Solution Effort and Cost Estimate Template (PERT, COSMIC)
Estimate class, methods, COSMIC size cross-check, PERT per work package, role and phase effort, rates, contingency and reserve, range, assumptions
उपयोग कैसे करें: Use it when you price a bid, a budget request or a project baseline from a WBS. Fill the scope baseline and estimate class first, then three-point estimates per work package and a functional size cross-check. The main pitfall is quoting a single number without its class, range and assumptions, or hiding contingency inside inflated work packages.
प्रीव्यू
Solution Effort and Cost Estimate: [Solution or bid name]
Effort and cost estimate for delivering a solution, built bottom-up from the work breakdown structure and cross-checked with a functional size count: scope baseline, estimate class, method, sizing, three-point (PERT) effort per work package, effort by role and phase, rates, non-labour costs, contingency and management reserve, confidence range, schedule implications, assumptions and exclusions, comparison with history and sign-off. Structure aligned with the estimating practice described in the PMI PMBOK Guide, Eighth Edition (2025), the five estimate classes of AACE International Recommended Practice 17R-97, and the functional size methods of ISO/IEC 20926:2009 (IFPUG) and ISO/IEC 19761:2011 (COSMIC, Measurement Manual v5.0). Replace every
[bracketed]value and every row marked Example. This is a format for estimating, not a commercial offer or financial advice.
Document control
| Field | Value |
|---|---|
| Document ID | [EST-001] |
| Solution or bid | [Solution name], [Opportunity or project code] |
| Customer or sponsor | [Organisation] |
| Scope baseline | [SoW / requirements / HLD reference and version] |
| Estimate class | [Class 5 / 4 / 3 / 2 / 1] (section 1.2) |
| Estimate purpose | [Feasibility / Budget request / Bid / Baseline / Re-estimate] |
| Currency and price basis | [USD], [nominal], rates valid to YYYY-MM-DD |
| Version | [0.1] |
| Status | [Draft / In review / Approved / Superseded] |
| Owner (lead estimator) | [@solution-architect] |
| Approvers/reviewers | [@delivery-manager], [@commercial-lead], [@peer-estimator] |
| Last updated | YYYY-MM-DD |
| Classification | [Internal / Confidential / Commercial in confidence] |
| Related documents | [WBS-NNN], [BOM-NNN], [RAID-NNN], [SOW-NNN] |
Approvals
| Role | Name | Decision | Date |
|---|---|---|---|
| Lead estimator | [@name] | [Submitted] | YYYY-MM-DD |
| Independent peer reviewer | [@name] | [Approve / Approve with conditions / Reject] | YYYY-MM-DD |
| Delivery manager | [@name] | [Decision] | YYYY-MM-DD |
| Commercial or finance lead | [@name] | [Decision] | YYYY-MM-DD |
| Bid or project sponsor | [@name] | [Decision] | YYYY-MM-DD |
Revision history
| Version | Date | Author | Change summary |
|---|---|---|---|
| 0.1 | YYYY-MM-DD | [@name] | First draft, Class 4 from discovery workshops |
| 0.2 | YYYY-MM-DD | [@name] | Example: Three-point estimates per work package, COSMIC cross-check added |
| 1.0 | YYYY-MM-DD | [@name] | Example: Approved as Class 3 bid estimate after peer review |
Contents
- Estimate purpose and class
- Scope baseline
- Estimating approach
- Functional size cross-check
- Work package effort
- Effort by role and phase
- Rates and labour cost
- Non-labour costs
- Contingency, reserve and cost baseline
- Confidence range and schedule implications
- Assumptions, dependencies and exclusions
- Comparison with history
- Review, sign-off and re-estimation
- Glossary and references
1. Estimate purpose and class
1.1 Purpose
[State the decision this estimate supports, for example a go or no-go on a bid, a budget request, or the cost baseline for a contracted project.] Example: This estimate prices the delivery of the customer self-service portal described in HLD v1.2 for the fixed-price bid due YYYY-MM-DD. It becomes the cost baseline if the bid is won.
1.2 Estimate class
AACE International classifies estimates into five classes (Class 5, least defined, to Class 1, most defined) and uses the maturity of the scope definition as the main characteristic of each class. The ranges below are your organisation's own targets, not figures from the recommended practice; agree them with your delivery and commercial leads.
| Class | Typical use | Definition available | Target range (your policy) |
|---|---|---|---|
| 5 | Idea screening, opportunity qualification | Problem statement, a few conversations | [Example: -50% to +100%] |
| 4 | Feasibility, early budget request | Capability list, context diagram | [Example: -30% to +50%] |
| 3 | Budget authorisation, business case, bid with priced risk | Requirements baseline, HLD, integration list | [Example: -20% to +30%] |
| 2 | Control baseline, bid or tender, fixed price | Detailed design for most components | [Example: -15% to +20%] |
| 1 | Check estimate, bid or tender, re-estimate of remaining work | Design complete, work under way | [Example: -10% to +15%] |
Selected class: [Example: Class 3. Requirements baseline v1.0, HLD v1.2 and the interface list are approved; detailed designs do not exist yet.]
Example: Bidding a fixed price on a Class 3 estimate is a deliberate exception to the class table. It is accepted only because the discrete risks are priced as expected monetary value in section 9.2, contingency is held at P80, and the sponsor approves the exposure in writing. If any of these conditions is missing, bid capped time and materials or ask for a paid discovery phase that brings the estimate to Class 2.
2. Scope baseline
| Baseline item | Reference and version | Notes |
|---|---|---|
| Requirements | [BRD / SRS ID, version] | Example: 46 functional, 31 non-functional requirements |
| Architecture | [HLD ID, version] | Example: HLD v1.2, approved by the design authority |
| Interfaces | [Interface list ID] | Example: 4 interfaces: CRM (REST), identity provider (OIDC), email (SMTP API), document store |
| Data migration | [Data migration strategy ID] | Example: 180,000 customer accounts, 1.2 million cases |
| Environments | [Environment plan] | Example: DEV, SIT, UAT, PROD, DR |
| Service transition | [Hypercare scope] | Example: 4 weeks of hypercare after go-live |
| WBS | [WBS ID, version] | Section 5 uses the same IDs |
In scope: [list the deliverables]. Out of scope: [list items, and move them to section 11.3].
3. Estimating approach
| Method | Where used | Evidence | Strength | Limitation |
|---|---|---|---|---|
| Bottom-up three-point (PERT) | Every work package in section 5 | Estimates from the people who will do the work | Detailed, exposes uncertainty | Misses work that is not in the WBS |
| Functional size (COSMIC or IFPUG) | Build and integration packages | Count of functional processes from requirements | Independent of team opinion | Needs a calibrated productivity rate |
| Analogous | Whole-project cross-check | Actuals from comparable past projects (section 12) | Quick, grounded in reality | Projects are never fully alike |
| Parametric | Testing, project management | Ratios from history, for example PM effort as a share of delivery effort | Consistent | Ratios drift with delivery model |
| Expert judgement (wideband Delphi) | Novel components | Two or more experts estimate independently, then converge | Captures tacit knowledge | Anchoring if experts confer too early |
Rules applied in this estimate:
- Estimate in person-days of 8 working hours of effort on the task. Leave, holidays and non-project time are applied once, as the availability ratio in section 10.2, when converting to calendar time.
- Estimators give optimistic, most likely and pessimistic values without seeing each other's numbers first.
- Every work package has one named estimator and one assumption ID.
- Tolerance between methods: the bottom-up and functional size estimates for the same scope must agree within [Example: 15%], or the gap is explained in section 4.3.
4. Functional size cross-check
4.1 Method
[Choose one.] COSMIC (ISO/IEC 19761:2011) sizes each functional process by counting its data movements: Entries (E) and Exits (X) cross the boundary with a user or another system, Reads (R) and Writes (W) touch persistent storage. Each data movement counts as one COSMIC function point (CFP). IFPUG function point analysis (ISO/IEC 20926:2009) counts data functions and transactional functions and weights them by complexity. Follow the official measurement manual for counting rules; this section records your count, not the rules.
4.2 Count
| Process ID | Functional process | E | X | R | W | CFP |
|---|---|---|---|---|---|---|
| FP-01 (Example) | Register customer account | 1 | 2 | 1 | 1 | 5 |
| FP-02 (Example) | Sign in through identity provider | 1 | 1 | 1 | 0 | 3 |
| FP-03 (Example) | View open cases | 1 | 2 | 2 | 0 | 5 |
| FP-04 (Example) | Create case and send to CRM | 1 | 2 | 1 | 1 | 5 |
| FP-05 (Example) | Update profile | 1 | 1 | 1 | 1 | 4 |
| FP-06 (Example) | Upload attachment to a case | 1 | 1 | 0 | 1 | 3 |
| Sample subtotal | 6 of 48 processes | 6 | 9 | 6 | 4 | 25 |
| Total (Example) | 48 functional processes | 212 |
4.3 Conversion and comparison
| Item | Value |
|---|---|
| Productivity rate (build and unit test, from section 12) | Example: 0.65 person-days per CFP |
| Size-based effort for build and integration | Example: 212 x 0.65 = 137.8 person-days |
| Bottom-up effort for the same scope (WBS 1.3 + 1.4, section 5) | Example: 83.3 + 65.0 = 148.3 person-days |
| Difference | Example: 148.3 - 137.8 = 10.5 person-days, 7.6% above the size-based figure |
| Within tolerance? | Example: Yes (limit 15%). The excess is resilience work on the CRM interface (retries, idempotency), which functional size does not measure |
5. Work package effort
For each work package the PERT (beta) approximation gives:
For the total, expected values add, and, if work packages are treated as independent, variances add: and .
| WBS | Work package | Estimator | O | M | P | E | σ | σ² |
|---|---|---|---|---|---|---|---|---|
| 1.1 (Example) | Project management and governance | @pm | 40 | 50 | 70 | 51.67 | 5.00 | 25.00 |
| 1.2 (Example) | Discovery and detailed design | @sa | 30 | 40 | 60 | 41.67 | 5.00 | 25.00 |
| 1.3 (Example) | Portal front end and services | @dev-lead | 60 | 80 | 120 | 83.33 | 10.00 | 100.00 |
| 1.4 (Example) | Integration (CRM, identity, email) | @int-lead | 40 | 60 | 110 | 65.00 | 11.67 | 136.11 |
| 1.5 (Example) | Data migration | @data-lead | 20 | 30 | 55 | 32.50 | 5.83 | 34.03 |
| 1.6 (Example) | Testing (SIT, performance, security support) | @qa-lead | 35 | 45 | 70 | 47.50 | 5.83 | 34.03 |
| 1.7 (Example) | Environments and delivery pipeline | @devops | 15 | 20 | 30 | 20.83 | 2.50 | 6.25 |
| 1.8 (Example) | Deployment, cutover and hypercare | @pm | 15 | 20 | 35 | 21.67 | 3.33 | 11.11 |
| Total | 255 | 345 | 550 | 364.17 | 19.28 | 371.53 |
Example check: person-days, and person-days. The total σ is not the sum of the individual σ values (295 / 6 = 49.17); summing them would overstate the spread for independent packages.
6. Effort by role and phase
The expected total of 364.17 person-days is planned as 364 person-days.
| Role | Mobilise and design | Build | Test | Deploy and hypercare | Total |
|---|---|---|---|---|---|
| Solution architect (Example) | 14 | 10 | 3 | 3 | 30 |
| Project manager (Example) | 10 | 20 | 8 | 7 | 45 |
| Business analyst (Example) | 20 | 8 | 5 | 2 | 35 |
| Senior developer (Example) | 10 | 65 | 8 | 7 | 90 |
| Developer (Example) | 4 | 62 | 8 | 6 | 80 |
| Integration engineer (Example) | 6 | 18 | 3 | 3 | 30 |
| QA engineer (Example) | 4 | 2 | 26 | 8 | 40 |
| DevOps engineer (Example) | 4 | 4 | 2 | 4 | 14 |
| Total | 72 | 189 | 63 | 40 | 364 |
Check the shape against history: in the example, testing (63 of 364, 17%) and project management (45 of 364, 12%) sit inside the ratios observed on past projects in section 12. A testing share far below your history is a warning sign, not a saving.
7. Rates and labour cost
| Role | Person-days | Cost rate per day (USD) | Labour cost (USD) | Rate source |
|---|---|---|---|---|
| Solution architect (Example) | 30 | 1,100 | 33,000 | Rate card RC-2026 |
| Project manager (Example) | 45 | 950 | 42,750 | Rate card RC-2026 |
| Business analyst (Example) | 35 | 800 | 28,000 | Rate card RC-2026 |
| Senior developer (Example) | 90 | 850 | 76,500 | Rate card RC-2026 |
| Developer (Example) | 80 | 650 | 52,000 | Rate card RC-2026 |
| Integration engineer (Example) | 30 | 850 | 25,500 | Subcontractor quote Q-118 |
| QA engineer (Example) | 40 | 600 | 24,000 | Rate card RC-2026 |
| DevOps engineer (Example) | 14 | 800 | 11,200 | Rate card RC-2026 |
| Total | 364 | 292,950 |
Example: the average cost rate is 292,950 / 364 = USD 804.81 per person-day. Section 9 uses it to convert effort contingency to cost.
Rate assumptions: [working days per month, overtime policy, travel time treatment, annual rate increases if the project spans a rate change, offshore or nearshore mix, currency of subcontractor rates].
8. Non-labour costs
| ID | Item | Basis | Cost (USD) | BoM reference |
|---|---|---|---|---|
| NL-01 (Example) | Non-production cloud environments during delivery | 4 months x 449.86 per month = 1,799.44, rounded | 1,800 | BOM-CL-101 to BOM-CL-104 |
| NL-02 (Example) | Test automation tool licences | 4 named users x 1,050 per year | 4,200 | BOM-SW-002 |
| NL-03 (Example) | Travel for on-site workshops and cutover | 6 trips x 1,000 | 6,000 | Not in BoM |
| NL-04 (Example) | Independent penetration test | Fixed quote from test provider | 12,000 | BOM-PS-002 |
| NL-05 (Example) | Production and DR cloud from go-live to the end of hypercare | 1 month x (1,352.88 + 294.20) = 1,647.08, rounded | 1,650 | BOM-CL-001 to BOM-CL-006, BOM-CL-201, BOM-CL-202 |
| Total | 25,650 |
Production and DR environments run from go-live while the supplier is still accountable (4 weeks of hypercare), so their cost sits inside the delivery price. From the start of Year 1 the customer pays them as run cost (BoM section 12).
9. Contingency, reserve and cost baseline
9.1 Contingency for estimating uncertainty
The example sets the effort target at the 80th percentile (P80). With the normal approximation of the total, .
| Item | Value |
|---|---|
| Expected effort E | Example: 364.17 person-days |
| Total σ | Example: 19.28 person-days |
| P80 effort | Example: 364.17 + 0.8416 x 19.28 = 380.40 person-days |
| Effort contingency (P80 - E) | Example: 16.23 person-days |
| Contingency cost at average rate | Example: 16.23 x 804.81 = 13,062.07, rounded USD 13,062 |
9.2 Contingency for discrete risks
Price risks that are not already inside the three-point ranges, using expected monetary value (probability times cost impact). Keep the risk IDs identical to the RAID Log.
| Risk ID | Risk | Probability | Cost impact (USD) | EMV (USD) |
|---|---|---|---|---|
| RSK-011 (Example) | CRM API limits force a caching layer | 30% | 12,750 | 3,825 |
| RSK-012 (Example) | Source data quality worse than profiled; extra cleansing cycle | 40% | 8,000 | 3,200 |
| RSK-013 (Example) | Identity federation needs an extra customer security review | 20% | 6,000 | 1,200 |
| Total | 8,225 |
9.3 Cost baseline and budget
| Line | Basis | USD |
|---|---|---|
| Labour cost | Section 7 | Example: 292,950 |
| Non-labour cost | Section 8 | Example: 25,650 |
| Base cost | Labour + non-labour | 318,600 (Example) |
| Contingency, estimating uncertainty | Section 9.1 | Example: 13,062 |
| Contingency, discrete risks | Section 9.2 | Example: 8,225 |
| Cost baseline | Base cost + contingency | 339,887 (Example) |
| Management reserve | Example: 5% of base cost = 15,930.00 | Example: 15,930 |
| Total budget | Cost baseline + management reserve | 355,817 (Example) |
Release rules: [Example: the delivery manager draws contingency against a named risk or variance and records it in the change log; management reserve needs sponsor approval and a change request].
9.4 Hand-off to pricing
Pricing is owned by the commercial lead. Record what was handed over so the link between cost and price stays auditable.
| Item | Value |
|---|---|
| Cost baseline handed over | Example: USD 339,887 |
| Pricing model | [Fixed price / Time and materials / Capped T&M / Milestone-based] |
| Target gross margin on cost baseline | Example: 30% |
| Indicative price, cost baseline / (1 - margin) | Example: 339,887 / 0.70 = 485,552.86, rounded USD 485,553 |
| Management reserve treatment | Example: Held by the supplier, not priced separately |
| Price owner and date | [@commercial-lead], YYYY-MM-DD |
10. Confidence range and schedule implications
10.1 Range
| Measure | Effort (person-days) | Comment |
|---|---|---|
| Sum of optimistic values | Example: 255 | Every package goes well at once; not a realistic target |
| Expected (P50 approximation) | Example: 364.17 | Planning value |
| P80 | Example: 380.40 | Effort target including contingency |
| P90 | Example: 364.17 + 1.2816 x 19.28 = 388.88 | Use for fixed-price exposure checks |
| Sum of pessimistic values | Example: 550 | Every package goes badly at once; use only to test worst-case affordability |
The P80 and P90 figures assume the work packages are independent. Risks that hit several packages at once (for example a late design approval) make the real spread wider; price those as discrete risks in section 9.2.
10.2 Duration and team
| Phase | Effort | Team size | Availability ratio (leave, holidays, non-project time) | Working days | Months (20 days) |
|---|---|---|---|---|---|
| Mobilise and design (Example) | 72 | 4 | 0.85 | 72 / 3.40 = 21.18 | 1.06 |
| Build (Example) | 189 | 7 | 0.85 | 189 / 5.95 = 31.76 | 1.59 |
| Test (Example) | 63 | 5 | 0.85 | 63 / 4.25 = 14.82 | 0.74 |
| Deploy and hypercare (Example) | 40 | 4 | 0.85 | 40 / 3.40 = 11.76 | 0.59 |
| Total | 364 | 79.52 | 3.98 |
Example: about 4 months end to end with phases run in sequence. The customer's target go-live is in 5 months, which leaves about one month of schedule float. Compressing to 3 months would need overlapping build and test and a larger team, which raises coordination effort; re-estimate rather than scaling the numbers.
11. Assumptions, dependencies and exclusions
11.1 Assumptions
| ID | Assumption | Impact if false | Owner | Validate by |
|---|---|---|---|---|
| ASM-001 (Example) | The CRM vendor provides a sandbox with production-like APIs from week 2 | Integration build slips; up to 10 extra days | Customer IT | YYYY-MM-DD |
| ASM-002 (Example) | Customer subject matter experts are available 2 days a week during design | Design phase extends | Customer project manager | YYYY-MM-DD |
| ASM-003 (Example) | UAT is executed by the customer; supplier supports with 1 QA engineer | Test effort rises by about 15 days | Customer | YYYY-MM-DD |
| ASM-004 (Example) | No more than two UI languages | Each extra language adds about 4 days | Product owner | YYYY-MM-DD |
11.2 Dependencies
| ID | Dependency | Provider | Needed by | Status |
|---|---|---|---|---|
| DEP-001 (Example) | Identity provider tenant and test users | Customer security team | Week 3 | Open |
| DEP-002 (Example) | Data extract of customer accounts | Customer data team | Week 6 | Open |
11.3 Exclusions
[List what is not priced.] Example: production and DR cloud running costs after hypercare (see BoM, Years 1 to 3), CRM licence changes, content writing and translation, accessibility audit by a third party, end-user training beyond two train-the-trainer sessions, support after the 4-week hypercare period.
12. Comparison with history
| Past project | Scope similarity | Size (CFP) | Actual effort | Days per CFP | Estimate vs actual |
|---|---|---|---|---|---|
| PRJ-2024-07 (Example) | Portal, 2 interfaces | 150 | 108 days build | 0.72 | Estimated 95, actual 108 (+14%) |
| PRJ-2025-02 (Example) | Portal, 3 interfaces | 190 | 118 days build | 0.62 | Estimated 120, actual 118 (-2%) |
| PRJ-2025-11 (Example) | Partner portal, 4 interfaces | 240 | 146 days build | 0.61 | Estimated 130, actual 146 (+12%) |
| This estimate | Portal, 4 interfaces | 212 | 148.3 days build (bottom-up) | 0.70 |
Example reading: the productivity rate of 0.65 used in section 4 is the mean of the three past rates, (0.72 + 0.62 + 0.61) / 3 = 0.65. This estimate's bottom-up rate, 148.3 / 212 = 0.70, is within the observed range. Two of three past projects overran by more than 10%, which supports holding contingency at P80 rather than P50.
13. Review, sign-off and re-estimation
13.1 Review checklist
| Check | Result | Reviewer |
|---|---|---|
| Every requirement and deliverable maps to at least one work package | [Pass / Fail] | [@name] |
| Project management, testing, environments, cutover and hypercare are included | [Pass / Fail] | [@name] |
| Each work package has O, M and P values from a named estimator | [Pass / Fail] | [@name] |
| Row and column totals in section 6 agree with section 5 | [Pass / Fail] | [@name] |
| Non-labour lines match the Bill of Materials version | [Pass / Fail] | [@name] |
| Contingency and management reserve are separate and justified | [Pass / Fail] | [@name] |
| Functional size cross-check within tolerance, or the gap explained | [Pass / Fail] | [@name] |
| Assumptions are testable, owned and dated | [Pass / Fail] | [@name] |
| Estimate class and range are stated on every summary that quotes the number | [Pass / Fail] | [@name] |
13.2 Re-estimation triggers
Re-estimate and issue a new version when any of these occurs:
- an approved change request alters the scope baseline in section 2;
- an assumption in section 11.1 is proved false;
- actual effort to date departs from the plan by more than [Example: 10%] at a phase gate;
- the design matures enough to move to a better estimate class;
- the rate card, team location mix or delivery model changes.
13.3 Roles
| Activity | Solution architect | Delivery manager | Estimators | Commercial lead | Sponsor |
|---|---|---|---|---|---|
| Define scope baseline and class | A | C | C | I | I |
| Three-point estimates | C | C | R | I | I |
| Functional size count | R | I | C | I | I |
| Contingency and reserve | C | R | C | C | A |
| Pricing on top of cost baseline | C | C | I | R | A |
| Approval | C | R | I | C | A |
R = responsible, A = accountable, C = consulted, I = informed.
14. Glossary and references
14.1 Glossary
| Term | Meaning in this template |
|---|---|
| Estimate class | Category of an estimate set by how mature the scope definition is, which in turn implies its expected range |
| Three-point estimate | Optimistic, most likely and pessimistic values for the same work |
| PERT expected value | Weighted mean (O + 4M + P) / 6 of a three-point estimate |
| P80 | Value that the outcome is expected not to exceed in 80% of cases |
| Contingency | Allowance for identified uncertainty and risks, inside the cost baseline |
| Management reserve | Allowance for unidentified events, outside the cost baseline, released by the sponsor |
| Cost baseline | Approved cost including contingency, used to measure performance |
| CFP | COSMIC function point: one data movement of a functional process |
| Productivity rate | Effort per unit of size, taken from your own completed projects |
| EMV | Expected monetary value: probability multiplied by cost impact |
14.2 References
| Reference | Version or date checked | Use |
|---|---|---|
| PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), pmi.org | Eighth Edition, November 2025 | Estimating, contingency and reserve concepts (structure only) |
| AACE International, Recommended Practice 17R-97, Cost Estimate Classification System, aacei.org | Check the current revision | Five estimate classes, maturity of definition as the main characteristic |
| ISO/IEC 20926:2009, IFPUG functional size measurement method, iso.org | 2009 edition; check the current review status at iso.org | Function point option in section 4 |
| ISO/IEC 19761:2011, COSMIC functional size measurement method, iso.org | 2011 edition; check the current review status at iso.org | COSMIC option in section 4 |
| COSMIC Measurement Manual, cosmic-sizing.org | Version 5.0 (Part 1 Principles, definitions and rules, May 2020; Part 2 Guidelines, May 2020) | Counting rules to follow |
| B. Boehm et al., Software Cost Estimation with COCOMO II, Prentice Hall | 2000 | Background on parametric models |
| [Internal rate card] | [Version, valid to YYYY-MM-DD] | Section 7 |
| [Internal estimating history] | [Extract date] | Section 12 |
Standard and licence note
Structure aligned with the estimating, contingency and reserve concepts of the PMI PMBOK Guide, Eighth Edition (2025), the estimate class concept of AACE International Recommended Practice 17R-97, and the functional size measurement methods standardised as ISO/IEC 20926:2009 (IFPUG) and ISO/IEC 19761:2011 (COSMIC). These are copyrighted works: only their names, concepts and the five-class structure are used, and no text, tables, definitions or accuracy ranges are reproduced. The PERT formula is common public practice. All text and worked figures are original and illustrative. Check the current editions at pmi.org, aacei.org, iso.org and cosmic-sizing.org and obtain the documents for their full rules. PMBOK is a registered mark of the Project Management Institute, Inc. Template licence: MIT.
संबंधित टेम्पलेट
Benefits Realization Plan Template
Benefits map, benefit profiles with measure, baseline, target, timing and owner, tracking schedule, dependencies and dis-benefits
परियोजना प्रबंधनData Migration Reconciliation Report Template
Load identification, record count balance, control totals, field sampling, rejected records, defects, tolerance assessment, business validation, trend, sign-off
परियोजना प्रबंधनProcurement Management Plan Template
Make-or-buy analysis, procurement items, contract types, weighted supplier evaluation, timeline, supplier management, approvals