ISMS Annual Calendar Template (ISO/IEC 27001 Recurring Activities)

12-month ISMS calendar: fixed dates, 30 recurring activities with owners and evidence, month view, Gantt chart, size tiers, rescheduling rules

SGSI e ISO/IEC 27001CompletaISO/IEC 27001:2022 + Amd 1:2024 clauses 8.1, 9.1 to 9.3 (cited only); ISO/IEC 17021-1:2015annualcalendardiagram

Cómo usar: Use it at the start of each ISMS year once the external audit date is known. Fill the fixed dates first and work backwards: internal audit before management review, management review before the external audit. The main pitfall is a calendar that is not in a real scheduling tool with owners and evidence links.

Vista previa

ISMS Annual Calendar: [Organization name], [Year]

Twelve-month plan of the recurring activities that keep the information security management system (ISMS) of [Organization name] running and produce the records an auditor expects: access reviews, risk and policy reviews, awareness and phishing, backup, disaster recovery and continuity tests, penetration testing, supplier reviews, key rotation, internal audit, management review and the external surveillance audit. It supports ISO/IEC 27001:2022 + Amd 1:2024 clauses 6.1, 8.1, 9.1, 9.2 and 9.3 and the operation of the Annex A controls named in each row. Replace every [bracketed] value and every row marked Example.

Document control

FieldValue
Document ID[DOC-ISMS-032]
Version[2027 v1.0]
Status[Draft / In review / Approved / Superseded]
Owner[@isms-manager]
Approvers/reviewers[@ciso], [@coo]
Last updatedYYYY-MM-DD
Classification[Internal]
Standard and editionISO/IEC 27001:2022 + Amd 1:2024
ISMS year covered[YYYY-MM-DD to YYYY-MM-DD]
External audit dates[Surveillance 1 / Surveillance 2 / Recertification, YYYY-MM-DD]
Certification cycle reference[DOC-ISMS-094, certification cycle plan]
Next scheduled review[Quarterly at the steering committee, next YYYY-MM-DD]

Approvals

RoleNameDecisionDate
ISMS owner[@isms-manager][Prepared]YYYY-MM-DD
Chief information security officer[@ciso][Reviewed]YYYY-MM-DD
Top management[@coo][Approved]YYYY-MM-DD

Revision history

VersionDateAuthorChange
2027 v1.0 (Example)YYYY-MM-DD[@isms-manager]Calendar for the first surveillance year
2027 v1.1 (Example)YYYY-MM-DD[@isms-manager]Incident response exercise moved from November to October so that it finishes before the readiness health check; approved by the CISO
[version]YYYY-MM-DD[@author][Change summary]

Contents

  1. Purpose and planning rules
  2. Fixed dates and dependencies
  3. Activity register
  4. Month-by-month calendar
  5. Calendar chart
  6. Size tiers
  7. Rescheduling and missed activities
  8. Records and evidence
  9. Review of the calendar
  10. References

1. Purpose and planning rules

This calendar schedules every recurring ISMS activity for [Year] so that controls operate at the frequency stated in policies and standards, and so that the records needed for the internal audit, the management review and the external audit are produced in good time.

Planning rules:

  1. Clause sequence. Internal audit (9.2) and the performance report (9.1) are completed before the management review (9.3). The management review is completed before the external audit.
  2. Spread the load. No more than [3] major activities in one month for the same team.
  3. Frequency from the source. Each activity's frequency comes from the policy, standard, contract or risk treatment that requires it; the source is named in the activity register.
  4. One owner, one record. Each activity has one accountable owner and one named record stored in a known location.
  5. Lead time. Reminders go out [10] working days before each activity; external testers and auditors are booked at least [8] weeks ahead.
  6. Freeze periods. Avoid scheduling disruptive tests during [peak trading periods, year-end close or major releases].

2. Fixed dates and dependencies

Fixed pointDate (Example)Set byDependent activities
Surveillance audit 12027-11-15 to 2027-11-17Certification bodyManagement review, internal audit, readiness health check
Management review2027-08-26Top managementInternal audit report, performance report, risk review
Internal audit window2027-06-07 to 2027-07-16Internal audit programme (DOC-ISMS-082)Audit plan, auditor availability
Annual risk assessment2027-04-05 to 2027-04-30Risk methodology (DOC-ISMS-010)Context review, SoA review
Peak business period (freeze)2027-12-01 to 2027-12-31BusinessNo disruptive tests in December
Financial year budget approval2027-10-15FinanceNext year's ISMS budget and test bookings

3. Activity register

IDActivityClause or controlFrequency (source)Months (Example)OwnerEvidence produced
CAL-001 (Example)User access review of in-scope systemsA.5.15, A.5.18Quarterly (access control policy DOC-ISMS-041)Mar, Jun, Sep, Dec[@it-ops-lead]Signed review per system, removal tickets
CAL-002 (Example)Privileged access reviewA.8.2Quarterly (privileged access standard)Mar, Jun, Sep, Dec[@iam-lead]Privileged account list with approvals
CAL-003 (Example)Physical access list reviewA.7.2Quarterly (physical security policy DOC-ISMS-055)Feb, May, Aug, Nov[@facilities-lead]Badge list review record
CAL-004 (Example)Context, interested parties and climate change issue reviewClauses 4.1, 4.2Annual (DOC-ISMS-003)Apr[@isms-manager]Updated context register with review date
CAL-005 (Example)Legal, regulatory and contractual register reviewA.5.31Half-yearly (DOC-ISMS-014)Jan, Jul[@legal-lead]Register version and change log
CAL-006 (Example)Annual risk assessmentClauses 6.1.2, 8.2Annual plus on change (DOC-ISMS-010)Apr[@isms-manager]Risk assessment report (DOC-ISMS-017), updated register
CAL-007 (Example)Risk register and treatment progress reviewClauses 6.1.3, 8.3QuarterlyJan, Apr, Jul, Oct[@isms-manager]Register snapshot, treatment plan status
CAL-008 (Example)Statement of Applicability reviewClause 6.1.3 dAnnual, after risk assessmentMay[@isms-manager]SoA new version or reviewed-unchanged record
CAL-009 (Example)Policy and standard reviewsA.5.1, clause 7.5Annual per document (DOC-ISMS-005)Rolling, peak in MayPolicy ownersApproved versions, review records
CAL-010 (Example)Asset inventory reconciliationA.5.9Half-yearly (DOC-ISMS-012)Mar, Sep[@it-ops-lead]Reconciliation report, variance tickets
CAL-011 (Example)Annual awareness training campaignA.6.3Annual plus at onboarding (security awareness programme)Feb[@awareness-lead]Completion report from the learning platform
CAL-012 (Example)Phishing simulationA.6.3, A.6.8Quarterly (DOC-ISMS-074)Jan, Apr, Jul, Oct[@awareness-lead]Campaign results, follow-up training list
CAL-013 (Example)Competence and training matrix reviewClause 7.2Annual (DOC-ISMS-026)Mar[@hr-lead]Updated matrix, training plan
CAL-014 (Example)Backup restore testA.8.13Quarterly (backup policy DOC-ISMS-061)Feb, May, Aug, Nov[@it-ops-lead]Restore test log entries (DOC-ISMS-071)
CAL-015 (Example)Disaster recovery testA.5.30, A.8.14Annual (ICT readiness plan DOC-ISMS-047)Sep[@it-ops-lead]DR test report, actions
CAL-016 (Example)Business continuity tabletop exerciseA.5.29Annual (DOC-ISMS-121)May[@bc-lead]Exercise report, lessons learned
CAL-017 (Example)Incident response exerciseA.5.24, A.5.26Annual (DOC-ISMS-020)Oct[@incident-manager]Exercise record, updated playbooks
CAL-018 (Example)External penetration testA.8.8, A.8.29Annual and after major changeMar[@security-lead]Test report, remediation tickets
CAL-019 (Example)Vulnerability scanning and remediation reviewA.8.8Monthly scans, monthly review (DOC-ISMS-072)Every month[@vuln-lead]Scan reports, tracker status
CAL-020 (Example)Firewall and network rule reviewA.8.20, A.8.22Half-yearly (DOC-ISMS-063)Jun, Dec[@network-lead]Rule review record, change tickets
CAL-021 (Example)Critical supplier security reviewsA.5.19, A.5.22Annual per critical supplier (DOC-ISMS-066)Feb to Mar[@procurement-lead]Supplier assessments (DOC-ISMS-067), assurance reports
CAL-022 (Example)Cryptographic key rotation and certificate reviewA.8.24Annual rotation, monthly expiry check (DOC-ISMS-070)Jan rotation, monthly check[@platform-lead]Key register updates, rotation tickets
CAL-023 (Example)Log review and monitoring rule tuningA.8.15, A.8.16Monthly review, half-yearly tuning (DOC-ISMS-064)Monthly, tuning in Apr and Oct[@soc-lead]Review sign-off, rule change records
CAL-024 (Example)Metrics collection and performance reportClause 9.1Monthly collection, quarterly report (DOC-ISMS-080)Report in Jan, Apr, Jul, Oct[@isms-manager]Performance report (DOC-ISMS-081)
CAL-025 (Example)Security steering committeeClause 5.1Quarterly (DOC-ISMS-007)Feb, May, Aug (with review), Nov[@ciso]Minutes and action log
CAL-026 (Example)Internal auditClause 9.2Annual coverage of the full ISMS (DOC-ISMS-082)Jun to Jul[@internal-audit]Audit plans, reports (DOC-ISMS-084), findings
CAL-027 (Example)Management reviewClause 9.3Annual minimumAug[@ceo]Minutes (DOC-ISMS-085)
CAL-028 (Example)Surveillance readiness health checkClauses 9 and 10Annual, 6 weeks before external audit (DOC-ISMS-096)Oct[@isms-manager]Health check report
CAL-029 (Example)External surveillance auditCertification cycleAnnual (DOC-ISMS-094)Nov[@isms-manager]CB audit report, findings action plan (DOC-ISMS-093)
CAL-030 (Example)Objectives setting and next-year calendarClauses 6.2, 8.1AnnualDec[@isms-manager]Objectives register, calendar for next year
[CAL-NNN][activity][clause or control][frequency and source][months][@owner][evidence]

4. Month-by-month calendar

Month (2027 Example)Activities (register IDs)Key deliverableWatch point
JanuaryLegal register review (CAL-005), risk register review (CAL-007), phishing (CAL-012), key rotation (CAL-022), Q4 performance report (CAL-024)Q4 performance reportKey rotation completed before certificates enter the 30-day expiry window
FebruaryAwareness campaign (CAL-011), physical access review (CAL-003), restore test (CAL-014), supplier reviews start (CAL-021), steering committee (CAL-025)Awareness completion above 95% by month endNew joiners from January included
MarchAccess reviews (CAL-001, CAL-002), asset reconciliation (CAL-010), competence review (CAL-013), penetration test (CAL-018), supplier reviews end (CAL-021)Penetration test reportTest scheduled outside the release freeze
AprilContext review (CAL-004), annual risk assessment (CAL-006), risk register review (CAL-007), phishing (CAL-012), monitoring tuning (CAL-023), Q1 report (CAL-024)Risk assessment reportContext review completed first, so new issues feed the risk assessment
MaySoA review (CAL-008), policy review peak (CAL-009), physical access review (CAL-003), restore test (CAL-014), BC tabletop (CAL-016), steering committee (CAL-025)Updated SoA and policiesPolicies approved before the internal audit starts
JuneAccess reviews (CAL-001, CAL-002), firewall rule review (CAL-020), internal audit starts (CAL-026)Audit plans issuedAuditees briefed; auditors independent of the areas they audit
JulyLegal register review (CAL-005), risk register review (CAL-007), phishing (CAL-012), Q2 report (CAL-024), internal audit ends (CAL-026)Internal audit reportsFindings logged in DOC-ISMS-086 within 5 working days
AugustPhysical access review (CAL-003), restore test (CAL-014), management review with steering committee (CAL-025, CAL-027)Management review minutesAll clause 9.3 inputs present, including audit results and the performance report
SeptemberAccess reviews (CAL-001, CAL-002), asset reconciliation (CAL-010), DR test (CAL-015)DR test reportRecovery measured against RTO and RPO from the BIA
OctoberRisk register review (CAL-007), phishing (CAL-012), incident exercise (CAL-017), monitoring tuning (CAL-023), Q3 report (CAL-024), readiness health check (CAL-028)Health check reportCorrective actions from the internal audit closed or on track
NovemberPhysical access review (CAL-003), restore test (CAL-014), steering committee (CAL-025), surveillance audit (CAL-029)CB audit reportFindings action plan submitted by the CB's deadline
DecemberAccess reviews (CAL-001, CAL-002), firewall rule review (CAL-020), objectives and next calendar (CAL-030)Objectives and calendar for next yearFreeze period: reviews only, no disruptive tests

Monthly activities not repeated in every row: vulnerability scanning and review (CAL-019), log review (CAL-023), certificate expiry check (CAL-022) and metrics collection (CAL-024).

5. Calendar chart

The chart shows the main annual and quarterly activities for the 2027 example year. Monthly activities are omitted for readability.

6. Size tiers

AspectSmall: Quillmere Analytics Ltd (Example)Medium: Quillmere Health Systems (Example)Large: Quillmere Group (Example)
Profile46 staff (38 employees, 8 contractors), one office plus remote staff, SaaS on one public cloud in two regions320 staff, two offices, one colocation suite2,400 staff, 6 sites in 4 countries, IT and OT, already certified to ISO 9001 and ISO 22301
Who runs the calendarPart-time ISMS manager (0.5 FTE, Head of Engineering Operations) in the team's ticketing toolFull-time ISMS manager with a 3-person security team, GRC tool or shared calendarSecurity office of 14 under the CISO, one group calendar plus site calendars inside the integrated management system
Access reviewsQuarterly for the cloud console, identity provider and code repository (about 6 systems)Quarterly for about 25 systems, monthly for privileged accounts on clinical systemsQuarterly per site, monthly for privileged and OT engineering accounts
Physical reviewsOffice badge list half-yearly; data centres covered by provider assurance reportsQuarterly for offices and the colocation suiteQuarterly per site, including plant control rooms
TestingOne annual penetration test of the SaaS platform; restore tests quarterly; region failover test annuallyAnnual penetration test plus application test before major releases; DR test of the colocation suitePenetration tests rotated across sites, OT assessments per plant, group DR test of the data centre
Internal auditOne auditor (external contractor or a trained colleague outside engineering), 3 to 4 days in one windowInternal audit spread over 6 weeks, auditors from quality and finance trained in ISO 19011Rolling audit programme across 6 sites, integrated with ISO 9001 and ISO 22301 audits
External auditsSurveillance audit once a year at one locationSurveillance audit once a year covering offices and colocationSurveillance audit with site sampling set by the certification body, integrated audit where the CB offers it
PhasingOne calendar for the whole companyOne calendar; separate dates for the colocation suiteGroup calendar for shared activities; site calendars follow the phased certification by site

Small organisations can combine activities in the same week (for example access review and asset reconciliation) to save effort, as long as each produces its own record.

7. Rescheduling and missed activities

SituationRuleApprovalRecord
Activity moved within the same quarterAllowed if the frequency in the source document is still metActivity owner informs the ISMS managerRevision history of the calendar
Activity moved to a later quarterAllowed only with a reason and a new dateCISO approvesRevision history and steering committee minutes
Activity missedTreat as a potential nonconformity: assess the impact on the control and the riskISMS manager assesses; CISO decidesEntry in DOC-ISMS-087 or a recorded rationale
Activity no longer neededRemove only after the source document or risk treatment is changedDocument owner and ISMS managerUpdated source document and calendar

Track completion as a metric: "calendar activities completed in the planned month" is a useful ISMS management indicator in the measurement programme (DOC-ISMS-080).

8. Records and evidence

RecordProvesKept byLocationRetention (Example)
Approved calendar per ISMS yearOperational planning (8.1)ISMS managerDocument management system3 years (one certification cycle)
Planned versus actual trackerActivities happened as planned or were rescheduled with approvalISMS managerGRC tool or calendar export3 years
Activity records (column "Evidence produced" in section 3)Each control operated at its frequencyActivity ownersLocations named in DOC-ISMS-033As set per record in DOC-ISMS-028
Rescheduling approvalsChanges were controlledISMS managerRevision history and minutes3 years
Reminder and booking confirmations for external tests and auditsLead times metActivity ownersE-mail or ticketing1 year

The control evidence matrix (isms/control-evidence-matrix, DOC-ISMS-033) lists the same records per clause and control with the last collection date; update both documents together.

9. Review of the calendar

  • Review progress against the calendar at each quarterly steering committee and record slipped activities.
  • Rebuild the calendar each December for the next year, after the certification body confirms the next audit date.
  • Update the calendar within one month when a new policy, standard, contract or risk treatment adds a recurring activity, or when the scope changes.
  • In a recertification year, bring the internal audit and management review forward so that the full ISMS is covered before the recertification audit (see DOC-ISMS-094).

10. References

ReferenceEditionUse
ISO/IEC 27001:2022 + Amd 1:2024https://www.iso.org/standard/82875.html ; https://www.iso.org/standard/88435.htmlClauses 8.1, 9.1, 9.2, 9.3 and Annex A controls named in the register
ISO/IEC 27002:2022https://www.iso.org/standard/75652.htmlGuidance on operating each control
ISO/IEC 17021-1:2015https://www.iso.org/standard/61651.htmlSurveillance audits at least once a calendar year, recertification before expiry
ISO 19011:2026https://www.iso.org/standard/88984.htmlGuidance for planning internal audits

Related templates: isms/control-evidence-matrix (DOC-ISMS-033), isms/isms-measurement-programme (DOC-ISMS-080), isms/isms-performance-report (DOC-ISMS-081), compliance/internal-audit-program (DOC-ISMS-082), compliance/management-review (DOC-ISMS-085), isms/certification-cycle-plan (DOC-ISMS-094), isms/surveillance-readiness-health-check (DOC-ISMS-096), ops/access-review, isms/phishing-simulation-plan (DOC-ISMS-074), isms/backup-restore-test-log (DOC-ISMS-071), isms/cryptographic-key-register (DOC-ISMS-070), isms/supplier-register (DOC-ISMS-066).

Standard and licence note

Structure aligned with ISO/IEC 27001:2022 + Amd 1:2024 clauses 8.1 and 9.1 to 9.3 and the certification cycle described in ISO/IEC 17021-1:2015. The activities, frequencies, months and dates are original, illustrative examples; the standards ask for planned intervals and leave frequencies to the organization. No ISO or IEC text is reproduced, and you need the official standards to apply the requirements. ISO and IEC standards are copyrighted and sold by ISO, IEC and national standards bodies. Check the current edition and amendments, and your certification body's rules, before use. Template licence: MIT.