Test Plan: [Project or release name]

Complete project test plan. The section structure follows the test plan information item of ISO/IEC/IEEE 29119-3: context, communication, risk register, test strategy, activities and estimates, staffing and schedule. Replace every [bracketed] value and every row marked Example, and explain any removed section in 4.12 (deviations).

Document control

FieldValue
Document ID[TP-PROJECT-001]
Project / release[Project name] [release or increment]
Test plan type[Project master test plan / Level test plan: system / Type test plan: performance]
Version[0.1]
Status[Draft / In review / Approved / Superseded]
Owner[@test-manager]
Classification[Internal / Confidential]
Last updatedYYYY-MM-DD
Governing strategy[TS-ORG-001 version x.y]
Related documents[SRS], [Architecture description], [Release plan], [Test design specifications]

Approvals

RoleNameDecisionDate
Test manager[@name][Approved / Rejected / Approved with comments]YYYY-MM-DD
Project manager[@name][Decision]YYYY-MM-DD
Product owner[@name][Decision]YYYY-MM-DD
Engineering lead[@name][Decision]YYYY-MM-DD

Revision history

VersionDateAuthorChange summary
0.1YYYY-MM-DD[@name]Initial draft
0.2YYYY-MM-DD[@name]Example: Added performance testing after PR-04 exposure rose to high
1.0YYYY-MM-DD[@name]Example: Approved for execution

Contents

1. Context of the testing

1.1 Projects and test sub-processes

This plan covers testing for [project name], delivering [one sentence on the business outcome] by YYYY-MM-DD. It is the [master / level] plan and covers these test sub-processes:

Sub-processCovered bySeparate plan
Unit and integration testingDevelopment teamsNo, governed here
System testingTest teamNo, governed here
Performance testingSRE and test team[TP-PROJECT-002]
Acceptance testingProduct owner and business users[UAT plan ID]

1.2 Test items

ItemVersion or buildSourceNotes
Example: Mobile app (iOS, Android)4.2.0Release branch release/4.2Store builds via CI
Example: Orders API2.8.xContainer image orders-api:2.8Includes schema migration 0042
[Item][Version][Source][Notes]

1.3 Test scope

  • Features to be tested: [feature 1 with requirement IDs], [feature 2], [regression of existing checkout].
  • Features not to be tested: [feature] because [reason, for example unchanged and covered by automated regression].
  • Quality characteristics in scope: functional suitability, performance efficiency, security, usability, compatibility, [accessibility].

1.4 Assumptions and constraints

IDAssumption or constraintImpact if false or binding
AC-01Example: Feature-complete build delivered to system test by YYYY-MM-DDSystem test window shrinks, coverage of low-risk features reduced
AC-02Example: Payment sandbox supports 3-D Secure test cardsStrong customer authentication flows tested in staging only
[AC-nn][Statement][Impact]

1.5 Stakeholders

StakeholderInterest in testingInvolvement
Product ownerRelease readiness, acceptanceApproves plan, leads UAT
Development teamsFast feedback, defect reportsUnit tests, fixes
Operations / SREOperability, performanceEnvironment, monitoring, performance tests
ComplianceEvidence for auditReviews completion report
[Stakeholder][Interest][Involvement]

2. Testing communication

CommunicationFrequencyParticipantsChannelOutput
Test stand-upDaily during executionTest team, dev leads[Video call]Blockers list
Defect triage[Daily / twice weekly]Test lead, dev lead, product owner[Issue tracker board]Triaged defects
Test status reportWeeklyProject board[Wiki page / email]Status report
Go/no-go meetingBefore releaseRelease boardMeetingRelease decision recorded

Escalation path: tester -> test lead -> test manager -> project manager -> steering committee. Blockers older than [one working day] are escalated.

3. Risk register

Exposure is E=L×IE = L \times I on a 1-25 scale; 15 and above is high, 8-14 medium, below 8 low.

3.1 Product risks

IDRiskLIETreatment in this planOwner
PR-01Example: Promotion stacking rules give larger discount than intended3515Decision table tests (4.3); API regression; finance review in UAT[@name]
PR-02Example: Offline mode loses cart changes on reconnect3412State transition tests; network-condition E2E tests[@name]
PR-03Example: App start time over 3 s on low-end Android236Device lab smoke tests[@name]
[PR-nn][Risk][1-5][1-5][E][Treatment][@name]

3.2 Project risks

IDRiskLIEMitigationOwner
PJ-01Example: Late delivery of the payment integration4416Contract tests with stubs; reserve buffer in schedule[@pm]
PJ-02Example: Only one tester knows the device lab339Pairing and runbook by week 2[@test-lead]
[PJ-nn][Risk][L][I][E][Mitigation][@name]

4. Test strategy

4.1 Test sub-processes

Sub-processObjectiveTest basisEntry criteria
Unit and integrationVerify components and interfacesCode, API contractsCode compiles, static checks pass
SystemVerify requirements end to endSRS, user stories, risk registerBuild deployed, smoke test passes
PerformanceVerify latency and throughput targetsNFRs, workload modelFeature-complete build in performance environment
AcceptanceValidate business fitBusiness processes, acceptance criteriaSystem exit criteria met

4.2 Test deliverables

DeliverableOwnerDue
Test plan (this document)Test managerYYYY-MM-DD
Test design specificationsTestersYYYY-MM-DD
Test cases and proceduresTestersYYYY-MM-DD
Test data and environment readiness reportEnvironment ownerYYYY-MM-DD
Test status reportsTest leadWeekly
Incident (defect) reportsAll testersContinuous
Test completion reportTest managerYYYY-MM-DD

4.3 Test design techniques

Feature or riskTechniqueCoverage target
Example: Promotion rules (PR-01)Decision table testingEvery rule column covered
Example: Quantity fieldEquivalence partitioning and boundary value analysisAll partitions, both sides of each boundary
Example: Cart sync (PR-02)State transition testingAll valid transitions and selected invalid ones
Example: New onboarding flowExploratory testing with chartersThree 90-minute sessions
[Feature][Technique][Target]

4.4 Test completion criteria

CriterionTarget
High-risk test cases executed100%
All planned test cases executed>= 95%
Pass rate>= 98%
Open S1 defects0
Open S2 defects0, or workaround approved by product owner
Must-have requirements traced to a passed test100%
Performance targetsMet at 100% of forecast peak

4.5 Metrics to be collected

Planned versus executed test cases, pass and fail counts, blocked tests, defects opened and closed per day by severity, requirements coverage, automated suite duration and flaky test count. Metrics feed the weekly status report and the completion report.

4.6 Test data requirements

Data setPurposeSourcePrivacy controlsOwner
Example: 500 synthetic customers in 12 countriesTax and shipping rulesSeed script seed/customers.tsSynthetic only[@name]
Example: Promotion catalogueDiscount rulesCopy of production configNo personal data[@name]
[Data set][Purpose][Source][Controls][@name]

4.7 Test environment requirements

EnvironmentComponentsConfigurationReady byOwner
System testWeb, mobile builds, Orders API, stubbed paymentProduction config with sandbox keysYYYY-MM-DD[@platform]
PerformanceOrders API at production sizingLoad generators in same regionYYYY-MM-DD[@sre]
Device lab[List of devices and OS versions]Latest test build installedYYYY-MM-DD[@test-lead]

4.8 Retesting and regression testing

Every resolved defect is retested in the build that contains the fix. The automated regression suite runs on every merge to the release branch; the full manual regression checklist runs once on the release candidate.

4.9 Suspension and resumption criteria

Suspend whenResume when
Smoke test fails on a new buildFixed build passes smoke test
More than 20% of planned tests blockedBlocking defects resolved
Environment down for more than four working hoursEnvironment restored and verified

4.10 Independence and test levels not performed

[State the level of independence for each sub-process and justify any test level or type that the strategy would require but this plan omits.]

4.11 Entry criteria for the plan itself

The plan is approved, the test environment is booked, test data is ready and the test team is staffed as in section 6.

4.12 Deviations from the organisational test strategy

Strategy ruleDeviationReasonCompensating measureApproved by
Example: TS 8 E2E gate before deploymentE2E for mobile runs nightly, not per mergeDevice lab capacityManual smoke on each store build[@head-of-quality]
[Rule][Deviation][Reason][Measure][@name]

5. Testing activities and estimates

ActivityOutputEffort (person-days)Basis of estimate
Test planning and risk analysisThis plan4Previous release
Test designTest design specs, 220 test cases15220 cases x 0.07 days
Environment and data preparationReady environments6Platform estimate
Automation of new regression tests80 automated cases1280 cases x 0.15 days
System test execution (two cycles)Executed runs, defect reports182 cycles x 9 days
Performance testingPerformance report6Four test types, one retest
UAT supportUAT sign-off5Ten business days at 50%
Reporting and closureCompletion report3Previous release
Total69

A contingency of [15%] is held by the test manager for retesting and scope changes.

6. Staffing

6.1 Roles, activities and responsibilities

RoleNameAllocationResponsibilities
Test manager[@name]50%Plan, report, risk, go/no-go input
Test lead[@name]100%Day-to-day coordination, triage
Quality engineer[@name]100%Design, automation, execution
Quality engineer[@name]100%Mobile and device lab
Performance engineer[@name]30%Performance scripts and analysis
Business testers[Names]20% during UATAcceptance scenarios

6.2 Hiring needs

[None / one contract performance engineer for four weeks from YYYY-MM-DD.]

6.3 Training needs

Person or roleTrainingBy when
Example: Business testersTwo-hour session on the UAT tool and defect reportingYYYY-MM-DD
[Who][Training]YYYY-MM-DD

7. Schedule

The schedule below shows the main test milestones; dates are illustrative and must be replaced with the project dates.

MilestoneDateDependency
Test plan approvedYYYY-MM-DDRequirements baseline
Feature-complete build in system testYYYY-MM-DDDevelopment
System test exitYYYY-MM-DDCycle 2 complete
UAT sign-offYYYY-MM-DDSystem test exit
Go/no-go decisionYYYY-MM-DDCompletion report

8. Glossary and references

TermMeaning
Test itemA work product that is the object of testing
Test sub-processA test level or test type with its own planning and control
Smoke testA short test set that shows a build is stable enough to test
[Term][Meaning]

References: [Test strategy TS-ORG-001], [SRS], [Release plan], ISO/IEC/IEEE 29119-3, Software testing, Part 3: Test documentation.

Standard and licence note

Structure aligned with ISO/IEC/IEEE 29119-3, Software and systems engineering: Software testing, Part 3: Test documentation, test plan information item. This template is original text written for this collection and reproduces no text from the standard; obtain the standard from ISO, IEC or IEEE for its normative requirements. Template licence: MIT.