Sales and Operations Plan Template (S&OP Monthly Cycle)

S&OP cycle, time fences, demand review with accuracy and bias, supply review, inventory projection, financial reconciliation, scenarios, decisions, KPIs

Logistik & Rantai PasokLengkapS&OP practice (ASCM)salesoperationsplan

Cara menggunakan: Use it to run one monthly sales and operations planning cycle from demand review to executive decision. Fill the demand plan and its assumptions first, then test it against capacity and money. The main pitfall is turning S&OP into a forecast meeting instead of a recorded decision with owners.

Pratinjau

Sales and Operations Plan: [Business unit], cycle [YYYY-MM]

A monthly sales and operations planning (S&OP) pack: portfolio review, demand review, supply review, inventory and service projection, financial reconciliation, scenarios, the executive decisions and the actions that follow. It follows widely used S&OP practice as taught by supply chain bodies such as ASCM (Association for Supply Chain Management); no single standard governs S&OP. Replace every [bracketed] value and every row marked Example. Figures in the examples are invented and are not benchmarks.

Document control

FieldValue
Document ID[SOP-2026-11]
Cycle[November 2026 cycle, horizon Nov 2026 to Oct 2027]
Version[1.0]
Status[Draft / Pre-S&OP agreed / Executive approved]
Process owner[@sop-process-owner]
Executive sponsor[@general-manager]
Business unit and sites[Business unit, plants, distribution centres]
Units of measure[Units, cases, tonnes; currency]
Last updatedYYYY-MM-DD
Next cycle startsYYYY-MM-DD
Classification[Confidential: contains forecasts and financial plans]

Approvals

RoleNameDecisionDate
Executive sponsor[@general-manager][Approved / Approved with changes]YYYY-MM-DD
Finance lead[@finance-director][Agreed]YYYY-MM-DD
Sales lead[@sales-director][Agreed]YYYY-MM-DD
Operations lead[@operations-director][Agreed]YYYY-MM-DD

Revision history

VersionDateAuthorChange
0.1 (Example)2026-11-12S&OP process ownerDemand and supply reviews entered
0.9 (Example)2026-11-19S&OP process ownerPre-S&OP recommendations added
1.0 (Example)2026-11-24Executive sponsorExecutive decisions recorded

Contents

  1. Scope and planning horizon
  2. Monthly cycle and calendar
  3. Roles and decision rights
  4. Product and portfolio review
  5. Demand review
  6. Supply review
  7. Inventory and service plan
  8. Financial reconciliation
  9. Gaps, scenarios and recommendations
  10. Executive review and decisions
  11. Performance measures
  12. Actions and follow-up
  13. Glossary
  14. References and related templates

1. Scope and planning horizon

ItemValue
Product families in scope[Family list, for example "Countertop blenders", "Kettles", "Spare parts"]
Sites in scope[Plants, contract manufacturers, distribution centres]
Horizon[18] months, monthly buckets
Frozen period[Month 1]: changes only by exception through the operations lead
Slushy period[Months 2 to 3]: changes need supply review agreement
Liquid period[Months 4 onward]: free to change in the next cycle
Planning unit[Units per family per month]
Currency[Currency] at [budget exchange rates]

Families should group products that share capacity and have a similar demand pattern. If two products use different lines or suppliers, they belong in different families even when marketing groups them together. Keep the family list stable from cycle to cycle so that trends can be compared; record any change in the revision history.

The time fences protect the operation from churn. Inside the frozen period, materials are bought and lines are scheduled, so a change costs real money. Write down who can approve an exception and how it is recorded (section 12).

2. Monthly cycle and calendar

StepWorking days (Example)OwnerInputsOutputs
1. Data gathering and portfolio reviewWD 1 to 3Demand planner, product managerLast month actuals, open orders, launch and phase-out listUpdated history, portfolio changes (section 4)
2. Demand reviewWD 4 to 7Sales leadStatistical baseline, sales and marketing input, key account plansAgreed unconstrained demand plan (section 5)
3. Supply reviewWD 8 to 11Operations leadDemand plan, capacity, supplier constraints, inventoryConstrained supply plan, constraints list (section 6)
4. Pre-S&OP reconciliationWD 12 to 14Process owner, finance leadDemand and supply plans, financial planGaps, scenarios, recommendations (sections 8 and 9)
5. Executive S&OP meetingWD 15 or 16Executive sponsorPre-S&OP packDecisions and approved plan (section 10)

Rules for the cycle:

  • Steps run in order. The supply review does not start until the demand plan is agreed, because a moving demand plan makes capacity analysis worthless.
  • A step that misses its deadline is reported at the executive meeting with the reason.
  • Decisions that cannot wait for the next cycle follow the exception route in section 12; they do not create a second, informal plan.

3. Roles and decision rights

RoleResponsibilityDecides
Executive sponsorChairs the executive meeting, resolves trade-offsFinal plan, scenario choice, budget changes within authority
S&OP process ownerRuns the calendar, prepares the pack, tracks actionsAgenda, escalation of late inputs
Demand plannerStatistical forecast, accuracy measuresBaseline method and parameters
Sales leadCommercial input, key account plans, demand plan sign-offDemand plan submitted to supply review
Marketing or product leadPromotions, launches, phase-outsPortfolio changes proposed for approval
Supply plannerCapacity and material checks, constrained planSupply options presented
Operations leadPlants, warehouses, logistics capacitySupply plan submitted to pre-S&OP
Procurement leadSupplier capacity and lead timesSupplier options presented
Finance leadConverts plans to money, compares with budgetFinancial view presented, budget variance flagged

4. Product and portfolio review

IDChangeFamilyDateVolume effectStatusOwner
PRT-001 (Example)Launch of a new blender modelCountertop blenders2027-02Adds 2,000 units per month from March, replaces older modelApproved[@product-manager]
PRT-002 (Example)Phase-out of the older blender modelCountertop blenders2027-03Last build in February, sell-through by AprilApproved[@product-manager]
PRT-003 (Example)Pack size change for spare partsSpare parts2027-01No unit change, pallet count down 8%Proposed[@packaging-engineer]

Questions for this step:

  • Which launches and phase-outs fall inside the horizon, and are they in the demand plan?
  • Is the phase-out stock plan agreed, so that old stock does not become obsolete while the new model ramps up?
  • Has any change moved demand from one family to another?

5. Demand review

5.1 Demand plan by family

Family: Countertop blenders (Example), units per month.

MonthStatistical baselineSales and marketing changesAgreed demand planAssumption reference
Nov 2026 (Example)40,000+2,000 promotion42,000ASM-001
Dec 2026 (Example)47,000+4,000 key account listing51,000ASM-002
Jan 2027 (Example)36,000036,000n/a
Feb 2027 (Example)34,000034,000n/a
Mar 2027 (Example)36,000+2,000 new model38,000PRT-001
Apr 2027 (Example)38,000+2,000 new model40,000PRT-001
Six-month total231,000+10,000241,000

5.2 Assumptions

IDAssumptionOwnerConfidenceUpside or downside
ASM-001 (Example)Retail promotion in weeks 46 to 48 adds 2,000 units[@marketing-lead]MediumDownside: promotion slot not confirmed
ASM-002 (Example)A retail chain lists two models from December[@key-account-manager]HighUpside: December demand up to 10% higher (5,100 units) if the chain extends to online

Each override must have an assumption with an owner. If nobody will own the number, it stays at the baseline.

5.3 Forecast accuracy and bias

MonthForecast at lag 1Actual demandAbsolute errorAbsolute percentage error
Aug 2026 (Example)35,00033,1001,9005.7%
Sep 2026 (Example)37,00038,9001,9004.9%
Oct 2026 (Example)40,00036,8003,2008.7%
Three months112,000108,8007,000
  • Mean absolute percentage error (MAPE) over the three months: 6.4%.
  • Weighted absolute percentage error (WAPE, total absolute error divided by total actual demand): 7,000 / 108,800 = 6.4%.
  • Bias (total forecast minus total actual, divided by total actual): +3,200 / 108,800 = +2.9%, so the plan ran slightly high.

Bias matters more than a single month's error: a forecast that is always high builds inventory, one that is always low causes shortages. Agree a tolerance band for bias (for example plus or minus 5%) and review the causes when the band is breached.

6. Supply review

6.1 Capacity check

MonthAgreed demand planAvailable capacityProposed productionUtilisation
Nov 2026 (Example)42,00044,00044,000100.0%
Dec 2026 (Example)51,00044,00044,000100.0%
Jan 2027 (Example)36,00044,00038,00086.4%
Feb 2027 (Example)34,00040,00036,00090.0%
Mar 2027 (Example)38,00044,00038,00086.4%
Apr 2027 (Example)40,00044,00040,00090.9%
Total241,000260,000240,000

February capacity is lower because of a planned line maintenance week. December demand is above capacity, so November runs at full capacity to build stock ahead of the peak.

6.2 Constraints and supply options

IDConstraintEffectOptionCost or riskOwner
CON-001 (Example)Assembly line capacity 44,000 units per monthDecember demand 7,000 above capacityPre-build in November (in plan)Extra holding cost for one month[@operations-lead]
CON-002 (Example)Motor supplier allocationSupplier confirms 48,000 motors per monthSecond source qualification16 weeks lead time[@procurement-lead]
CON-003 (Example)Outbound dock capacity in December2,600 pallets per weekSaturday shifts in weeks 49 to 51Overtime cost[@warehouse-manager]

Questions for this step:

  • Which constraint binds first if demand is 10% higher than planned?
  • Which supplier commitments are confirmed in writing, and which are assumptions?
  • Can the warehouse and transport network move the volume, not only the plant make it?

7. Inventory and service plan

Opening inventory on 1 November: 30,000 units (Example). Target range: 25,000 to 32,000 units, with safety stock of 20,000 units (Example).

MonthOpeningProductionDemand planClosingWithin target range
Nov 2026 (Example)30,00044,00042,00032,000Yes (at maximum)
Dec 2026 (Example)32,00044,00051,00025,000Yes (at minimum)
Jan 2027 (Example)25,00038,00036,00027,000Yes
Feb 2027 (Example)27,00036,00034,00029,000Yes
Mar 2027 (Example)29,00038,00038,00029,000Yes
Apr 2027 (Example)29,00040,00040,00029,000Yes

The six-month production total (240,000) is 1,000 units below the demand total (241,000), which matches the fall in inventory from 30,000 to 29,000.

Service targets to report alongside the projection:

MeasureTarget (Example)Last month (Example)
Order line fill rate97%96.2%
On-time in full (OTIF) to customers95%93.5%
Days of supply at month end18 to 2422

8. Financial reconciliation

MonthDemand plan (units)Average price (Example)Revenue planBudget revenue (Example)Variance to budget
Nov 202642,00048.002,016,0001,968,000+48,000
Dec 202651,00048.002,448,0002,400,000+48,000
Jan 202736,00048.001,728,0001,776,000-48,000
Feb 202734,00048.001,632,0001,680,000-48,000
Mar 202738,00048.001,824,0001,824,0000
Apr 202740,00048.001,920,0001,920,0000
Total241,00011,568,00011,568,0000

All amounts in [currency]. In this example the six-month revenue equals budget, but the phasing differs: more in November and December, less in January and February. Finance should state whether the phasing change affects quarter results, working capital or covenants.

Other financial lines to check each cycle:

  • Inventory value at standard cost against the working capital target.
  • Overtime, expediting and premium freight in the supply options.
  • Margin effect of promotions and price changes in the demand plan.
  • Capital requests that follow from capacity constraints.

9. Gaps, scenarios and recommendations

9.1 Gaps

IDGapSizeTimeResolved at pre-S&OP?
GAP-001 (Example)December demand above capacity7,000 unitsDec 2026Yes, by November pre-build
GAP-002 (Example)Upside risk at the retail chain (ASM-002)Up to 5,100 unitsDec 2026No, executive decision needed
GAP-003 (Example)Second motor source not qualifiedCapacity risk above 48,000 per monthFrom Mar 2027No, executive decision needed

9.2 Scenarios

ScenarioDescriptionDecember closing inventoryService riskCost
A. Plan (Example)Agreed demand plan, production as in section 625,000LowIn plan
B. Upside, no action (Example)December demand +10% (56,100)19,900, below safety stock of 20,000MediumNone
C. Upside with overtime (Example)As B plus 4,000 overtime units in December (48,000 built, within the motor allocation in CON-002)23,900Low10,000 overtime (4,000 units at 2.50)

9.3 Recommendations to the executive meeting

IDRecommendationReasonDecision needed by
REC-001 (Example)Approve overtime budget for scenario C, to be released only if the retail chain confirms online listing by 2026-11-30Protects service at the main customer at low cost2026-11-24
REC-002 (Example)Start second motor source qualification nowRemoves the binding supplier constraint before the new model ramps up2026-11-24

10. Executive review and decisions

Agenda (Example, 60 minutes):

  1. Performance against last cycle: accuracy, service, inventory, actions (10 min)
  2. Portfolio changes (5 min)
  3. Decisions REC-001 and REC-002 (30 min)
  4. Risks and opportunities beyond the slushy period (10 min)
  5. Summary of decisions and owners (5 min)
IDDecisionDecided byPlan changeOwnerDate
DEC-001 (Example)REC-001 approved with a release date of 2026-11-30Executive sponsorScenario C becomes contingency[@operations-lead]2026-11-24
DEC-002 (Example)REC-002 approved, budget from operations capitalExecutive sponsorSecond source in supply plan from Mar 2027[@procurement-lead]2026-11-24

Decisions with lasting effect also go into the business decision log (business/decision-log) with the reasoning.

11. Performance measures

MeasureDefinitionTarget (Example)Owner
Forecast accuracy (WAPE, lag 1, family)Total absolute error divided by total actualAt most 10%Demand planner
Forecast bias(Forecast minus actual) divided by actualWithin plus or minus 5%Sales lead
Production plan adherenceProduced quantity within plus or minus 5% of plan, by family95% of familiesOperations lead
OTIF to customersOrders delivered on the agreed date and in full95%Operations lead
Days of supplyClosing inventory divided by average daily demand of the next monthWithin target rangeSupply planner
Cycle disciplineSteps completed by their deadline5 of 5Process owner

Use the KPI scorecard template (business/kpi-scorecard) if the organization already reports measures in a common format.

12. Actions and follow-up

IDActionOwnerDueStatus
ACT-001 (Example)Confirm online listing with the retail chain[@key-account-manager]2026-11-30Open
ACT-002 (Example)Issue request for quotation to two motor suppliers[@procurement-lead]2026-12-05Open
ACT-003 (Example)Update the budget phasing for November to February[@finance-lead]2026-12-01Open

Exceptions inside the frozen period:

IDDateChangeRequested byApproved byReason
EXC-001 (Example)2026-11-06Moved 1,500 units from week 46 to week 45Sales leadOperations leadCustomer collection date moved earlier

13. Glossary

TermMeaning in this plan
S&OPSales and operations planning: the monthly process that balances demand, supply and financial plans at aggregate level
Unconstrained demandWhat customers would buy if supply were unlimited
Constrained supply planWhat the operation can produce and deliver given capacity, materials and logistics
Product familyA group of products that share capacity and planning logic
Time fenceA boundary in the horizon after which plan changes need more approval
LagThe number of months between the forecast snapshot and the month it predicts
WAPEWeighted absolute percentage error, total absolute error over total actual
BiasSystematic over- or under-forecasting
OTIFOn time in full delivery to customers
Days of supplyInventory expressed as days of expected demand

14. References and related templates

  • ASCM, Association for Supply Chain Management: professional body whose education material covers sales and operations planning (https://www.ascm.org/). Terms in this template are written in original wording.
  • Related templates in this library:
    • mba/mba-supply-chain-guide for supply chain concepts and terms.
    • mba/mba-inventory-card for safety stock and inventory policy.
    • mba/mba-supply-chain-resilience-card for scenario thinking about disruptions.
    • logistics/warehouse-sop and logistics/carrier-scorecard for the distribution side of the supply plan.
    • business/decision-log and business/kpi-scorecard for decisions and measures.

Standard and licence note

Based on widely used sales and operations planning practice; no single standard or law defines the process. ASCM is named as a source of professional education on S&OP; no text from ASCM or any other publisher is reproduced. All structure, wording, tables and numbers are original, and the figures are invented examples, not benchmarks. Check current guidance from your professional body and your own policies before use. This is a planning format, not financial advice.

Template licence: MIT.