Project Schedule Baseline Template (Gantt)

Schedule baseline: milestones, activity list with FS/SS dependencies, Mermaid gantt, critical path, resource loading, buffers

Manajemen ProyekStandarschedulediagrammath

Cara menggunakan: Use once the WBS is stable to build and baseline the schedule. Fill the activity list with dependencies first; the gantt and critical path follow from it. Main pitfall: activities without dependency logic, which hides the critical path.

Pratinjau

Project Schedule: [Project name]

Schedule baseline for the project: milestones, activities with durations and dependencies, a gantt chart, resource loading, schedule risks and buffers, and the log of approved schedule changes. Based on common project management practice. Replace every [bracketed] value and every row marked Example.

FieldValue
Document ID[SCH-PROJECT-001]
Project[Project name]
Version[0.1]
Baseline dateYYYY-MM-DD
Status dateYYYY-MM-DD
Owner[@project-manager]
Scheduling tool[Tool or "this document"]
Calendar[5-day week, public holidays of country X]

1. Scheduling approach

The schedule was developed from the WBS ([WBS-001]) by defining activities per work package, sequencing them with dependency logic, estimating durations with the owners, and analysing the critical path. Durations are in working days. The project manager updates actuals and forecasts every [Friday]; the baseline changes only through approved change requests.

ParameterValue
Estimating method[Three-point estimates for critical activities, expert judgement elsewhere]
Dependency typesFS finish-to-start, SS start-to-start, FF finish-to-finish, with lag in days
Project buffer[10] working days before go-live
Status reportingBiweekly status report, variance by milestone

2. Milestones

The milestone table is the headline view used in status reports.

IDMilestoneBaselineForecastVariance (days)Status
M1Plan baselinedYYYY-MM-DDYYYY-MM-DD0Achieved
M2Design approvedYYYY-MM-DDYYYY-MM-DDExample: +3At risk
M3UAT completeYYYY-MM-DDYYYY-MM-DD[n][On track]
M4Go-liveYYYY-MM-DDYYYY-MM-DD[n][On track]
M5Handover to operationsYYYY-MM-DDYYYY-MM-DD[n][On track]

3. Activity list

Activities are listed with their WBS reference, duration, dependencies and owner.

IDActivityWBSDuration (d)PredecessorsStartFinishOwnerCritical
A01Example: Current-state workshops1.2.110M1 FSYYYY-MM-DDYYYY-MM-DD[@ba]Yes
A02Example: Target process design1.2.215A01 FSYYYY-MM-DDYYYY-MM-DD[@ba]Yes
A03Example: Vendor selection1.325M1 FSYYYY-MM-DDYYYY-MM-DD[@procurement]No
A04Example: Front-end build1.3.135A02 FS, A03 FSYYYY-MM-DDYYYY-MM-DD[@vendor-lead]Yes
A05Example: Integration build1.3.230A04 SS+10YYYY-MM-DDYYYY-MM-DD[@tech-lead]No
A06Example: Training material development1.4.120A02 FSYYYY-MM-DDYYYY-MM-DD[@change-lead]No
A07Example: User acceptance testing1.3.315A04 FS, A05 FSYYYY-MM-DDYYYY-MM-DD[@test-lead]Yes
A08Example: Staff training delivery1.4.115A06 FS, A07 SS+5YYYY-MM-DDYYYY-MM-DD[@change-lead]No
A09Example: Production release1.5.13A07 FS, A08 FFYYYY-MM-DDYYYY-MM-DD[@ops-lead]Yes

4. Gantt chart

The chart shows the baseline schedule by workstream; critical path activities are highlighted.

5. Critical path

The critical path runs A01, A02, A04, A07, A09 to M4, with a total duration of [78] working days and zero float. Any slip on these activities moves go-live unless absorbed by the project buffer.

Near-critical paths (float of [5] days or less): [A05 Integration build, float 5 days]. These are monitored weekly alongside the critical path.

6. Resource loading

Resource demand per role and month is compared with availability; overallocations are resolved by levelling or by adding capacity.

RoleMonth 1Month 2Month 3Month 4Available FTEOverallocated
Example: Business analyst1.01.00.50.21.0No
Example: Developer02.03.52.03.0Month 3 (+0.5)
Example: Tester00.51.02.01.5Month 4 (+0.5)
[Role][x][x][x][x][x][Yes/No]

Levelling actions: [for example, shift A05 start by 5 days within its float; request 0.5 FTE tester from QA pool for month 4].

7. Schedule risks and buffers

The following risks could delay milestones; they are also recorded in the RAID log.

Risk IDRiskAffected activitiesExposure (days)Response
RSK-003Example: Vendor team ramps up lateA04, A0510Contract clause for named team; weekly staffing check
RSK-009Example: UAT testers unavailable during month-endA075Book testers now; avoid month-end week
[ID][Risk][IDs][n][Response]

Buffer policy: a project buffer of [10] working days sits before M4. Buffer consumption is reported as a percentage; more than [50%] consumed before UAT starts triggers a recovery plan.

Buffer consumed=Days of buffer usedTotal buffer days×100%\text{Buffer consumed} = \frac{\text{Days of buffer used}}{\text{Total buffer days}} \times 100\%

8. Schedule change log

Approved changes to the schedule baseline are recorded below.

DateChangeMilestones affectedDaysChange requestApproved by
YYYY-MM-DDExample: Added accessibility audit before UATM3, M4+5CR-004[@sponsor]
YYYY-MM-DD[Change][IDs][n][CR-xxx][@name]

Standard and licence note

Based on common project management practice for schedule development, critical path analysis and schedule control. This template is original text written for this collection. Template licence: MIT.