Construction RFI Log Template

Construction request for information log: drawing and spec references, required-by dates, answers, cost and time impact, change links

ConstructionLégerrfilog

Mode d'emploi: Use it to track site questions to designers from first issue to closed answer. Fill the drawing reference and required-by date for every RFI. The main pitfall is treating an answer that changes scope as an instruction without raising a change record.

Aperçu

Construction RFI Log: [Project name]

A register of construction requests for information (RFIs): questions from the site team or a contractor to the designers or contract administrator about drawings, specifications or site conditions, with the drawing and model references, the answer, the due dates and any cost or time impact. Based on common construction practice. This is the site RFI, not a procurement request for information (for that, see business/rfi). Replace every [bracketed] value and every row marked Example.

Document control

FieldValue
Log ID[RFI-LOG-FHL]
Owner[Contractor's design manager, @name]
Contractual response period[Days stated in the contract, or agreed working days]
Last updatedYYYY-MM-DD

1. RFI register

RFI IDRaisedRaised byToSubject and questionDrawing, revision, gridSpec clauseRequired byAnsweredAnswer summaryCost impactTime impactChange ref.Status
RFI-041 (Example)YYYY-MM-DDSteel erectorStructural engineerConnection detail for beam B12 at grid D/4 not shown; confirm bolt groupFHL-OKS-ST-02-DR-S-00220 rev C01, D/4[Clause]YYYY-MM-DDYYYY-MM-DDUse standard detail SD-07NoneNoneClosed
RFI-042 (Example)YYYY-MM-DDRoofing contractorArchitectClient request for two extra rooflights: confirm sizes and trimmingFHL-MPA-01-R1-DR-A-00410 rev C01, C-D/4-5[Clause]YYYY-MM-DDYYYY-MM-DDRevised drawing rev C02 issuedYesYesVO-007Closed
RFI-043 (Example)YYYY-MM-DDGroundworksArchitectExisting drain found at grid A/1 clashing with pile cap PC-03; propose diversionSurvey drawing rev P02, A/1[Clause]YYYY-MM-DDPossiblePossibleOpen
[RFI-nnn]YYYY-MM-DD[Who][Who][One question][Ref][Clause]YYYY-MM-DDYYYY-MM-DD[Answer][None/Yes/Possible][None/Yes/Possible][VO-nnn][Status]

2. Summary

MeasureValue
Total raisedExample: 43
OpenExample: 1
Overdue (past required-by date, no answer)Example: 0
With cost or time impactExample: 1 confirmed (RFI-042, linked to VO-007); 1 possible (RFI-043), change record to follow if confirmed

Related: BIM issues tracked as BCF items in the BIM execution plan (construction/bim-execution-plan), product approvals in construction/submittal-register.

Standard and licence note

Based on common construction project practice for requests for information. The text is original. Check your contract for the formal procedure, response periods and notice requirements. Template licence: MIT.