Requirements Management Plan Template
Elicitation approach, RACI, requirement attributes, prioritisation, baseline and change control, traceability, metrics
Cómo usar: Use it at project start to agree how requirements will be handled from elicitation to acceptance. Agree roles and change control thresholds with the sponsor first. The main pitfall is a plan too heavy for the team to follow.
Vista previa
Requirements Management Plan: [Project or product name]
Requirements management plan describing how requirements will be elicited, documented, prioritised, baselined, changed, traced and reported for [Project name]. Based on common industry practice in business analysis and systems engineering. Replace every
[bracketed]value and every row marked Example.
| Field | Value |
|---|---|
| Document ID | [RMP-PROJECT-001] |
| Project | [Project name] |
| Version | [0.1] |
| Status | [Draft / Approved] |
| Owner | [@lead-business-analyst] |
| Approved by | [@sponsor], [@project-manager] |
| Last updated | YYYY-MM-DD |
1. Purpose and scope
This plan governs the requirements of [Project name] from initial elicitation to acceptance and handover. It covers [business, stakeholder, system and software requirements / epics and user stories] for [releases in scope]. It does not cover [for example operational change requests after handover, which follow the service management process].
2. Elicitation approach
| Stakeholder group | Techniques | Frequency / timing | Output | Facilitator |
|---|---|---|---|---|
| Example: Executive sponsors | Interviews | Weeks 1 to 2 | Business objectives, constraints | [@ba] |
| Example: Operations staff | Observation, workshops | Weeks 2 to 5, 3 workshops | Process maps, user requirements | [@ba] |
| Example: Customers | Survey, usability sessions | Weeks 3 to 6 | Needs, pain points | [@ux] |
| Example: IT and security | Document analysis, interviews | Weeks 2 to 4 | Constraints, interface requirements | [@architect] |
| [Group] | [Technique] | [Timing] | [Output] | [@name] |
Elicitation records (notes, recordings, photos of whiteboards) are stored
in [location] with ID ELC-nnn so that each requirement can cite its
source.
3. Roles and responsibilities
| Activity | Sponsor | Product owner | Business analyst | Architect | QA lead | Dev team | CCB |
|---|---|---|---|---|---|---|---|
| Elicit requirements | I | C | A/R | C | C | C | - |
| Document and analyse | I | C | A/R | C | C | C | - |
| Prioritise | C | A | R | C | I | C | - |
| Approve baseline | A | R | R | C | C | I | C |
| Assess change impact | I | C | A/R | R | R | R | I |
| Approve changes | C | R | C | C | C | I | A |
| Maintain traceability | - | I | A/R | C | R | R | - |
| Verify and accept | C | A | R | C | R | C | - |
The change control board (CCB) consists of [sponsor or delegate, product owner, architect, project manager, QA lead] and meets [weekly / as needed].
4. Requirement types and attributes
| Type | ID format | Documented in |
|---|---|---|
| Business requirement | BR-nnn | BRS |
| Stakeholder / user requirement | STK-UR-nnn | StRS |
| Functional requirement or user story | SRS-FR-nnn / [KEY]-nnn | SRS / backlog |
| Non-functional requirement | NFR-<char>-nn | NFR specification |
| Transition requirement | TR-nnn | Transition plan |
| Constraint | CON-nnn | Relevant specification |
| Attribute | Values | Mandatory |
|---|---|---|
| ID | Unique, never reused | Yes |
| Statement | One testable sentence | Yes |
| Source | Stakeholder and elicitation record | Yes |
| Rationale | Why it is needed | Yes |
| Priority | Must / Should / Could / Won't | Yes |
| Owner | Accountable stakeholder | Yes |
| Status | Proposed, Approved, Implemented, Verified, Deferred, Rejected | Yes |
| Verification method | Inspection, Analysis, Demonstration, Test | Yes |
| Target release | Release ID | When approved |
| Risk / complexity | High, Medium, Low | Optional |
5. Prioritisation method
Scope is set with MoSCoW. Within each category, items are ordered by a value-to-cost score:
Each factor is scored 1, 2, 3, 5, 8 or 13 by the product owner (value, time criticality), architect (risk reduction) and development team (effort). Must requirements together may not exceed [60%] of planned capacity. Ties are resolved by the product owner; disputes escalate to the sponsor.
6. Baseline
A baseline is the approved set of requirements, at a stated version, for a
release. Baselines are taken at [end of analysis phase / each release
planning] and are labelled REQ-BL-<release>.<n>. After baseline, any
change to an approved requirement follows section 7. Editorial changes
that do not alter meaning (spelling, formatting) are allowed without CCB
approval but are recorded in the revision history.
7. Change control process
The flow below shows how a change request moves from submission to closure.
| Threshold | Decided by |
|---|---|
| Example: Effort under 3 days, no change to a Must, no schedule impact | Product owner |
| Example: Effort 3 days or more, or affects a Must, a milestone or budget | CCB |
| Example: Budget increase above [10%] or milestone moved | Sponsor via CCB |
Each change request records: ID, requester, date, description, reason, affected requirements, impact estimate, decision, decision date and decider.
8. Traceability approach
Links maintained: business requirement to stakeholder requirement to system or software requirement to design element to test case. Links are recorded in [tool] and exported to the requirements traceability matrix [RTM-xxx] at each baseline. The BA is accountable; developers link commits and pull requests to requirement IDs; QA links test cases.
9. Tools and repositories
| Purpose | Tool | Location | Access |
|---|---|---|---|
| Example: Requirements repository | [Requirements tool or Markdown in Git] | [URL or path] | Project team: edit; stakeholders: read |
| Example: Backlog | [Issue tracker] | [URL] | Team |
| Example: Models and diagrams | [Modelling tool] | [URL] | BA, architects |
| Example: Test management | [Tool] | [URL] | QA, BA |
| [Purpose] | [Tool] | [Location] | [Access] |
10. Review and approval
| Review | Participants | When | Exit criteria |
|---|---|---|---|
| Peer review | BA, another BA | Each new requirement set | Checklist complete; no open major comments |
| Stakeholder walkthrough | Owners of the requirements | Before baseline | Each owner confirms correctness |
| Technical review | Architect, dev lead, QA lead | Before baseline | Feasible, testable, no conflicts |
| Formal approval | Sponsor, product owner | Baseline | Signed approval recorded |
Requirement quality checklist: necessary, unambiguous, singular, feasible, verifiable, consistent, traceable, and free of design detail.
11. Metrics
| Metric | Definition | Target | Report frequency |
|---|---|---|---|
| Requirements volatility | Changed + added + deleted after baseline / baselined count | Under [10%] per release | Per sprint |
| Change request cycle time | Median days from submission to decision | Under [5] days | Monthly |
| Test coverage | Approved requirements with at least one test / approved | 100% of Must | Per baseline |
| Review defect density | Defects found in review / requirements reviewed | Trending down | Per review |
| Requirements defects in test | Defects traced to wrong or missing requirements | [Target] | Per release |
12. Communication
| Audience | Information | Channel | Frequency | Owner |
|---|---|---|---|---|
| Sponsor and steering group | Baseline status, major changes, metrics | Steering report | Monthly | [@pm] |
| Delivery team | New and changed requirements | Backlog refinement | Weekly | [@po] |
| Stakeholder owners | Decisions on their requests | Email, CR log | Per decision | [@ba] |
| All stakeholders | Approved baseline | Repository link | Per baseline | [@ba] |
13. Revision history
| Version | Date | Author | Change summary |
|---|---|---|---|
| 0.1 | YYYY-MM-DD | [@name] | Initial plan |
| [x.y] | YYYY-MM-DD | [@name] | [Change] |
Standard and licence note
Based on common industry practice for requirements management planning in business analysis and systems engineering. Original text written for this collection; examples are illustrative. Template licence: MIT.
Plantillas relacionadas
Business Requirements Specification (BRS) Template
Business purpose, measurable objectives, processes, rules, business requirements with attributes, success metrics (BRS/BRD)
Requisitos y análisisData Requirements Specification Template
Entities, data dictionary, quality targets, retention, privacy basis, lineage, data interfaces, migration, ERD