End Stage Report Template
Stage close: performance vs original and exception plan, products and concessions, business case review, benefits, lessons, carried-forward risks, next stage request
Cara menggunakan: Use it at each stage boundary, submitted with the next stage plan and the updated business case. Fill the plan-versus-actual table and the business case review first. The main pitfall is asking for the next stage without restating whether the project is still worth doing.
Pratinjau
End Stage Report: [Project name], Stage [N] [stage name]
An end stage report closes one management stage. The project manager tells the project board what the stage delivered against its plan, how the project stands as a whole, whether the business case is still viable, and asks for authority to start the next stage on the basis of a new stage plan. It is the main input to the board's stage-gate decision. The structure is aligned with the end stage report management product and the stage boundary process described in PRINCE2 7 (PeopleCert, 2023), and it fits any stage-gated or phase-gated project. Replace every
[bracketed]value and every row marked Example.
Document control
| Field | Value |
|---|---|
| Document ID | [ESR-PROJ-NN] |
| Project | [Project name] ([project code]) |
| Stage closing | [Stage number and name] |
| Plan reported against | [Stage plan v1.0 / Exception plan v1.0] |
| Next stage requested | [Stage number and name] |
| Version | [1.0] |
| Status | [Draft / Submitted / Approved] |
| Author | [@project-manager] |
| Board review date | YYYY-MM-DD |
| Classification | [Internal] |
Approvals
| Role | Name | Decision | Date |
|---|---|---|---|
| Executive (sponsor) | [@executive] | [Authorise next stage / Do not authorise / Close project] | YYYY-MM-DD |
| Senior user | [@senior-user] | [Agree / Disagree] | YYYY-MM-DD |
| Senior supplier | [@senior-supplier] | [Agree / Disagree] | YYYY-MM-DD |
Revision history
| Version | Date | Author | Change |
|---|---|---|---|
| 0.1 | YYYY-MM-DD | [@author] | Draft |
| 1.0 | YYYY-MM-DD | [@author] | Submitted with stage 4 plan |
The worked example continues the fictional Brackwell Vale Housing Trust Tenant Services Portal. Stage 3, Build and migrate, was re-planned after exception report ER-TSP-001 (option B approved): budget 534,000 EUR, end 2027-05-28. The project budget is 1,090,000 EUR for four stages plus a 90,000 EUR risk budget, 1,180,000 EUR in total.
1. Stage summary
[Summary]
Example: Stage 3 built the new portal and migrated current tenancy data. All 9 planned products are complete, with historic repairs before 2022 left read-only in the legacy system as approved in the exception. The stage ended on 2027-05-28 as re-planned, at 531,500 EUR, 2,500 EUR (0.5%) below the exception plan budget of 534,000 EUR. The business case remains viable. The board is asked to authorise stage 4, Rollout, at 210,000 EUR over 10 weeks.
2. Performance against the stage plan
| Area | Original stage plan | Plan in force | Actual | Variance vs plan in force |
|---|---|---|---|---|
| Time | [Date] | [Date] | [Date] | [Weeks] |
| Cost | [Amount] | [Amount] | [Amount] | [Amount, %] |
| Scope | [Products] | [Products] | [Products] | [Difference] |
| Quality | [Criteria] | [Criteria] | [Result] | [Difference] |
| Example: Time | 2027-05-21 | 2027-05-28 | 2027-05-28 | 0 |
| Example: Cost | 520,000 EUR | 534,000 EUR | 531,500 EUR | -2,500 EUR (-0.5%) |
| Example: Scope | 9 products, full history | 9 products, current tenancies only | 9 products | None |
| Example: Quality | 0 open severity 1 defects | Same | 0 open severity 1, 4 severity 3 | Accepted by senior user |
Against the original budget, the stage cost 11,500 EUR (2.2%) more, funded by 14,000 EUR drawn from the risk budget.
3. Products delivered
| Product ID | Product | Status | Quality evidence | Accepted by |
|---|---|---|---|---|
| [PRD-NN] | [Product] | [Approved / Approved with concession / Not delivered] | [Evidence] | [@approver] |
| PRD-31 (Example) | Tenant login with multi-factor option | Approved | System and security test reports | [@product-owner] |
| PRD-36 (Example) | Cleansed tenancy records | Approved | Reconciliation: 18,500 of 18,500 current tenancies matched | [@data-owner] |
| PRD-39 (Example) | Portal accessibility statement | Approved with concession | 4 minor issues to fix in stage 4 | [@senior-user] |
Off-specifications and concessions: [List, with IDs and who accepted them.]
4. Business case review
| Item | At initiation | Now forecast | Comment |
|---|---|---|---|
| Total project cost | [Amount] | [Amount] | [Comment] |
| Go-live | [Date] | [Date] | [Comment] |
| Annual net benefit | [Amount] | [Amount] | [Comment] |
| Payback | [Years] | [Years] | [Comment] |
| Example: Project cost excluding risk budget | 1,090,000 EUR | 1,096,000 EUR | Actuals 886,000 EUR for stages 1 to 3 plus stage 4 plan 210,000 EUR |
| Example: Annual net benefit | 255,500 EUR | 249,500 EUR | Read-only legacy licence kept 2 years at 6,000 EUR a year |
Conclusion: [Still justified / Justified with changes / No longer justified]
Example: Still justified. Actuals to date are 58,000 EUR (stage 1), 296,500 EUR (stage 2) and 531,500 EUR (stage 3), 886,000 EUR in total. The risk budget has 76,000 EUR left.
5. Benefits achieved so far
| Benefit | Measure | Baseline | Achieved | Next review |
|---|---|---|---|---|
| [Benefit] | [Measure] | [Value] | [Value] | YYYY-MM-DD |
| Example: Calls moved to self-service | Share of repairs reported online | 9% | Not yet live | 3 months after go-live |
6. Team performance and lessons
| ID | Lesson | Type | Action for the next stage |
|---|---|---|---|
| [LL-NN] | [Lesson] | [Keep / Change] | [Action] |
| LL-07 (Example) | Sampling under-estimated data quality problems | Change | Profile full data before any future migration estimate |
| LL-08 (Example) | Daily burn-down of cleansing gave early warning | Keep | Use the same burn-down for rollout support tickets |
7. Issues and risks carried forward
| ID | Description | Score or priority | Owner | Plan in next stage |
|---|---|---|---|---|
| [ID] | [Description] | [Score] | [@owner] | [Plan] |
| RSK-019 (Example) | Tenants without email cannot self-register | 3 x 4 = 12 | [@senior-user] | Assisted registration at local offices |
8. Next stage request
| Item | Value |
|---|---|
| Next stage | [Number and name] |
| Products | [Main products] |
| Start and end | YYYY-MM-DD to YYYY-MM-DD |
| Budget | [Amount] |
| Proposed tolerances | [Time, cost, scope, quality, risk, sustainability] |
| Plan document | [Link] |
| Example: Next stage | 4, Rollout |
| Example: Start and end | 2027-05-31 to 2027-08-06 (10 weeks) |
| Example: Budget | 210,000 EUR |
| Example: Proposed tolerances | Cost +/-5% (10,500 EUR), time +/-1 week |
9. Related templates
- Highlight report and Exception report for the stage history
- Project closure report for the final stage
- Lessons learned
- Business case
- Project schedule for the next stage plan
Glossary
- Stage boundary: the point between two stages where the board decides whether to continue.
- Exception plan: a plan that replaces a stage plan after the board accepts an option in an exception report.
- Concession: acceptance of a product that does not fully meet its specification.
- Off-specification: something that should be provided but is not, or that does not meet its specification.
- Risk budget: money set aside for risk responses, controlled by the board.
Standard and licence note
Structure aligned with the end stage report management product and the "manage by stages" principle of PRINCE2 7 (Managing Successful Projects with PRINCE2, 7th edition, PeopleCert, 2023), including the stage boundary process. PRINCE2 is cited by name only: no text, tables or figures from the publication are reproduced, and the headings, wording and the fictional Brackwell Vale example are original. Official text: PeopleCert, purchase or licensed access: https://www.peoplecert.org/prince2. PRINCE2 is a registered trademark of PeopleCert. Check the current edition and your organisation's stage-gate rules before use. Template licence: MIT.
Templat terkait
Earned Value Report Template (EVM)
Periodic EVM report: PV, EV, AC, SV, CV, SPI, CPI, S-curve, control accounts, variance analysis, earned schedule, EAC methods, TCPI check, decisions
Manajemen ProyekException Report Template
Forecast tolerance breach: cause, stage and project consequences, costed options checked against both tolerance levels, recommendation, board decision record