Change Enablement Policy Template (ISO/IEC 20000-1, DORA)

Change policy: standard, normal and emergency changes, risk scoring, authorities, CAB, change models, freezes, emergency path, DORA metrics

OperasionalLengkapISO/IEC 20000-1:2018 + Amd 1:2024 (cl. 8.5.1); ISO/IEC 27001:2022 A.8.32; DORA metrics; ITIL practice name onlychangeenablementpolicy

Cara menggunakan: Use it to set one change policy for every team and service. Fill the risk model and the change authority table together and test them on twenty recent changes. The main pitfall is sending every change to a weekly meeting, so that teams route around the process.

Pratinjau

Change Enablement Policy: [Organisation name]

Organisation policy for changes to services and configuration items: what is a change, change types (standard, normal, emergency), risk assessment, change authorities by type and risk, peer review and the change advisory meeting, standard change models, the change schedule and freeze periods, the emergency path, automated pipelines as a control, separation of duties, records, and change metrics including the DORA software delivery metrics. Structure aligned with ISO/IEC 20000-1:2018 with Amendment 1:2024 (the current edition as of October 2026), clause 8.5.1 change management (8.5.1.1 policy, 8.5.1.2 initiation, 8.5.1.3 activities), and ISO/IEC 27001:2022 Annex A control 8.32. "Change enablement" is the ITIL practice name, cited by name only. This policy sets the rules; each change is recorded with the Change Request template (ops/change-request). Replace every [bracketed] value and every row marked Example.

Document control

FieldValue
Document ID[POL-ITSM-CHG]
Version[1.0]
Status[Draft / In review / Approved / Retired]
Owner (change enablement process owner)[@change-manager]
Approvers/reviewers[@head-of-service-management], [@cto], [@ciso]
Applies to[Services, environments and teams in scope] Example: All production services and their configuration items, including infrastructure as code, managed cloud services and supplier-operated components
Effective dateYYYY-MM-DD
Next reviewYYYY-MM-DD (at least yearly)
Last updatedYYYY-MM-DD
Classification[Internal]

Approvals

RoleNameDate
Process owner[@name]YYYY-MM-DD
Head of service management[@name]YYYY-MM-DD
Chief information security officer[@name]YYYY-MM-DD

Revision history

VersionDateAuthorChange summary
0.1YYYY-MM-DD[@name]First draft
1.0YYYY-MM-DD[@name]Example: Approved; weekly change advisory meeting limited to High risk changes
1.1YYYY-MM-DD[@name]Example: Added "removes a safety check?" question to the risk model after problem PRB-0042

Contents

1. Purpose, scope and principles

Purpose. Increase the number of successful changes to services by making sure that risks are assessed, changes are authorised by the right people, and the organisation learns from changes that fail, while keeping the time from idea to production as short as safety allows.

Scope. Every addition, modification or removal of a configuration item that could affect a service in the service catalogue, in every environment that serves users or holds production data. Out of scope: [list] Example: content edits through the content management system, routine data changes made through application features, and changes in development environments that never hold production data.

PrincipleMeaning in practice
CHG-P1 Risk decides the routeThe more a change can hurt, the more scrutiny it receives; low risk changes are not slowed down to match high risk ones
CHG-P2 Authority sits close to the workThe people who understand the change and the service decide, wherever possible by peer review
CHG-P3 Automate the evidenceTests, approvals and deployment logs recorded by the pipeline count as evidence; nobody re-types them
CHG-P4 Every change is traceableEach change links to its configuration items, its record and, if it fails, to the incident it caused
CHG-P5 Learn from failureFailed changes are reviewed without blame and feed the risk model and change models

2. Definitions

TermMeaning in this policy
ChangeAdding, modifying or removing anything that could directly or indirectly affect a service
Change recordThe record of one change, using ops/change-request or the equivalent pipeline record
Change authorityThe person or group allowed to authorise a type or risk class of change
Change modelA pre-defined, tested way to carry out a recurring kind of change, with its own risk assessment and steps
Change scheduleThe calendar of planned and implemented changes, shared with the service desk and stakeholders
Freeze periodA period during which only listed kinds of change may be made
Failed changeA change that caused an incident, was backed out, or needed an unplanned fix to restore service
Configuration item (CI)A component that is managed to deliver a service, recorded in the CMDB (ops/cmdb-data-model)

3. Roles

RoleResponsibilities
Change requesterRaises the change with a clear reason and expected benefit
Change ownerAccountable for the change from assessment to closure, including risk assessment, scheduling and review
ImplementerCarries out the change and records the result; never authorises their own Medium or High change
Peer reviewerA qualified engineer who reviews Low and Medium changes for correctness and risk
Service ownerAccepts business risk for changes to their service; authorises Medium and High changes
Change advisory meetingA forum of service owners, security and operations that advises on High risk changes and conflicts
Emergency change authorityA small named group (on-call manager plus service owner, or their deputies) that authorises emergency changes
Change managerOwns this policy, the change schedule, change models and metrics; facilitates the change advisory meeting

4. Change types

TypeDefinitionRouteLead time (Example)
StandardLow risk, repeatable change that follows an approved change model (section 7)Pre-authorised; implementer follows the model and the record is created by the tool or pipelineNone beyond the model's own steps
NormalAny change that is not standard or emergencyAssessed and authorised by risk class (sections 5 and 6)Low: same day; Medium: 2 business days; High: 5 business days
EmergencyMust be made as soon as possible to restore service, prevent imminent serious harm or close an actively exploited vulnerabilityEmergency path (section 9)As fast as safely possible

Rules:

  • A change that does not match its model exactly is a normal change.
  • Urgency alone does not make a change an emergency: a missed deadline for a planned project is a normal change with a request for faster assessment.
  • Security patches follow the cadences in ops/patch-management-policy; routine patching runs as standard changes where a model exists.

5. Risk and impact assessment

Every normal change is scored on six questions, each from 1 (lowest risk) to 3 (highest risk). The Change Request template (ops/change-request, section 2.2) uses the same questions.

Question123
How critical is the affected service?Internal, non-criticalImportant, workaround existsTier 1 or revenue-bearing
How many users or customers are affected if it fails?Few, internalA segmentAll, or external customers
Has this kind of change succeeded here before?Many timesSimilar changesNever
Is the change reversible within the window?Fully, testedPartly, or untestedNo
Was it tested in a production-like environment?Yes, with production-like dataPartlyNo
Does it change security controls or data flows?NoIndirectlyYes
Total scoreRisk class (Example)
6 to 8Low
9 to 12Medium
13 to 18High

Overriding rules (Example):

  • A score of 3 on reversibility makes the change High, whatever the total.
  • A change that removes or weakens a safety check (validation, rate limit, alert, backup, access control) is at least Medium.
  • A change during a freeze period (section 8) is at least High, unless the freeze exception list allows it.

6. Change authorities

Change type or risk classChange authority (Example)Minimum evidence
StandardChange model owner (pre-authorised through the model)Pipeline or tool record showing the model steps passed
LowPeer review by a second qualified engineerApproved code or configuration review, tests passed
MediumService owner plus technical peerRisk assessment, test evidence, backout plan
HighService owner after advice from the change advisory meeting, with security for security-relevant changesAll of the above, plus rehearsed backout and communication plan
EmergencyEmergency change authority (on-call manager and service owner)Verbal or chat approval recorded with time; full record within [2] business days

6.1 Change advisory meeting

ItemRule (Example)
PurposeAdvise on High risk changes, resolve schedule conflicts, review failed changes and the metrics
MembersChange manager (chair), owners of the services on the agenda, operations lead, security representative, service desk lead
CadenceWeekly, 30 minutes; cancelled if no High change is pending
InputsChange records submitted at least 3 business days before the meeting
OutputsAdvice recorded on each change record; actions in the minutes
QuorumChair plus the service owner of each change discussed

7. Standard change models

Model IDDescriptionOwnerPreconditionsApprovedReview dueFailures in last 12 months
CM-001 (Example)Application deployment through the main pipeline with automated tests and canary release[@platform-lead]All pipeline gates green; no open P1 or P2 on the serviceYYYY-MM-DDYYYY-MM-DD2 of 1,140
CM-002 (Example)Monthly operating system patching of non-critical servers, ring by ring[@infra-lead]Previous ring healthy for 24 hYYYY-MM-DDYYYY-MM-DD0 of 36
CM-003 (Example)Add or remove a user-facing feature flag[@product-eng-lead]Flag registered, owner namedYYYY-MM-DDYYYY-MM-DD1 of 410
CM-004 (Example)Scale a stateless service within approved limits[@sre-lead]Within the capacity plan limitsYYYY-MM-DDYYYY-MM-DD0 of 95
[CM-][Description][@name][Preconditions]YYYY-MM-DDYYYY-MM-DD[n of m]

Model lifecycle: a model is proposed with at least [5] successful normal changes of the same kind, approved by the change manager and the service owner, reviewed yearly, and suspended after any failure that caused a P1 or P2 incident until the problem review is complete.

8. Change schedule and freeze periods

8.1 Change schedule

All Medium, High and emergency changes appear on the change schedule with service, configuration items, window and change owner. Standard changes are visible in the pipeline log and summarised on the schedule. The service desk reviews the schedule at the start of each shift.

8.2 Freeze periods (Example)

FreezeDatesScopeAllowed during freezeException authority
FRZ-01 Peak trading[YYYY-MM-DD to YYYY-MM-DD] Example: Last two weeks of NovemberCheckout, payments, orders, warehouse systemsEmergency changes; standard models CM-002 and CM-004Head of service management and the service owner
FRZ-02 Financial year end[YYYY-MM-DD to YYYY-MM-DD]Finance and reporting systemsEmergency changes onlyChief financial officer delegate and service owner
FRZ-03 Major event[Dates][Scope][Allowed][Authority]

A freeze exception is requested on the change record, explains why the change cannot wait, and is decided before scheduling.

9. Emergency changes

StepRule (Example)
1 QualifyThe change meets the emergency definition in section 4, usually linked to a P1 or P2 incident or an actively exploited vulnerability
2 AuthoriseEmergency change authority approves by call or chat; the approval time and names are recorded
3 Minimum safetyA second engineer reviews the command or diff before it runs, unless that would extend a P1 outage, in which case the review happens within [24] hours
4 ImplementChanges are made through the normal tooling where possible, so that logs exist
5 RecordA full change record is completed within [2] business days
6 ReviewEvery emergency change is reviewed at the next change advisory meeting

Indicator: if emergency changes exceed [5]% of all changes in a month, the change manager reviews why with the service owners concerned.

10. Automated pipelines and separation of duties

ControlRequirement (Example)Evidence
CHG-C01 Version controlEvery change to code and infrastructure configuration is committed to version controlCommit history
CHG-C02 Independent reviewMerges to the main branch need approval from someone other than the authorRepository branch protection settings and review log
CHG-C03 Automated testsUnit, integration and security checks pass before deploymentPipeline run record
CHG-C04 Progressive releaseProduction deployments use canary or ring release with automatic rollback on health checksDeployment log
CHG-C05 No direct production access for changeManual production changes only through break-glass access, which is logged and reviewedAccess logs reviewed in ops/access-review
CHG-C06 TraceabilityDeployments carry the change or model IDDeployment metadata

Separation of duties: the person who writes a change does not alone approve it for production. In small teams where full separation is not possible, a compensating control applies (Example): automated tests plus after-the-fact review of every production change within [1] business day.

11. Post-implementation review and records

Change categoryReview rule (Example)
Failed changes (incident, backout or unplanned fix)Always reviewed; problem record opened if the cause is not obvious
Emergency changesAlways reviewed at the next change advisory meeting
High risk changesAlways reviewed by the change owner within [5] business days
Medium and Low changesA [5]% sample reviewed monthly by the change manager
Standard changesReviewed through model failure counts in section 7

Records: change records are kept for [3] years or longer if a contract or regulation requires it. Configuration item records in the CMDB are updated as part of closing each change.

12. Change metrics

12.1 DORA software delivery metrics

The DORA research programme describes five software delivery performance metrics, grouped as throughput and instability (checked at dora.dev on 2026-10-30):

MetricGroupDefinition used hereTarget (Example)
Change lead timeThroughputTime from commit to running in productionMedian under 1 day for CM-001
Deployment frequencyThroughputNumber of production deployments per periodTrend only
Failed deployment recovery timeThroughputTime to recover from a deployment that needs immediate interventionMedian under 1 hour
Change fail rateInstabilityShare of deployments needing immediate intervention such as rollback or hotfixBelow 5%
Deployment rework rateInstabilityShare of deployments that are unplanned and triggered by a production incidentTrend only

12.2 Control metrics

IDMeasureFormulaTarget (Example)
CHG-M01Change failure rate (all change types)failed changes / changes implementedBelow 5%
CHG-M02Emergency change shareemergency changes / changes implementedBelow 5%
CHG-M03Standard change sharestandard changes / changes implementedAbove 60% and rising
CHG-M04Unauthorised changes foundchanges detected without a record or model0
CHG-M05Records completed on timeemergency records completed within 2 business days / emergency changes100%
CHG-M06Incidents caused by changeincidents linked to a change / incidentsTrend only

Worked example (Example): in a quarter with 214 implemented changes (150 standard, 58 normal, 6 emergency) and 7 failed changes, the change failure rate is 7 / 214 = 3.27%, the emergency share is 6 / 214 = 2.8% and the standard share is 150 / 214 = 70.1%. The same figures appear in the Service Review Report example (ops/service-review-report).

13. Exceptions and non-compliance

ItemRule (Example)
Exception requestRaised to the change manager with scope, reason, compensating controls and end date
Exception approvalHead of service management; security exceptions also need the chief information security officer
Maximum duration[90] days, renewable once with fresh review
Unauthorised change detectedLogged as an incident, assessed for impact, retrospective record created within [1] business day, root cause reviewed
Repeated non-complianceEscalated to the team's line management with a corrective action plan

14. Standards mapping and references

Section of this policyISO/IEC 20000-1:2018ISO/IEC 27001:2022 Annex ATopic (short original label)
1, 2, 4 Scope, definitions, types8.5.1.1 Change management policy8.32 Change managementDefine what is controlled and how changes are classified
5, 6 Risk and authority8.5.1.2 Change management initiation, 8.5.1.3 Change management activities8.32Assess, approve and plan changes
7 Change models8.5.1.38.32Pre-defined routes for repeatable changes
8 Schedule and freezes8.5.1.38.32Plan and communicate the schedule
9 Emergency changes8.5.1.38.32Handle urgent change with control
10 Pipelines and separation8.5.3 Release and deployment management8.25 Secure development life cycle, 8.31 Separation of environments, 5.3 Segregation of dutiesControlled deployment
11 Review and records8.5.1.3, 8.2.6 Configuration management, 10.2 Continual improvement8.32, 8.9 Configuration managementReview results and update records
12 Metrics9.1 Monitoring, measurement, analysis and evaluation, 9.4 Service reportingMeasure and report
ReferenceVersion or date checkedUse
ISO/IEC 20000-1:2018, Information technology, Service management, Part 1: Service management system requirements, with Amd 1:2024Current edition as of October 2026Clause numbers
ISO/IEC 27001:2022, Information security management systems, Requirements, with Amd 1:2024Current edition as of October 2026Annex A control numbers
DORA software delivery performance metrics, dora.dev/guides/dora-metricsChecked 2026-10-30Names and definitions of the five metrics, summarised
ITIL, PeopleCertITIL 4 available; ITIL (Version 5) released in phases from 2026; checked 2026-10-30Practice name "change enablement" and change type names, by name only

Standard and licence note

Structure aligned with ISO/IEC 20000-1:2018 with Amendment 1:2024, clause 8.5.1 change management and the related clauses in section 14, and with ISO/IEC 27001:2022 with Amendment 1:2024, Annex A control 8.32. Both are copyrighted standards: this template cites clause and control numbers with short original labels only; no text, table or definition is copied. Official text: ISO, purchase or licensed access: https://www.iso.org/standard/70636.html (ISO/IEC 20000-1) and https://www.iso.org/standard/82875.html (ISO/IEC 27001), also sold by national standards bodies. The DORA metric names are summarised from the public DORA guide at https://dora.dev/guides/dora-metrics/. The practice name change enablement and the change type names follow common ITIL usage and are cited by name only; ITIL is published by PeopleCert, which released ITIL (Version 5) in phases during 2026 while ITIL 4 remains available (https://www.peoplecert.org/news-and-announcements/itil-version-5-explained); ITIL is a registered trademark of the PeopleCert group. The risk model, authorities, lead times, freeze examples and targets are illustrative, not taken from any standard. All text is original, written for this collection. Check the current edition of any standard you certify against. Template licence: MIT.