Data Centre and Colocation Assessment Template (ISO/IEC 27001)

Facility profile, shared responsibility, evidence pack, weighted checklist (access, power, cooling, fire, contract, audit rights, climate), scoring, decision

SMKI & ISO/IEC 27001LengkapISO/IEC 27001:2022 + Amd 1:2024 A.5.19 to A.5.22, A.5.30, A.7 (cited only); ISO/IEC 27002:2022datacentrecolocationassessment

Cara menggunakan: Use it before a colocation contract, annually per facility and after major incidents; adapt it as a self-assessment for your own data centre. Fill the facility profile and agree weights and knock-out items first. The main pitfall is accepting a provider certificate whose scope does not name this facility.

Pratinjau

Data Centre and Colocation Assessment: [Facility name and provider]

Assessment checklist and scoring record for a data centre that the organization runs itself or rents space in (colocation suite, cage or racks). It covers site, physical access, power, cooling, fire, monitoring, connectivity, remote hands, contract and audit rights, provider certifications and climate resilience. It supports ISO/IEC 27001:2022 + Amd 1:2024 Annex A physical controls A.7.1 to A.7.14, supplier controls A.5.19 to A.5.22 and ICT readiness A.5.30, with guidance in ISO/IEC 27002:2022. Replace every [bracketed] value and every row marked Example. This is a documentation format, not legal advice: have contract terms reviewed by your legal adviser.

Document control

FieldValue
Document IDDOC-ISMS-079
Version[1.0]
Status[Draft / In review / Approved / Superseded]
Owner[@it-infrastructure-lead]
Approvers/reviewers[@isms-manager], [@ciso], [@procurement-lead], [@legal-counsel]
Last updatedYYYY-MM-DD
Classification[Confidential] (contains site security details)
Standard and editionISO/IEC 27001:2022 + Amd 1:2024, A.5.19 to A.5.22, A.5.30, A.7.1 to A.7.14; ISO/IEC 27002:2022
Next scheduled reviewYYYY-MM-DD (annual, or after an incident or contract change)
Facility[Name, address, hall and cage or rack IDs]
Provider and supplier ID[Provider name], [SUP-NNN in DOC-ISMS-066]
Assessment type[Pre-contract / Annual / Post-incident / Self-assessment of own facility]
Assessment date and teamYYYY-MM-DD, [@assessor-1], [@assessor-2]

Approvals

RoleNameDecisionDate
Lead assessor[@it-infrastructure-lead][Prepared]YYYY-MM-DD
ISMS manager[@isms-manager][Reviewed]YYYY-MM-DD
Risk owner for hosted services[@cto][Accepted / Accepted with action plan / Rejected]YYYY-MM-DD

Revision history

VersionDateAuthorChange
1.0 (Example)2027-03-10[@it-infrastructure-lead]Annual assessment of colocation suite, score 78.5 of 100
1.1 (Example)2027-06-15[@it-infrastructure-lead]Audit rights clause signed; section I re-scored

Contents

  1. Purpose and scope
  2. Facility profile and shared responsibility
  3. Method, scoring and knock-out criteria
  4. Evidence requested before the visit
  5. Assessment checklist
  6. Scoring summary and decision
  7. Findings and action plan
  8. Size tiers
  9. Records and evidence
  10. References

1. Purpose and scope

This assessment determines whether [facility] provides physical, environmental and operational protection adequate for the information and services hosted there, and whether the contract gives the organization the rights it needs to keep that assurance over time.

ItemValue
Hosted services[e.g. production database cluster, backup storage, OT historian]
Highest classification of hosted information[Confidential / Restricted]
Role of the facility[Primary / Recovery / Both]
Recovery time objective of hosted services[hours, from the BIA DOC-ISMS-120]
Risks addressed[RISK-NNN in DOC-ISMS-016]
Out of scope[e.g. provider's other halls, provider's office building]

2. Facility profile and shared responsibility

AreaProviderOrganizationEvidence of the split
Site perimeter, reception, guards[Yes][No][Service description, clause n]
Hall and cage access control[Badge and biometric system][Cage lock, own access list][Access procedure]
Power to the rack (UPS, generator)[Yes, to the power distribution unit][Rack power strips, load within contract][SLA]
Cooling and environment[Yes][Blanking panels, airflow in own racks][SLA]
Fire detection and suppression[Yes][No combustible storage in cage][House rules]
CCTV and alarms[Hall and corridors][Optional camera inside cage][Service description]
Network connectivity[Meet-me room, cross connects][Own routers, carriers][Order forms]
Remote hands[Yes, on ticket][Approves and specifies tasks][Remote hands terms]
Media destruction[Optional service][Owns the decision and the record DOC-ISMS-057][Order]

3. Method, scoring and knock-out criteria

3.1 Method

The assessment runs in the same order every cycle, so results from different years and facilities can be compared.

3.2 Item scale

ScoreMeaning
0Not in place, or no evidence offered
1Partly in place; significant gaps
2In place with minor gaps or partial evidence
3Fully in place with current, verifiable evidence
N/ADoes not apply to this facility (excluded from the average, reason recorded)

3.3 Section weights and bands

Section score = average of its item scores. Weighted points = weight x section score / 3. Total = sum of weighted points (maximum 100).

BandTotalDecision rule
Acceptable80 or more, no knock-out at 0Risk owner accepts; next review in 12 months
Acceptable with action plan65 to 79.9, no knock-out at 0Risk owner accepts with dated actions; re-check within [6 months]
Not acceptableBelow 65, or any knock-out at 0Do not place new services; escalate per DOC-ISMS-015

3.4 Knock-out items

Items marked K in section 5. Example knock-outs: no individual access logging to the hall, no generator or equivalent for the stated SLA, no fire detection in the hall, no right to receive independent assurance reports, provider unable to show insurance or financial stability information.

4. Evidence requested before the visit

EvidenceWhat to checkReceived
ISO/IEC 27001 certificate and Statement of Applicability summaryFacility named in the certificate scope; valid dates; certification body accredited under the Global ACI MRA (formerly IAF MLA)[Yes / No]
Independent assurance report (for example a SOC 2 Type 2 or SOC 1 report)Facility in scope; period covered; exceptions and complementary user entity controls[Yes / No]
Business continuity certification or plan summary (for example ISO 22301)Facility in scope; last exercise date[Yes / No]
Data centre design or operation classification (for example ISO/IEC 22237 series or ANSI/TIA-942 based)Claimed level matches the design you are buying; independent or self-declared[Yes / No]
Payment card attestation where card data is hostedPhysical requirements in scope[Yes / No / N/A]
Maintenance and test records summary (UPS, generator, cooling, fire)Dates within the last 12 months[Yes / No]
Incident history for the last 24 monthsPower, cooling and security incidents with root cause[Yes / No]
Insurance certificate and financial stability informationCover type and amount; ownership changes[Yes / No]
Environmental and climate risk statementFlood, heat, water supply, grid risk[Yes / No]

5. Assessment checklist

A. Site and location (weight 8)

IDCheckEvidence expectedKScoreNotes
DCA-A-01Site risk assessment covers flood, seismic, industrial neighbours, flight paths and transport accessProvider risk summary, maps[0-3]
DCA-A-02Building is discreet: no external signage that reveals the data centre purposeObservation[0-3]
DCA-A-03Distance to the other site (primary or recovery) is enough that one regional event does not hit bothMap, BIA[0-3]
DCA-A-04Staff can reach the site during disruption (transport, parking, out-of-hours access)Access procedure[0-3]

B. Perimeter and building access (weight 14)

IDCheckEvidence expectedKScoreNotes
DCA-B-01Layered perimeter: fence or building shell, reception, hall, cageObservation, floor plan[0-3]
DCA-B-02Every entry to the hall is logged to an individual (badge plus PIN or biometric)Access system demo, log sampleK[0-3]
DCA-B-03Visitors are identified with a government ID, pre-registered by an authorised customer contact and escortedVisitor procedure, log sample[0-3]
DCA-B-04Anti-tailgating at hall entry (mantrap, turnstile or guard)Observation[0-3]
DCA-B-05Customer access list changes are processed only from authorised contacts and confirmed in writingTicket sample[0-3]
DCA-B-06Organization can obtain its own access log for its cage on request within [5 working days]Contract, sample[0-3]
DCA-B-07Loading bay is separated from halls; deliveries are inspected and loggedObservation[0-3]
DCA-B-08Cage or rack locks are individual; master keys controlled by provider key registerKey procedure[0-3]

C. Power (weight 14)

IDCheckEvidence expectedKScoreNotes
DCA-C-01Redundant utility feeds or documented single-feed risk with mitigationSingle-line diagram[0-3]
DCA-C-02UPS with redundancy (for example N+1) and battery autonomy matching the generator start timeUPS design summary[0-3]
DCA-C-03Generator capacity for full hall load with on-site fuel for [24 to 48 hours] (Example) and refuel contractsFuel contract, test logK[0-3]
DCA-C-04Generator tested on load at the stated interval; results recordedTest records last 12 months[0-3]
DCA-C-05Dual power feeds (A and B) delivered to each rack from separate distribution pathsObservation, order form[0-3]
DCA-C-06Power usage per rack monitored and reported to the customerPortal demo[0-3]

D. Cooling and environment (weight 10)

IDCheckEvidence expectedKScoreNotes
DCA-D-01Cooling capacity with redundancy for the hallDesign summary[0-3]
DCA-D-02Temperature and humidity monitored at rack inlet with alert thresholds agreed in the SLASLA, portal[0-3]
DCA-D-03Leak detection under raised floors and around cooling unitsObservation, test record[0-3]
DCA-D-04Hot and cold aisle containment or equivalent airflow managementObservation[0-3]
DCA-D-05Plan for extreme heat days (capacity margin, water supply for cooling where used)Provider statement[0-3]

E. Fire detection and suppression (weight 10)

IDCheckEvidence expectedKScoreNotes
DCA-E-01Early warning smoke detection in the hallObservation, maintenance recordK[0-3]
DCA-E-02Suppression system suitable for electrical equipment, zoned to limit impactDesign summary[0-3]
DCA-E-03Fire systems inspected and tested at the interval set by local rulesInspection certificate[0-3]
DCA-E-04No combustible storage in halls; house rules enforcedObservation[0-3]
DCA-E-05Customer notified of fire alarms and suppression events affecting its equipmentNotification procedure[0-3]

F. Monitoring and operations (weight 8)

IDCheckEvidence expectedKScoreNotes
DCA-F-01Operations centre staffed around the clock or with defined on-callStaffing summary[0-3]
DCA-F-02CCTV covers perimeter, entrances, halls and corridors; retention at least [30 days] (Example)Observation, retention setting[0-3]
DCA-F-03Security incidents and physical alarms are reported to customers within an agreed timeContract, incident sample[0-3]
DCA-F-04Provider staff are screened and trained; contractors escortedHR summary, training record[0-3]

G. Connectivity (weight 6)

IDCheckEvidence expectedKScoreNotes
DCA-G-01Several carriers available; diverse building entry pointsCarrier list, plan[0-3]
DCA-G-02Meet-me room access controlled and loggedObservation[0-3]
DCA-G-03Cross-connect orders and changes documented and confirmed to the customerOrder sample[0-3]

H. Remote hands and change (weight 6)

IDCheckEvidence expectedKScoreNotes
DCA-H-01Remote hands work only on tickets from authorised contacts, with identity check for phone requestsProcedure[0-3]
DCA-H-02Remote hands staff follow customer instructions for media: no removal of drives without written approvalProcedure, contract[0-3]
DCA-H-03Provider maintenance that may affect customers is announced in advance with a change windowChange notices sample[0-3]

I. Contract, audit rights and exit (weight 12)

IDCheckEvidence expectedKScoreNotes
DCA-I-01Right to receive independent assurance reports and certificates each yearContract clauseK[0-3]
DCA-I-02Right to audit or visit, including after a security incidentContract clause[0-3]
DCA-I-03SLA for power and cooling availability with service credits and reportingSLA[0-3]
DCA-I-04Security incident notification duty with a time limitContract clause[0-3]
DCA-I-05Subcontracting of security or operations needs notice to the customerContract clause[0-3]
DCA-I-06Exit: notice period, support to move equipment, return of access cards and keysContract clause[0-3]

J. Certifications and assurance (weight 8)

IDCheckEvidence expectedKScoreNotes
DCA-J-01ISO/IEC 27001 certificate names this facility and is validCertificate, register check[0-3]
DCA-J-02Independent assurance report covers this facility; exceptions reviewedReport[0-3]
DCA-J-03Complementary customer controls listed in reports are mapped to the organization's own controlsMapping note[0-3]
DCA-J-04Design or operation classification claims are supported by evidenceCertificate or statement[0-3]

K. Climate and sustainability resilience (weight 4)

IDCheckEvidence expectedKScoreNotes
DCA-K-01Provider has assessed climate-related hazards for the site (flood, heat, water, grid)Statement, risk summary[0-3]
DCA-K-02Energy efficiency and water use are reported, where relevant to customer requirements from clause 4.2Report[0-3]

6. Scoring summary and decision

6.1 Worked example: Quillmere Health Systems colocation suite

SectionWeightSection score (0 to 3)Weighted points
A. Site and location (Example)82.506.67
B. Perimeter and building access (Example)142.7512.83
C. Power (Example)142.5011.67
D. Cooling and environment (Example)102.408.00
E. Fire detection and suppression (Example)102.006.67
F. Monitoring and operations (Example)82.506.67
G. Connectivity (Example)63.006.00
H. Remote hands and change (Example)62.004.00
I. Contract, audit rights and exit (Example)121.506.00
J. Certifications and assurance (Example)82.757.33
K. Climate and sustainability resilience (Example)42.002.67
Total (Example)10078.5

Section scores are averages of whole-number item scores (B: 22 of 24 points over 8 items; C: 15 of 18 over 6 items). Weighted points are rounded to two decimals; the total is computed from unrounded values. Knock-out check: no K item scored 0. The lowest K item was DCA-I-01 (score 1: reports available only under a separate NDA request each year, no contractual right).

Decision (Example): 78.5 falls in the band "Acceptable with action plan". The risk owner accepted with actions ACT-001 to ACT-003, a re-check of section I within 6 months, and risk RISK-044 kept at Medium in DOC-ISMS-016.

6.2 Decision record

FieldValue
Total score and band[nn.n, band]
Knock-out items at 0[None / list]
Decision[Accepted / Accepted with action plan / Not acceptable]
Conditions[list]
Risk register update[RISK-NNN, new score]
Decided by and date[@risk-owner], YYYY-MM-DD
Next assessment dueYYYY-MM-DD

7. Findings and action plan

Action IDItemFindingActionOwnerDueStatus
ACT-001 (Example)DCA-I-01No contractual right to annual assurance reportsAdd assurance report clause at renewal (amendment signed)[@procurement-lead]2027-06-30Closed 2027-06-15
ACT-002 (Example)DCA-E-03Fire suppression inspection certificate 14 months oldObtain current certificate from provider[@it-infrastructure-lead]2027-04-30Open
ACT-003 (Example)DCA-H-02Remote hands terms silent on drive removalWritten instruction filed with provider; confirm in next contract amendment[@it-ops-lead]2027-05-31Open
[ACT-NNN][item][finding][action][@owner]YYYY-MM-DD[Open / Closed]

8. Size tiers

TopicSmall: Quillmere Analytics LtdMedium: Quillmere Health SystemsLarge: Quillmere Group
FacilitiesNone of its own; production on one public cloud provider in two regionsOne colocation suite (primary production for the managed service)One own group data centre plus any colocation used by country units
Use of this templateNot used for the cloud regions: assess the provider through reports under compliance/supplier-security-assessment. Use only if a colocation rack is added laterPre-contract and annual assessment with a site visit by the infrastructure lead and a security team memberAnnual self-assessment of the own data centre (sections I and J adapted to internal service agreements) and annual assessment of each colocation site
AssessorsNot applicable2 people, one day on siteSecurity office plus site facilities; internal audit samples one facility per year
ReportingNot applicableSteering committee and management reviewGroup steering committee, site results consolidated

9. Records and evidence

RecordOwnerLocationRetention
Completed assessment with scores and decisionIT infrastructure lead[GRC tool or document system]Contract plus [3 years]
Evidence pack (certificates, reports, test records)IT infrastructure lead[Restricted folder]Contract plus [3 years]
Site visit notes and photos (where allowed)Lead assessor[Restricted folder]Contract plus [3 years]
Action plan and closure evidenceISMS managerSection 7 and DOC-ISMS-088Until closed plus [3 years]
Access list reconciliations for the cageIT operations[Ticket system][3 years]

Map these records under A.5.22 and A.7 in the control evidence matrix (DOC-ISMS-033, isms/control-evidence-matrix) and link the supplier entry in DOC-ISMS-066.

10. References

ReferenceEditionUse
ISO/IEC 27001:2022 + Amd 1:20242022, Amd 1 2024-02-23Annex A A.5.19 to A.5.22, A.5.30, A.7. https://www.iso.org/standard/82875.html and https://www.iso.org/standard/88435.html
ISO/IEC 27002:20222022Control guidance. https://www.iso.org/standard/75652.html
ISO/IEC 27036-1:20212021Supplier relationships overview. https://www.iso.org/standard/82905.html
ISO/IEC 27031:20252025ICT readiness for business continuity. https://www.iso.org/standard/80975.html
ISO 22301:2019 + Amd 1:20242019, Amd 2024Business continuity management. https://www.iso.org/standard/75106.html
ISO/IEC 22237 series (data centre facilities and infrastructure)Part 1: 2021; check the current edition of each partExample of a design and operation classification

Related templates: isms/physical-security-policy, isms/supplier-register, isms/supplier-security-agreement-27036, compliance/supplier-security-assessment, compliance/business-impact-analysis, isms/ict-readiness-business-continuity-plan, ops/disaster-recovery-plan, isms/equipment-disposal-reuse-record, isms/cloud-services-security-policy, isms/control-evidence-matrix.

Standard and licence note

Structure aligned with ISO/IEC 27001:2022 (including Amd 1:2024) Annex A controls A.5.19 to A.5.22, A.5.30 and A.7.1 to A.7.14, with guidance from ISO/IEC 27002:2022. The checklist, weights, scoring model and examples are original wording; no ISO/IEC text is reproduced, and the named certifications and design standards are examples, not recommendations of any provider. You need the official standards to apply the controls: https://www.iso.org/standard/82875.html. Check the current edition of each reference before use. This is a documentation format, not legal advice. Quillmere names are fictional. Template licence: MIT.