tau) + F + \frac{h\,(p\,I_{\text{pipeline}} + c_L\,SS)}{D}
SymbolMeaningUnit
ii, jjDemand region, candidate siteindex
did_i, DDAnnual demand of region ii, total annual demandunits per year
fjf_j, KjK_jFixed annual cost and capacity of site jjcurrency per year, units per year
cijc_{ij}Inbound plus outbound transport and handling cost per unit from site jj to region iicurrency per unit
yjy_j, xijx_{ij}Open site (0 or 1), share of region ii served from jjnone
wiw_i, (xi,yi)(x_i, y_i)Weight (usually volume, or volume x rate) and coordinates of region iiunits, km
σi\sigma_i, ρik\rho_{ik}Weekly demand standard deviation of region ii, correlation between regionsunits per week, none
zz, LLStandard normal quantile of the cycle service level, replenishment lead timenone, weeks
TTTransit timeyears (or weeks with weekly demand)
pp, τ\tau, FFPurchase price, duty rate, freight per unitcurrency per unit, %, currency per unit
hh, cLc_LHolding cost rate, landed unit cost used to value safety stock% per year, currency per unit

Excel equivalents. Road distance: =1.2*SQRT((x1-x2)^2+(y1-y2)^2). Total cost: =SUMPRODUCT(fixed,open)+SUMPRODUCT(demand_matrix,cost_matrix,assign_matrix). Pooled SD: =SQRT(SUMSQ(sigmas)) for independent regions. Safety stock: =NORM.S.INV(CSL)*pooled_SD*SQRT(L). Centre of gravity: =SUMPRODUCT(w,x)/SUM(w).

Solver set-up (Excel, Simplex LP): objective = total cost cell, minimise; variable cells = the 4 open flags and the 20 assignment cells; constraints: open flags binary, assignment cells binary, each region's assignment row sums to 1, each assignment cell ≤\le its site's open flag. Add a capacity row per site, and fix lanes beyond the service distance at 0, when those apply.

Assumptions and limits

AssumptionWhat breaks itWhat to do
Demand by region is known for the planning horizonChannel shift, new markets, growthRun scenarios (low, base, high) and keep options that are good in all
Transport cost is linear in distance and volumeRate tables with breaks, backhaul, fuel surchargesUse lane rates from rate cards; test fuel scenarios
Inventory follows the square-root lawCorrelated demand across regions, different service levels, different product mixes by regionPool with the correlation formula; size stock by item, not by site
Fixed cost is fixedLeases with break clauses, step costs for automationModel steps as extra binary variables
Each region is served from one siteSplit deliveries, store-to-online fulfilmentAllow fractional xijx_{ij} or add a second echelon
Costs are today'sLabour inflation, tariffs, carbon pricesSensitivity tables on the two or three largest cost lines
Static, one-period modelSeasonality, ramp-upModel peak weeks for capacity and the average for cost

Tariffs and duty rates change by product and origin and are policy decisions; take them from the official tariff schedule of the importing country on the date of the study, and check them again before a decision. The trade terms that decide who pays freight, insurance and duties are usually written with the ICC Incoterms rules: as of October 2026 the current set is Incoterms 2020, eleven rules in force since 1 January 2020 (check https://iccwbo.org/business-solutions/incoterms-rules/ before you rely on it).

How managers use it

  • Price the delivery promise. Marketing wants next-day delivery everywhere; the model says what it costs (Worked example A: USD 0.153m a year, 2.0% of network cost). The decision becomes a margin question, not a debate.
  • Consolidation programmes. Closing stocking points releases fixed cost and safety stock (Worked example B); the model shows what happens to freight and service.
  • Merger integration. Overlapping networks after an acquisition are a classic synergy source; the location model on the combined sites gives a defensible estimate (see mba/mba-supply-chain-guide).
  • Near-shoring and dual sourcing. Landed cost with pipeline and safety stock often narrows or reverses a far-shore price advantage (Exercise C); resilience adds a further argument (mba/mba-supply-chain-resilience-card).
  • Capital budgeting. A new facility is an investment: the annual saving from the model is the cash flow line in the NPV (mba/mba-npv-irr-card and finance/capex-request).
  • Emissions. Transport emissions grow with tonne-km; network models can carry an emissions line beside cost. Logistics emissions accounting commonly follows ISO 14083:2023 (published March 2023) and the GLEC Framework (version 3.0, September 2023, aligned with ISO 14083; later versions are reported, so check smartfreightcentre.org for the current one) before you report figures.

Choosing the method

Pick the lightest method that answers the question: a centre of gravity to frame a search, enumeration when candidates are few, a mixed-integer model when they are many, and a landed-cost comparison when the question is about sources rather than warehouses.

Worked example A (fully solved): Northfield distribution network

Situation (Example, fictional). Northfield Outdoor Co. serves five regions from leased distribution centres and wants to redesign its network. Imports land at a port at map position (100, 200). Coordinates are in km on a map grid; road distance is 1.2 times straight-line distance.

RegionPosition (km)Annual demand (thousand units)Weekly demand SD (units)
R1 North(100, 800)3002,700
R2 West(150, 300)4503,600
R3 Central(500, 500)6004,200
R4 East(850, 600)3503,000
R5 South(600, 100)3002,700
Candidate sitePosition (km)Fixed cost (USD m a year)Road km from portInbound USD per unit
S1(200, 650)0.70553.20.664
S2(450, 450)0.95516.10.619
S3(800, 550)0.65939.11.127
S4(500, 150)0.60483.70.580

Cost rules: outbound USD 0.40 per unit plus USD 0.006 per unit per road km (=0.40+0.006*road_km); inbound full trucks USD 0.0012 per unit per road km. Safety stock at each site covers a 97% cycle service level (zz = 1.8808, =NORM.S.INV(0.97)) over a 2-week replenishment lead time, on the pooled SD of the regions it serves, valued at USD 40 a unit with a 25% holding rate. Regions are independent. The service promise is next-day delivery, which means a site within 450 road km.

A1. Road distance (km) and outbound cost per unit (USD).

SiteR1 NorthR2 WestR3 CentralR4 EastR5 South
S1 km / USD216.3 / 1.698424.3 / 2.946402.5 / 2.815782.3 / 5.094816.1 / 5.297
S2 km / USD594.0 / 3.964402.5 / 2.81584.9 / 0.909512.6 / 3.476456.9 / 3.142
S3 km / USD892.0 / 5.752835.7 / 5.414365.0 / 2.59084.9 / 0.909590.9 / 3.946
S4 km / USD915.9 / 5.895456.9 / 3.142420.0 / 2.920684.1 / 4.505134.2 / 1.205

A2. All 15 networks. Each region is served by the open site with the lowest inbound plus outbound cost per unit. Costs in USD m a year; components are rounded, so a total can differ from their sum by 0.001.

Open sites (Example)FixedOutboundInboundSafety stock holdingTotalDemand within next-day reach
S2 + S31.6004.2621.4160.2597.53770.0%
S20.9505.1601.2390.1967.54552.5%
S2 + S3 + S42.2003.6811.4050.3157.60185.0%
S2 + S41.5504.5791.2270.2547.61067.5%
S1 + S2 + S32.3003.5821.4300.3157.62785.0%
S1 + S21.6504.4811.2520.2547.63767.5%
S1 + S2 + S3 + S42.9003.0011.4180.3717.690100.0%
S1 + S2 + S42.2503.9001.2400.3117.70182.5%
S1 + S3 + S41.9504.2041.4650.3157.934100.0%
S1 + S31.3505.0261.6290.2718.27685.0%
S1 + S41.3005.4621.2730.2718.30782.5%
S3 + S41.2505.6141.3520.2598.47562.5%
S40.6006.8721.1610.1968.82945.0%
S10.7006.8961.3280.1969.11967.5%
S30.6507.2182.2540.19610.31747.5%

A3. Reading the result.

  • The cheapest network is S2 + S3 at USD 7.537m: S2 (central) serves R1, R2, R3 and R5, S3 serves R4 East. A mixed-integer model without the inventory line (scipy.optimize.milp or Solver) opens the same two sites at USD 7.278m; adding back the USD 0.259m of safety stock holding gives the same total.
  • One central site (S2) costs only USD 0.008m more. The cost curve is flat: the best network with one, two, three and four sites costs 7.545, 7.537, 7.601 and 7.690.
  • Safety stock rises with the number of sites: 19,578 units with one site (pooled SD 7,360.7 a week, =1.8808*SQRT(2700^2+3600^2+4200^2+3000^2+2700^2)*SQRT(2)) and 37,056 units with four.
  • The price of the promise. Only two networks reach every region next day. The cheaper is all four sites at USD 7.690m: next-day delivery everywhere costs USD 0.153m a year more than the cheapest network, 2.0% of network cost. If next-day service for R1 North and R5 South (30% of demand) adds more than that in margin, open all four.

A4. Centre of gravity as a screen. Weights are annual demand in thousands.

QuantityResultExcel
xˉ\bar{x}437.5 km=SUMPRODUCT(w,x)/SUM(w)
yˉ\bar{y}457.5 km=SUMPRODUCT(w,y)/SUM(w)
Nearest candidateS2 at (450, 450)=SQRT((450-437.5)^2+(450-457.5)^2) = 14.6 km away
Weighted straight-line distance from the centre of gravity607.7 million unit-km=SUMPRODUCT(w,SQRT((x-437.5)^2+(y-457.5)^2))/1000
Point that minimises weighted distance (Weiszfeld)(500, 500), the R3 Central demand point: 582.5 million unit-kmIterate, or check the vertex condition

The centre of gravity pointed at S2, which is the backbone of the best networks. But the distance-minimising point is R3 itself: R3 carries a weight of 600 against a combined pull of 325.18 from the other regions, so the optimum sits on it. Neither point accounts for inbound freight from the port, fixed costs or the service promise; that is what the location model adds.

Worked example B (half solved): Corvane Robotics spare-parts depots

Situation (Example, fictional). Corvane Robotics keeps a critical drive-module kit for its warehouse robots in four regional depots. Each depot holds 500 kits of safety stock for the same service level, and the four regions have equal, independent demand. A kit is valued at USD 2,500 and the holding rate is 20% a year. Operations proposes one central depot with express courier delivery.

  1. Square-root law: safety stock with one depot = 2,000 x 1/4\sqrt{1/4} = [ ] kits (=2000*SQRT(1/4)).
  2. With two depots: [ ] kits (=2000*SQRT(2/4)).
  3. Annual holding cost of safety stock: four depots USD [ ]; one depot USD [ ]; two depots USD [ ] (=kits*2500*0.2).
  4. Now suppose demand in the four regions is correlated with ρ\rho = 0.3 (the same customers' robots run the same seasonal peaks). Pooled safety stock with one depot = 5004+4×3×0.3500\sqrt{4 + 4 \times 3 \times 0.3} = [ ] kits (=500*SQRT(4+12*0.3)); saving versus four depots = [ ]%.
  5. A robot down at a customer's warehouse costs the customer about USD 9,000 an hour (Example). Courier delivery from one central depot takes 6 hours longer on average than from a regional depot. Which costs, risks and contract terms (service-level agreement penalties) would you add before recommending consolidation?

Exercise C (unsolved): near-shore or far-shore for a backpack line

Northfield sources a backpack line, 52,000 units a year (Example, fictional). Two offers:

ItemFar-shore supplierNear-shore supplier
Price per unit (FOB)USD 62.00USD 70.00
Duty rate (Example; check the tariff schedule)12%0% (trade agreement)
Freight per unitUSD 3.10USD 1.40
Transit time6 weeks1 week
Replenishment lead time (order to receipt)10 weeks3 weeks
Weekly demand SD250 units250 units

Holding cost rate 20% a year; pipeline stock is valued at the purchase price and safety stock at the landed unit cost (price plus duty plus freight); cycle service level 95%.

  1. Compute the landed unit cost (price plus duty plus freight) for each option.
  2. Compute pipeline inventory (units and annual holding cost) for each, using Little's Law with weekly demand.
  3. Compute safety stock (units and annual holding cost) for each.
  4. Compute the total annual cost and the cost per unit. Which option is cheaper, and by how much a year?
  5. Name two factors outside this calculation (one strategic, one risk) that could change the decision, and say which Incoterms rule you would want in each contract and why.

Connections to other cards

  • mba/mba-inventory-card (core): safety stock, service levels and Little's Law, used here for pooling and pipeline stock.
  • mba/mba-decision-analytics-guide (core): linear programming and Solver, the engine of the location model.
  • mba/mba-supply-chain-guide: where network design sits in the elective, with Fisher's (1997) efficient versus responsive logic.
  • mba/mba-bullwhip-effect-card: lead times set by the network drive order amplification.
  • mba/mba-sourcing-procurement-card: supplier selection and contracts after the landed-cost screen.
  • mba/mba-supply-chain-resilience-card: single-site and single-source networks look cheapest until a disruption.
  • mba/mba-npv-irr-card and finance/capex-request: a facility decision is an investment decision.
  • mba/mba-relevant-costs-card: only costs that change with the network belong in the comparison (sunk lease costs do not).

Common mistakes and misconceptions

  • Treating the centre of gravity as the answer. It minimises squared distance, ignores costs and real estate, and can point to a lake. Use it to find candidates.
  • Forgetting inventory. A model with only fixed and transport costs opens too many sites; each extra site adds safety stock.
  • Applying the square-root law blindly. It assumes equal, independent markets and the same service level; with correlated demand the saving shrinks (Worked example B).
  • Mixing time units. Annual demand with weekly standard deviations, or fixed costs per month with transport per year.
  • Ignoring the inbound leg. A site near customers but far from the port can lose on inbound freight (S3 in Worked example A).
  • Comparing suppliers on price. Landed cost includes duty, freight, pipeline and safety stock, and the far-shore price advantage can disappear (Exercise C).
  • Over-trusting the optimum. When options are within 1 to 2% of each other, the ranking can flip with a freight rate; present the flat region and the robust choice.
  • Forgetting the service promise. The cheapest network may not reach customers on time; price the promise explicitly.
  • Hard-coding today's duties and rates. Tariffs and freight change; date every rate and re-run before a decision.
  • Including sunk costs. A lease already signed and not cancellable does not belong in the comparison.

Self-test

  1. Name the four cost lines that change with the number of distribution centres and the direction each moves as you add sites.
  2. Why is the total cost curve often flat across the number of sites, and what does that imply for the recommendation?
  3. A company consolidates nine equal, independent stocking points with 1,000 units of safety stock each into one. What safety stock does the square-root law predict?
  4. A supplier ships 2,000 units a week with a 5-week transit time. How many units are in the pipeline?
  5. Two customers sit on a line at km 0 (weight 100) and km 400 (weight 300). Where is the centre of gravity, and where is the point that minimises total weighted distance?
  6. A unit costs USD 50 at the factory, duty is 8% and freight USD 2. What is the landed unit cost before inventory?
  7. In the facility location model, what does the constraint xij≤yjx_{ij} \le y_j do?
  8. How do you compute the cost of a delivery promise with the model?
  9. Why does correlation between regions reduce the value of pooling?
  10. What did Hakimi (1964) show that made location a combinatorial choice?
  11. Which of the following belongs in a network comparison: (a) a non-cancellable lease on an existing site, (b) the severance cost of closing a site, (c) the safety stock change?
  12. Interleaving: which card first? (a) Orders from a distributor swing more than store sales. (b) How many depots for spare parts? (c) How much of a seasonal jacket to buy before the season?

My notes and next steps

ItemMy entry
Confidence with network design (1 = lost, 5 = could teach it)[ ]
A network I know that looks over- or under-built, and why[ ]
Questions for my study group or professor[ ]
Mistakes logged in mba/mba-error-log[Date and short description]
Next review date (spacing: +2 days, +1 week, +1 month)YYYY-MM-DD
Next card to study[mba/mba-sourcing-procurement-card / mba/mba-supply-chain-resilience-card]

Sources and further reading

  • Weber, A. (1909). Über den Standort der Industrien. Mohr. English translation: Theory of the Location of Industries (1929), University of Chicago Press.
  • Weiszfeld, E. (1937). Sur le point pour lequel la somme des distances de n points donnés est minimum. Tôhoku Mathematical Journal, 43. English translation by F. Plastria (2009), Annals of Operations Research, 167(1), 7-41.
  • Hakimi, S. L. (1964). Optimum locations of switching centers and the absolute centers and medians of a graph. Operations Research, 12(3), 450-459.
  • Geoffrion, A. M., and Graves, G. W. (1974). Multicommodity distribution system design by Benders decomposition. Management Science, 20(5), 822-844.
  • Maister, D. H. (1976). Centralisation of inventories and the "square root law". International Journal of Physical Distribution, 6(3), 124-134.
  • Eppen, G. D. (1979). Effects of centralization on expected costs in a multi-location newsboy problem. Management Science, 25(5), 498-501.
  • Fisher, M. L. (1997). What is the right supply chain for your product? Harvard Business Review, March-April 1997.
  • International Chamber of Commerce. Incoterms 2020 (in force from 1 January 2020), https://iccwbo.org/business-solutions/incoterms-rules/ (as of October 2026; check for a newer edition).
  • Textbooks (further reading, by name only): Chopra and Meindl, Supply Chain Management: Strategy, Planning, and Operation; Simchi-Levi, Kaminsky and Simchi-Levi, Designing and Managing the Supply Chain; Watson, Lewis, Cacioppi and Jayaraman, Supply Chain Network Design.
  • Open resource: MIT OpenCourseWare, ESD.273J Logistics and Supply Chain Management (Fall 2009), https://ocw.mit.edu/courses/esd-273j-logistics-and-supply-chain-management-fall-2009/.

Answer key

Worked example B. (1) 1,000 kits. (2) 1,414.21 kits. (3) Four depots: 2,000 x 2,500 x 0.2 = USD 1,000,000; one depot USD 500,000; two depots USD 707,106.78. (4) 5007.6500\sqrt{7.6} = 1,378.40 kits; saving 621.60 kits, 31.08% (against 50% with independent demand). (5) Add the customer downtime cost (6 extra hours x USD 9,000 per incident, times the expected number of urgent incidents), courier cost per shipment, service-level agreement penalties and credits, the risk of a single depot outage (fire, strike, IT), and customer contract terms on response time. A two-depot network or a forward-stocking scheme for the largest customers is a common compromise.

Exercise C. (1) Far: 62 x 1.12 + 3.10 = USD 72.54 (=62*(1+0.12)+3.10); near: 70 + 1.40 = USD 71.40. (2) Weekly demand 1,000. Far pipeline 6,000 units, holding 6,000 x 62 x 0.20 = USD 74,400; near 1,000 units, USD 14,000. (3) Far safety stock =NORM.S.INV(0.95)*250*SQRT(10) = 1,300.37 units, holding 1,300.37 x 72.54 x 0.20 = USD 18,865.78; near =NORM.S.INV(0.95)*250*SQRT(3) = 712.24 units, holding USD 10,170.82. (4) Far total 72.54 x 52,000 + 74,400 + 18,865.78 = USD 3,865,345.78 (USD 74.33 a unit); near USD 3,736,970.82 (USD 71.86 a unit). Near-shore is cheaper by USD 128,374.96 a year even though its price is USD 8 higher. (5) Strategic: speed to market and the option to reorder in season (worth more for innovative products, Fisher 1997). Risk: concentration and disruption risk of the far-shore route, and duty changes. Incoterms: for example FCA or FOB when you control main carriage and want to manage freight, or DAP or DDP when you want the supplier to carry delivery risk to your site; which rule fits depends on who can manage carriage and customs better. Check the rule text in Incoterms 2020.

Self-test.

  1. Fixed facility cost rises; outbound transport falls; inbound transport usually rises a little; safety stock rises.
  2. The rising and falling cost lines offset each other near the optimum. Several networks are near-equal, so choose on service, risk and flexibility, and show the sensitivity.
  3. 9,000 x 1/9\sqrt{1/9} = 3,000 units.
  4. 2,000 x 5 = 10,000 units.
  5. Centre of gravity: (100 x 0 + 300 x 400) / 400 = km 300. The weighted-distance minimiser is km 400, at the heavier customer: moving from 400 towards 0 adds 300 units of weighted distance per km and saves only 100.
  6. 50 x 1.08 + 2 = USD 56.00.
  7. It prevents assigning a region to a site that is not open.
  8. Solve without the promise, then remove every lane that breaks it and solve again; the difference in total cost is the price of the promise.
  9. Pooling works because high and low demands cancel out; when regions move together, they cancel less.
  10. That, on a network, a location minimising total weighted distance exists among the nodes (later extended to several facilities), so the search is over a finite set of candidates.
  11. (b) and (c). The non-cancellable lease is sunk and stays the same in every option; severance and inventory change.
  12. (a) mba/mba-bullwhip-effect-card. (b) This card, risk pooling. (c) The newsvendor model in mba/mba-inventory-card.

Revision history

VersionDateAuthorChange summary
0.1YYYY-MM-DD[Your name]First draft from the template
0.2YYYY-MM-DD[Your name]Example: Replaced Northfield data with own regions and rate cards, service promise priced

Standard and licence note

Based on the published location and supply chain literature, chiefly Weber (1909), Hakimi (1964), Geoffrion and Graves (1974), Maister (1976) and Eppen (1979), with the ICC Incoterms rules named as a dated fact only; all text, data and examples are original and fictional, and textbooks are named as further reading only. This template is not affiliated with or endorsed by any business school, publisher, standards body or course. Check your course materials for the notation your professor uses and the official sources for current duty rates and trade terms. Template licence: MIT.