Hypercare Plan Template

Post-go-live support: duration, support tiers and rota, daily cadence, severity targets, monitoring, known issues, triage, KPIs, exit criteria, handoff

OperacionesCompletaAWS Prescriptive Guidance (hypercare); Dynamics 365 implementation guidehypercareplan

Cómo usar: Use it for the elevated-support period after a go-live or migration cutover. Fill the business event calendar and exit criteria first, so duration follows what must be proved. The main pitfall is exiting on a calendar date while severity 2 incidents or the first period-end close are still open.

Vista previa

Hypercare Plan: [Solution or release name]

Plan for the period of elevated support that follows a go-live or a migration cutover: scope and duration, the support model and rota, the command centre and daily checkpoint, severity targets and escalation, monitoring focus, known issues and the fix release path, triage, user support, KPIs and daily reporting, exit criteria, the handoff to operations and the closure report. Structure aligned with the hypercare period and handoff described in AWS Prescriptive Guidance for large migrations and with the hypercare and support readiness guidance in the Microsoft Dynamics 365 implementation guide, written for any technology. Replace every [bracketed] value and every row marked Example.

Document control

FieldValue
Document ID[HYP-001]
Solution or release[Solution name] [Release, wave or rollout]
Go-live (end of cutover window)[YYYY-MM-DD HH:MM time zone]
Planned hypercare start[YYYY-MM-DD HH:MM]
Planned hypercare end (target)[YYYY-MM-DD]
Maximum extension without steering approval[Number] business days
Hypercare lead[@hypercare-lead]
Version[0.1]
Status[Draft / Approved / Active / Extended / Closed]
Owner[@service-owner]
Approvers/reviewers[@business-owner], [@programme-director], [@service-desk-manager], [@solution-architect]
Classification[Internal / Confidential]
Last updatedYYYY-MM-DD
Related documents[Cutover plan], [Readiness review], [Operations handover plan], [Known issues log]

Approvals

RoleNameDecisionDate
Receiving service owner[@name][Approve / Approve with conditions / Reject]YYYY-MM-DD
Business owner[@name][Decision]YYYY-MM-DD
Programme director[@name][Decision]YYYY-MM-DD
Service desk manager[@name][Decision]YYYY-MM-DD

Revision history

VersionDateAuthorChange summary
0.1YYYY-MM-DD[@name]First draft
1.0YYYY-MM-DD[@name]Example: Approved before the go-live readiness review
1.1YYYY-MM-DD[@name]Example: Extended by 5 business days to cover the delayed month-end close

Contents

1. Scope, objectives and duration

1.1 Scope

In scopeOut of scope
Example: All processes, interfaces and reports delivered in release 1 for entities DE01 and FR01Legacy system look-up access (supported by the legacy team)
Example: Data issues arising from the migrationNew feature requests (go to the product backlog)
Example: User how-to questions and access requests for the new systemHardware faults on user devices (standard service desk route)
[Item][Item]

1.2 Objectives

IDObjectiveProved by
HYP-OBJ-001 (Example)Stabilise the service so that incident volume trends down to a level the operations team can absorbKPI K-01 and K-02 in section 9
HYP-OBJ-002 (Example)Complete each critical business event once without a severity 1 or 2 incidentBusiness event calendar in 1.3
HYP-OBJ-003 (Example)Transfer working knowledge to the receiving support teamsReverse-shadow results in the operations handover plan
HYP-OBJ-004 (Example)Close or transfer every go-live condition and known issueKnown issues log at exit
[HYP-OBJ-NNN][Objective][Evidence]

1.3 Duration and business event calendar

Hypercare starts when the cutover is signed off (Example: Monday 06:00, T+48h in the cutover plan) and ends when the exit criteria in section 10 are met. For a migration wave of rehosted servers, AWS Prescriptive Guidance describes a hypercare period that typically lasts 1 to 4 days before the migration team transfers the workloads to cloud operations. For an enterprise application, plan to cover every business event in the table below.

EventPlanned dateWhy it mattersCovered?
First full business day (Example)Day 1Volume of logins, access issues, how-to questions[Yes / No]
First overnight batch and interface cycle under real volume (Example)Day 1 nightJob durations and error handling[Status]
First weekly payment run (Example)Day 4Bank file and approval workflow[Status]
First month-end close (Example)Days 15 to 18Accruals, reconciliations, reporting[Status]
First peak trading day (Example)Day 20Performance under peak load[Status]
[Event][Date][Reason][Status]

Example: planned duration 20 business days, which covers the month-end close and the first peak day; target end on day 20.

1.4 Extension rule

Extend hypercare when an exit criterion is not met on the target date. The hypercare lead proposes the extension with the unmet criteria and a plan; the service owner approves up to the maximum in Document control; anything longer goes to the steering committee.

2. Support model and rota

2.1 Support tiers during hypercare

TierWhoHandlesHours
Floor supportSuper-users and floorwalkers at each siteHow-to questions, quick fixes, logging tickets for usersBusiness hours, first 10 days
First lineService desk with hypercare scriptsIntake, categorisation, known-issue matching, access requests[Service desk hours]
Second lineApplication support team, paired with project functional expertsFunctional and data issues, workarounds, configuration fixes[Hours], plus on call
Third lineProject developers, integration and platform engineersCode defects, interface failures, performance[Hours], plus on call for severity 1 and 2
VendorSoftware and platform vendorsProduct defects and platform incidentsPer support contract

2.2 Rota

WeekHypercare leadFunctional expert on callTechnical on callIntegration on callBusiness contact
Week 1 (Example)[@name][@name][@name][@name][@name]
Week 2 (Example)[@name][@name][@name][@name][@name]
Week 3 (Example)[@name][@name][@name][@name][@name]
Week 4 (Example)[@name][@name][@name][@name][@name]

Use the On-call Handbook (ops/on-call-handbook) for paging rules and the Shift Handoff (ops/shift-handoff) record at each shift change.

2.3 RACI

ActivityHypercare leadService deskApplication supportProject teamService ownerBusiness owner
Ticket intake and first responseIRCIAI
Severity assignmentARCCIC
Fix of a code defectCICRAI
Request and implement an emergency changeCICRAC
Approval of an emergency changeCICCAC
Daily checkpoint and reportRCCCAI
Extension or exit decisionRCCCAC

The change manager (or emergency change authority) is responsible for approving an emergency change together with the service owner, as set out in section 6.2; the project team requests and implements it but never approves its own change.

3. Command centre, channels and cadence

ItemArrangement
Command centreExample: Room 4.12 in week 1 and 2, then virtual
User entry pointService desk portal and phone; all issues become tickets, including those raised to floorwalkers
Hypercare ticket tag[HYPERCARE-R1] on every ticket for reporting
Team channel[#hypercare-release-name] for coordination, not for issue intake
Bridge for severity 1[Conference link], opened by the hypercare lead
Status page[Link], updated by the communications lead for incidents with user impact

3.1 Daily cadence

Time (Example)MeetingAttendeesOutput
08:30Triage stand-up (15 min)Hypercare lead, second and third line leadsNew tickets classified, owners set
12:00Business pulse (15 min, weeks 1 and 2)Hypercare lead, super-user leadsSite feedback, training needs
16:30Daily checkpoint (30 min)Hypercare lead, service owner, business owner, project leadsDaily report in section 9, decisions, exit criteria status
WeeklySteering updateProgramme director, sponsorsTrend, risks, extension or exit forecast

Daily checkpoint agenda: incidents by severity since the last checkpoint; open severity 1 and 2 status; KPI trends; business events in the next 48 hours; fixes ready for release; exit criteria status; decisions needed.

4. Severity, targets and escalation

SeverityDefinitionHypercare responseHypercare update intervalTarget to workaround or fixBAU target after exit
1 CriticalCritical business process stopped for many users, or data integrity at risk, no workaround15 min1 hWorkaround within 4 h[BAU]
2 HighCritical process degraded, or a process stopped for one site or team, workaround is hard30 min4 hWorkaround within 1 business day[BAU]
3 MediumNon-critical process affected, workaround exists4 business hoursDailyFix planned in a scheduled release[BAU]
4 LowCosmetic issue or question1 business dayOn changeAs capacity allows[BAU]

All values in the table are Example targets; replace them with values agreed with the business owner and recorded in the service level agreement draft.

4.1 Escalation

LevelTriggerEscalate to
1Severity 1 raised, or severity 2 without a workaround after 4 hoursHypercare lead and service owner
2Severity 1 without a workaround after 2 hoursProgramme director, business owner, vendor account manager
3Severity 1 lasting more than 4 hours or a data integrity issue confirmedSponsor; consider the business continuity procedure

For user and stakeholder messages during incidents, use Incident Communication (dev/incident-communication).

5. Monitoring focus

IDSignalSourceThreshold or expectationCheckedOwner
MON-01 (Example)Orders created per hour against the legacy baseline for the same weekdayBusiness dashboardWithin 20 % of baseline after day 3Hourly in week 1Business validation lead
MON-02 (Example)Interface error queue depth per interfaceIntegration monitorZero unprocessed errors older than 1 hourContinuous alertingIntegration lead
MON-03 (Example)Batch job completion and durationSchedulerComplete within rehearsal duration plus 25 %Each morningPlatform lead
MON-04 (Example)Response time of the five most used transactionsApplication performance monitoringWithin the tested targetsContinuousTechnical lead
MON-05 (Example)Workflow items waiting for approvalWorkflow reportNo item older than 2 business daysDailyFunctional lead
MON-06 (Example)Data quality checks on new records (missing tax codes, duplicate partners)Data quality reportZero failures for mandatory rulesDailyData lead
MON-07 (Example)Logins per site and active users against expected usersUsage analytics in the applicationAt least 90 % of expected users active by day 5DailyChange lead
MON-08 (Example)Security events for new roles and privileged accessSecurity monitoringAlerts triaged the same dayContinuousSecurity lead
[MON-NN][Signal][Source][Expectation][Frequency][@owner]

Make sure alerts route to the hypercare rota from the first minute and are re-routed to the operations rota at exit. See Observability Specification (ops/observability-spec).

6. Known issues and fix release path

6.1 Known issues log

IDDescriptionOriginWorkaroundUsers informedFix targetOwnerStatus
KI-001 (Example)Report R-17 slow at peakReadiness defect DEF-0398 and condition GLC-03; cutover decision CD-001Scheduled at 05:00Yes, day 0 noticeHypercare release 2[@name][Open / Fixed / Transferred]
KI-002 (Example)Credit note layout misses one tax line for FR01Readiness defect DEF-0412, fix slipped past T-3dManual credit note templateYesHypercare release 1[@name][Status]
[KI-NNN][Description][Source][Workaround][Yes / No][Release][@owner][Status]

6.2 Fix release path

PathUse forApprovalTestingCadence
Emergency changeSeverity 1 fix or a workaround that needs a changeService owner plus change manager, recorded after the fact within 1 business day if neededTargeted test in pre-production; regression of the affected processAny time
Hypercare releaseSeverity 2 and 3 fixes, bundledChange advisory board, fast-track slotRegression suite plus business re-testExample: Twice a week, Tuesday and Thursday 19:00
Standard releaseSeverity 4, improvements, change requestsNormal change processFull test cycleProduct release calendar

Keep the code and configuration freeze from the cutover plan in place until the first hypercare release; after that, only the paths above may change production. Raise changes with Change Request (ops/change-request).

7. Triage and classification

ClassDefinitionRouteCounts toward defect KPI?
DefectThe solution does not behave as specifiedThird line, fix release pathYes
Data issueMigrated or newly entered data is wrong or incompleteData lead; data fix by approved scriptNo, reported separately
Configuration issueSetup differs from the designSecond line, change recordYes
Training or how-toThe solution works; the user needs helpFirst line or floor support; feeds training top-upsNo
Access request or issueMissing or wrong roleAccess managementNo
Change requestA new or different requirementProduct backlog with business ownerNo
Infrastructure or vendor incidentFault outside the applicationPlatform team or vendorNo, reported separately

Open a problem record for every severity 1 and for any pattern of three or more related tickets. Use Postmortem (dev/postmortem) for severity 1 incidents.

8. User support and adoption

MeasureArrangement
FloorwalkersExample: Two per site in week 1, one per site in week 2; each carries a tablet to log tickets
Super-user networkNamed per team; daily 15-minute call in weeks 1 and 2
Quick referenceOne-page guides per role, linked from the application home page
FAQUpdated daily from ticket themes; published on the intranet
Training top-upsShort sessions scheduled when one topic produces more than [number] tickets in a day
FeedbackDaily site pulse at 12:00 in weeks 1 and 2; weekly survey of super-users
Business continuityManual fallback procedures from the readiness review remain available until exit

9. KPIs and daily reporting

9.1 KPIs

IDKPIDefinitionTarget at exit (Example)
K-01New incidents per dayTickets tagged HYPERCARE, all classes, opened per business dayFive consecutive days at or below the level operations can absorb, agreed as [number] per day
K-02Open severity 1 and 2Count of open severity 1 and 2 incidentsZero severity 1; severity 2 only with an accepted workaround
K-03Backlog ageOpen tickets older than 5 business daysFewer than [number]
K-04First-line resolution shareTickets resolved by first line without escalationAt least [percentage]
K-05Business throughputKey business volume against baseline (MON-01)Within normal range for 5 consecutive days
K-06Batch and interface successSuccessful runs divided by scheduled runsAt least [percentage] for 5 consecutive days
K-07Active usersActive users divided by expected usersAt least [percentage]

9.2 Daily report

FieldValue
Date and hypercare dayYYYY-MM-DD, day [N] of [planned N]
Overall status[Green / Amber / Red] with one-sentence reason
New tickets today (by class)[Defect N, data N, training N, access N, change N, other N]
Open severity 1 / 2 / 3 / 4[N / N / N / N]
Incidents of note[ID and one line each]
KPI trend[K-01 to K-07 with arrow up, down or flat]
Fixes released today, fixes planned[Release ID and KI IDs]
Business events in the next 48 hours[Events]
Exit criteria met[N of N]
Decisions needed[Decision, owner, date]

10. Exit criteria

IDCriterionEvidenceConfirmed byStatus
HYP-EX-001 (Example)No open severity 1; every open severity 2 has an accepted workaround and a fix dateTicket reportService owner[Met / Not met]
HYP-EX-002 (Example)K-01 at or below the agreed level for 5 consecutive business daysKPI reportHypercare lead[Status]
HYP-EX-003 (Example)All business events in section 1.3 completed once without severity 1 or 2Business event calendarBusiness owner[Status]
HYP-EX-004 (Example)Batch and interface success at target for 5 consecutive daysScheduler and integration reportsPlatform lead[Status]
HYP-EX-005 (Example)Every known issue fixed, or transferred to operations with an owner and a dateKnown issues logService owner[Status]
HYP-EX-006 (Example)Receiving teams handled tickets unaided in reverse shadow for at least 5 business daysOperations handover plan resultsApplication support lead[Status]
HYP-EX-007 (Example)Monitoring and alerts re-routed to the operations rota and testedAlert test recordOperations lead[Status]
HYP-EX-008 (Example)Documentation pack accepted by operationsOperations handover acceptanceService owner[Status]
[HYP-EX-NNN][Criterion][Evidence][@name][Status]

The service owner declares exit when all criteria are met, or when the remaining ones are waived in writing with a transfer plan.

11. Handoff to operations

IDItemStatusNotes
HO-01 (Example)Open tickets reassigned from project queues to operations queues[Done / Not done][Count]
HO-02 (Example)Known issues and problem records transferred with owners and dates[Status][IDs]
HO-03 (Example)Alert routing, on-call rota and escalation contacts switched to operations[Status][Test reference]
HO-04 (Example)Project access removed or reduced; vendor access under operations control[Status][Access review reference]
HO-05 (Example)Runbooks updated with hypercare lessons[Status][Links]
HO-06 (Example)Service level targets switched from hypercare to BAU in the ITSM tool[Status][Date]
HO-07 (Example)Warranty or early life support terms confirmed with the delivery team[Status][Contract reference]
HO-08 (Example)Stakeholders notified that hypercare is complete and of the support route[Status][Message reference]
[HO-NN][Item][Status][Notes]

The detailed knowledge transfer, shadowing and acceptance into service are in Operations Handover and Knowledge Transfer (ops/operations-handover).

12. Risks

IDRiskLikelihoodImpactMitigationOwner
HYP-R-001 (Example)Project experts leave for the next rollout before exitMediumHighNamed experts released only at exit; backfill plan approvedProgramme director
HYP-R-002 (Example)Peak season raises volume before stabilisationMediumHighPerformance watch MON-04; extra capacity booked for weeks 3 and 4Technical lead
HYP-R-003 (Example)Users bypass the system with spreadsheetsMediumMediumFloorwalker reports; business owner messages; quick fixes for the pain pointsChange lead
HYP-R-004 (Example)Fix releases introduce regressionsLowHighRegression suite on every hypercare releaseTest lead
[HYP-R-NNN][Risk][L][I][Mitigation][@owner]

13. Closure report

FieldValue
Hypercare dates[Start] to [end], [N] business days (planned [N])
Extensions[None / N days, reason]
Tickets by class and severity[Table or link]
Severity 1 incidents[Number, IDs, postmortem links]
Defects fixed during hypercare[Number, releases]
Items transferred to operations[Number of tickets, known issues, problems]
KPI values at exit[K-01 to K-07]
Business events completed[List]
Effort used[Person-days by team]
Lessons for the next rollout[Summary; full list in lessons learned]
Signed off by[@service-owner], [@business-owner], YYYY-MM-DD

Record lessons in Lessons Learned (project/lessons-learned) and schedule the Post-Implementation Review (project/post-implementation-review).

14. Glossary and references

14.1 Glossary

TermMeaning in this plan
HypercarePeriod of elevated, time-limited support right after go-live
Command centrePhysical or virtual hub where the hypercare team coordinates
FloorwalkerPerson who supports users at their desks or sites in the first days
Known issueProblem known at or after go-live with a documented workaround
Emergency changeChange made urgently to restore service, with lighter approval and later review
Exit criteriaMeasurable conditions that end hypercare
BAUBusiness as usual: the normal support model after hypercare
Reverse shadowReceiving team does the work while the project team observes

14.2 References

ReferenceVersion or date checkedUse
AWS Prescriptive Guidance, Introduction to governance for large migrations, preparing the organization (hypercare period), docs.aws.amazon.comWeb edition checked 2026-10-23Hypercare as a short post-cutover period ending in a handoff checklist with cloud operations
AWS Prescriptive Guidance, Project governance playbook for AWS large migrations (gates 8 and 9: hypercare start and end), docs.aws.amazon.comInitial publication 2022-02-28Hypercare start and end notices
Microsoft Dynamics 365 implementation guide, go-live checklist (operational support readiness), learn.microsoft.comPage updated 2026-07-15Hypercare as elevated support after go-live, paraphrased
Microsoft Dynamics 365 implementation guide, create a support strategy, learn.microsoft.comPage updated 2026-07-15Support scope, team and operations themes
ISO/IEC 20000-1:2018, Service management system requirements, clause 8.6 (resolution and fulfilment)Edition 2018, confirmed 2023; Amd 1:2024Incident and request handling alignment
[Internal ITSM process][Version][Severity definitions]

Standard and licence note

Structure aligned with the hypercare period and handoff described in AWS Prescriptive Guidance for large migrations, with the hypercare and support readiness guidance in the Microsoft Dynamics 365 implementation guide, and with the incident and request clause structure of ISO/IEC 20000-1:2018. Clause numbers and guidance titles are cited for mapping; no vendor text, checklist item or ISO text is reproduced. Amazon Web Services, AWS, Microsoft and Dynamics 365 are trademarks of their owners; this template is not affiliated with or endorsed by them. This template is original text written for this collection. Check the current official guidance and standard versions before use. Template licence: MIT.