BIM Execution Plan Template (ISO 19650)

ISO 19650 BIM execution plan: roles, EIR response, CDE workflow, naming and status codes, level of information need, TIDP and MIDP

建設フルISO 19650-2:2018 clause 5; ISO 19650-1:2018; ISO 19650-5:2020; ISO 19650-6:2025; ISO 7817-1:2024bimexecutionplan

使い方: Use it when a delivery team responds to a client's exchange information requirements at tender or confirms its plan at appointment. Fill the EIR response matrix and the responsibility matrix first. The main pitfall is restating the EIR without saying who produces each item, when, and how it is checked.

プレビュー

BIM Execution Plan: [Project name]

The delivery team's plan for producing, checking and handing over project information on a building or infrastructure project: who does the information management, how the exchange information requirements will be met, the common data environment (CDE), naming and metadata, level of information need, and the delivery plans that schedule every information container. Structure aligned with the information management process of ISO 19650-2:2018 (clause 5), the concepts of ISO 19650-1:2018, and the security and health and safety parts ISO 19650-5:2020 and ISO 19650-6:2025. Replace every [bracketed] value and every row marked Example. Facts checked October 2026.

Document control

FieldValue
Document ID[FHL-QCN-ZZ-ZZ-RP-X-00001]
Project[Project name and code]
BEP stage[Pre-appointment (ISO 19650-2 5.3.2) / Confirmed at appointment (5.4.1)]
Responds to[Appointing party's EIR, ID and version], [Lead appointed party's EIR to task teams (5.4.3), ID and version]
Version[P01]
Status[S3 suitable for review and comment / A1 accepted]
Owner[Lead appointed party information manager, @name]
Approvers / reviewers[Appointing party information manager @name], [Lead appointed party project director @name]
Last updatedYYYY-MM-DD
Classification[Commercial in confidence; security-minded approach per section 11]
ISO 19650 editions applied[ISO 19650-1:2018, ISO 19650-2:2018, plus national annex if any, ISO 19650-5:2020, ISO 19650-6:2025]

Approvals

RoleNameDecisionDate
Lead appointed party, information manager[@name][Author]YYYY-MM-DD
Lead appointed party, project director[@name][Approved for submission]YYYY-MM-DD
Appointing party, information manager[@name][Accepted into appointment]YYYY-MM-DD

Revision history

VersionDateAuthorChange summary
P01YYYY-MM-DD[@name]Pre-appointment BEP for tender
C01YYYY-MM-DD[@name]Example: Confirmed at appointment; responsibility matrix detailed, TIDPs and MIDP linked
C02YYYY-MM-DD[@name]Example: Health and safety information requirements added for the handover stage

Contents

1. Project information

ItemValue
Asset and scopeExample: New three-storey library, 2,400 m2 gross internal area, steel frame, external works
Procurement routeExample: Two-stage design and build
Appointing partyExample: Fernhollow Town Trust
Lead appointed partyExample: Quillmere Construction
Project stages used[Your plan of work stages, for example strategic definition to handover]
Key information delivery milestones[Linked from the appointing party's milestones, ISO 19650-2 5.1.3]
Handover targetYYYY-MM-DD

2. Information management function and roles

RoleOrganisationNamed personTime committedResponsibilities
Information manager (delivery team)Example: Quillmere Construction[@name][0.6 FTE]Owns this BEP, the MIDP, CDE workflow and information model audits
Task information manager, architectureExample: Marrowpike Architects[@name][0.2 FTE]Owns the architecture TIDP and model quality checks
Task information manager, structureExample: Okeburn Structures[@name][0.2 FTE]Owns the structure TIDP
Task information manager, MEPExample: Tessaline Building Services[@name][0.3 FTE]Owns the MEP TIDP and coordination of services
Interface managerExample: Quillmere Construction[@name][0.2 FTE]Runs clash detection and coordination meetings
Appointing party information managerExample: Fernhollow Town Trust's agent[@name][As needed]Reviews and accepts the information model

3. Information requirements and response

3.1 Hierarchy of requirements

ISO 19650-1 describes how requirements cascade: organisational information requirements (OIR) and asset information requirements (AIR) from the asset owner, project information requirements (PIR) for the project, and exchange information requirements (EIR) for each appointment. The delivery team answers the EIR in this plan.

3.2 EIR response matrix

EIR IDRequirement (summary)Response: what is producedFormatResponsible task teamMilestoneAcceptance check
EIR-01 (Example)Federated design model for each stage gateFederated model plus clash reportIFC 4 and nativeArchitecture (lead), allEnd of each design stageClash report with no unresolved critical clashes
EIR-02 (Example)Space data for the library management systemRoom schedule with area, use, occupancySpreadsheet export from the modelArchitectureStage 4Areas within 1% of the measured drawing
EIR-03 (Example)Asset data for maintainable equipmentAsset register with attributes listed in the AIRSpreadsheet in the agreed asset data templateMEPHandoverEvery maintainable asset in the register has its required attributes
EIR-04 (Example)Health and safety information for the fileResidual risk register, as-built drawings, access and maintenance informationPDF and model attributesAll, coordinated by the principal designerHandoverSection 12 checks passed
[EIR-nn][Requirement][Response][Format][Team][Milestone][Criteria]

4. Information delivery strategy

  • Approach to the EIR: [How each requirement is produced, by whom and when, with reference to the response matrix in section 3.2.]
  • Collaboration goals: Example: single federated model reviewed every two weeks; design coordination before each stage gate; contractor input to buildability from stage 3.
  • Organisation and commercial relationships: Example: Quillmere Construction holds the appointment with the appointing party; design task teams are appointed by Quillmere under novated or direct appointments, each with its own TIDP.
  • Task team split: Example: architecture and landscape (one task team), structure, MEP, and the contractor's own construction sequencing team.

5. Federation strategy and volumes

Volume codeDescriptionOwning task team
ZZAll volumesAll
01 (Example)Library buildingArchitecture
02 (Example)External works and landscapeArchitecture
ST (Example)Structure, whole buildingStructure
ME (Example)Mechanical and electrical systemsMEP

Federation rules:

  • One discipline per model container; no team edits another team's container.
  • Shared coordinates and project base point set in the project information standard and checked at each upload.
  • Federated model assembled by the interface manager every [two weeks].

6. Responsibility matrix

Information elementDeliverableArchitectureStructureMEPContractorAppointing party
Example: Building fabricModel and drawingsRCCIA
Example: Structural frameModel, drawings, calculationsCRICA
Example: Building servicesModel, schematics, asset dataCIRCA
Example: Construction sequence4D programme modelICCRI
Example: Cost modelCost plansIIIRA
[Element][Deliverable][R/A/C/I]

R responsible, A accepts, C consulted, I informed.

7. Level of information need

PurposeMilestoneObject or systemGeometry (detail, dimension, location, appearance)Alphanumerical dataDocumentation
Example: Planning approvalStage 3 endExternal envelopeIndicative form and openingsMaterial typeElevations, materials schedule
Example: CoordinationStage 4Ductwork above 300 mmActual size, position within 25 mmSystem, sizeCoordination drawings
Example: Facilities managementHandoverAir handling unitsBounding box and access zoneManufacturer, model, serial number, warranty, maintenance intervalO&M manual section, test certificate
[Purpose][Milestone][Object][Geometry][Data][Documents]

8. Common data environment and workflow

ItemValue
CDE solution[Product and hosting, set by the appointing party under 5.1.7 or proposed by the delivery team]
Hosted byExample: Appointing party, with delivery team access
Access controlRole-based; task teams write only to their own work-in-progress areas
Backup and retention[Frequency, retention period, owner]
TransitionCheckWho
Work in progress to sharedQuality assurance check: naming, metadata, model health, content against the TIDP (ISO 19650-2 5.6.3, 5.6.4)Task team
Shared to publishedReview and authorise the information model (5.7.1, 5.7.2)Lead appointed party
Published, acceptedReview and accept against the EIR acceptance criteria (5.7.3, 5.7.4)Appointing party
Published to archivedArchive at close-out (5.8.1)Information manager

9. Naming, metadata and classification

9.1 Container naming

Example using the field order of the UK National Annex: Project, Originator, Volume or system, Level or location, Type, Role, Number.

FieldExample codeMeaning
ProjectFHLFernhollow Library and Learning Centre
OriginatorMPAMarrowpike Architects
Volume or system01Library building
Level or location02Second floor
TypeDRDrawing
RoleAArchitect
Number00201Sequential number

Resulting name: FHL-MPA-01-02-DR-A-00201.

9.2 Status and revision metadata

ISO 19650-1 asks for a status code and a revision code on every container. Example status codes used in UK guidance (check the national annex edition your project applies):

StatusMeaning (summary)CDE state
S0Initial status, work in progressWork in progress
S1Suitable for coordinationShared
S2Suitable for informationShared
S3Suitable for review and commentShared
S4Suitable for stage approvalShared
A1, A2Authorised and acceptedPublished
B1, B2Partial sign-off with commentsPublished
CRAs constructed recordPublished

Revisions: P01, P02 for preliminary; C01, C02 for contractual, with sub-revisions such as P01.1 while in work in progress. [Confirm against the project information standard.]

9.3 Classification

[Name the classification system, for example Uniclass, OmniClass or a national system, and the tables applied to elements, systems, products and spaces.]

10. Production methods, quality assurance and coordination

TopicMethod
Model set-upExample: Shared coordinates from the survey; template files issued by the information manager
Units and tolerancesMillimetres; modelling tolerance [5 mm]
Model health checksExample: Weekly automated check of naming, warnings, unused views, file size
Clash detectionExample: Every two weeks; rules and tolerances in the coordination procedure
Issue trackingBIM Collaboration Format (BCF) issues linked to the request for information log (construction/rfi-log)
Drawing productionDrawings generated from models; no 2D overdrawing of model geometry
Open formatsIFC 4 for exchange [confirm schema and model view], PDF for drawings, spreadsheet for data

10.1 Coordination meeting cycle

MeetingFrequencyInputsOutputs
Design coordinationEvery [two] weeksFederated model, clash reportBCF issues assigned with due dates
Information model reviewBefore each milestoneTIDP status, quality reportsGo or no-go to publish

11. Security-minded information management

ItemValue
Security triage outcome[Sensitive / not sensitive, decided by the appointing party]
Security management plan reference[ID, if one exists]
Information not to be sharedExample: Security system layouts and locations of cash handling areas
ControlsExample: Restricted CDE folder, named access, no export to personal devices, watermarking on published drawings
Incident reporting[How a security breach involving project information is reported]

12. Health and safety information

InformationProduced byWhenWhere heldFeeds
Design residual risksEach designerEach design stageRisk attributes in the model and the risk registerPre-construction information, construction phase plan (construction/construction-phase-plan)
Construction risks and RAMSContractorsBefore each activityCDE, RAMS folder (construction/rams)Site management
Health and safety file contentPrincipal designer with all teamsThrough construction, final at handoverCDE, handover folderHealth and safety file in construction/punch-list-handover

13. Delivery plans and milestones

TIDP or MIDPOwnerLocationLast baselined
MIDPInformation manager[CDE link]YYYY-MM-DD
TIDP architectureTask information manager, architecture[CDE link]YYYY-MM-DD
TIDP structureTask information manager, structure[CDE link]YYYY-MM-DD
TIDP MEPTask information manager, MEP[CDE link]YYYY-MM-DD

MIDP extract (Example):

ContainerDescriptionTask teamLevel of information need ref.Due milestoneDue dateStatus
FHL-MPA-01-ZZ-M3-A-00001Architecture modelArchitectureLOIN-04-ARCHStage 4 coordinationYYYY-MM-DDS1
FHL-OKS-ST-ZZ-M3-S-00001Structural modelStructureLOIN-04-STRStage 4 coordinationYYYY-MM-DDS1
FHL-TBS-ME-ZZ-M3-M-00001Mechanical modelMEPLOIN-04-MEPStage 4 coordinationYYYY-MM-DDS0
FHL-QCN-ZZ-ZZ-SH-X-00010Asset register for handoverContractorLOIN-HO-ASSETHandoverYYYY-MM-DDNot started

14. Software, hardware and IT infrastructure

UseSoftware and versionUsed byExchange format
Authoring, architecture[Product, version]ArchitectureNative and IFC
Authoring, structure[Product, version]StructureNative and IFC
Authoring, MEP[Product, version]MEPNative and IFC
Federation and clash[Product, version]Interface managerIFC, BCF
CDE[Product]AllNot applicable
Hardware minimum[Specification]AllNot applicable

15. Mobilisation, capability and risk

15.1 Capability and capacity

Task teamAssessed capabilityCapacity (people)Gaps and actions
Example: ArchitectureIFC export tested, BCF in use4 modellersNone
Example: MEPNo previous use of the asset data template3 modellersTraining session before stage 4
[Team][Capability][n][Action]

15.2 Mobilisation plan

  1. Issue templates, shared coordinates and the project information standard to all task teams.
  2. Grant CDE access and test the workflow with a sample container through every state (ISO 19650-2 5.5.3).
  3. Run a trial federation and clash test before the first coordination meeting.
  4. Confirm the TIDPs and baseline the MIDP.

15.3 Information delivery risks

IDRisk (cause, event, effect)LikelihoodImpactResponseOwner
IR-01 (Example)Because the MEP team is new to the asset data template, handover data may be incomplete, delaying acceptanceMediumHighTraining, early sample submission at stage 4MEP task information manager
IR-02 (Example)Because the CDE is hosted by the appointing party, access delays may hold up sharingLowMediumAccess requests at mobilisation, named backup administratorInformation manager
[IR-nn][Risk][L][I][Response][@owner]

Project-wide risks belong in the RAID log (project/raid-log).

16. Glossary and references

16.1 Glossary

TermMeaning in this plan
Appointing partyThe client receiving information from the lead appointed party
Lead appointed partyThe party appointed directly by the appointing party that coordinates a delivery team
Task teamA group of people doing one specific part of the information production
EIRExchange information requirements: what the appointing party needs from an appointment, with format, timing and acceptance criteria
CDECommon data environment: the agreed source of information for the project, with a managed workflow between states
Information containerA named, persistent set of information, such as a model file, drawing or schedule
Level of information needThe quality, quantity and granularity of information required for a defined purpose
TIDP, MIDPTask information delivery plan; master information delivery plan compiled from all TIDPs
FederationCombining separate discipline models into one coordinated view without merging the source files

16.2 References

ISO 19650 is a paid standard. This template cites part, edition and clause numbers only, in original wording.

  • ISO 19650-1:2018, Concepts and principles, ISO.
  • ISO 19650-2:2018, Delivery phase of the assets, ISO. Clause 5 activities 5.1 to 5.8 are used for the section structure.
  • ISO 19650-5:2020, Security-minded approach to information management, ISO.
  • ISO 19650-6:2025, Health and safety information, ISO.
  • ISO 7817-1:2024, Level of information need, concepts and principles, ISO.
  • Official text: ISO and national standards bodies (for example BSI for BS EN ISO 19650 with the UK National Annex), purchase or licensed access: ISO catalogue search, BSI Knowledge.
  • UK BIM Framework, free guidance on applying ISO 19650, including Guidance Part 2 (Edition 3, January 2020) on the BEP contents and status codes, ukbimframework.org.
  • Related templates: construction/construction-phase-plan, construction/rfi-log, construction/punch-list-handover, project/project-management-plan, project/raid-log, compliance/iso-55001-samp.

Standard and licence note

Structure aligned with ISO 19650-2:2018 clause 5 (information management process during the delivery phase), with concepts from ISO 19650-1:2018, ISO 19650-5:2020, ISO 19650-6:2025 and ISO 7817-1:2024, as checked in October 2026. The text is original and reproduces no wording, tables or definitions from these standards. Official text: ISO and national standards bodies, purchase or licensed access at the links in section 16.2. A revision of Parts 1 to 3 was in draft in 2026; check the current editions and the version named in your appointment. Template licence: MIT.