One PDSA test of change: Model for Improvement aim and measures, driver diagram, plan with prediction, do, study, act, ramp of cycles, run chart with rules

의료표준IHI Model for Improvement (Langley et al. 2009); run chart rules (Perla et al. 2011)pdsacyclediagram

사용법: Use it for each small test of change in a quality improvement project. Fill the aim, the measures and the prediction first, before the test runs. The main pitfall is claiming improvement from before and after averages instead of applying the run chart rules.

미리보기

PDSA Cycle Worksheet: [Change idea being tested]

Worksheet for one Plan-Do-Study-Act (PDSA) test of change, set inside the three questions of the Model for Improvement, with a ramp log for linked cycles and a run chart of the outcome measure. The Model for Improvement was developed by Associates in Process Improvement and is described in Langley GJ et al., The Improvement Guide (2nd edition, Jossey-Bass, 2009); IHI teaches it as its core improvement method. Run chart rules follow Perla, Provost and Murray, BMJ Quality and Safety 2011. Replace every [bracketed] value and every row marked Example. This is a quality improvement format, not medical advice; follow local policy, clinical judgement and your organisation's governance process. Use aggregate, de-identified data only.

Document control

FieldValue
Document ID[PDSA-PROJ-NN-C1]
Project[Project name and ID]
Cycle number[1 / 2 / 3]
Team[Names, roles]
Sponsor[Name, role]
Version[1.0]
Status[Planned / Running / Studied / Closed]
Owner[@qi-lead]
Approvers/reviewers[@clinical-lead], [@qi-team]
Last updatedYYYY-MM-DD
Classification[Internal, aggregate data only]

Revision history

VersionDateAuthorChange
0.1YYYY-MM-DD[Name]Plan and prediction written
1.0YYYY-MM-DD[Name]Study and Act completed

1. Model for Improvement

QuestionAnswer
What are we trying to accomplish? (aim)[Measure, from baseline to target, for which population, by when]
How will we know that a change is an improvement? (measures)[Outcome, process and balancing measures, section 2]
What change can we make that will result in improvement? (change ideas)[Change ideas from the driver diagram, section 3]

Example: Aim: on Ward 5 of the fictional Halvermoor District Hospital, raise the share of adult admissions with medicines reconciled within 24 hours from a baseline of 46.1% (149 of 323, eight weeks) to 75% by YYYY-MM-DD.

2. Measures

IDTypeDefinition (numerator / denominator)SourceFrequencyOwner
M-01 (Example)OutcomeAdmissions with a completed reconciliation within 24 hours of the decision to admit / all adult admissions to Ward 5Electronic record reportWeekly[Pharmacy lead]
M-02 (Example)ProcessAdmissions with a best possible medication history taken from two or more sources / all adult admissionsWeekly audit of 10 recordsWeekly[Ward pharmacist]
M-03 (Example)BalancingPharmacy technician minutes spent on the ward per dayTime logWeekly[Pharmacy manager]

3. Driver diagram and change ideas

Read the diagram from left to right: the aim, the primary drivers that must change to reach it, the secondary drivers under each, and the change ideas the team will test. Example below.

4. This cycle

Plan

ItemDetail
Objective of this cycle[What you want to learn]
Change being tested[Change idea ID and description]
Prediction[What you expect to happen, with a number]
Who[People involved]
Where[Unit, bay, clinic]
When[Dates, shifts]
Data to collect[Measure IDs, plus notes on problems]

Example: Cycle C1 tests CI-01 on one bay for one week. Prediction: technician-led histories will raise M-01 above 55% that week, and each history will take under 20 minutes.

Do

Record what happened, including problems and observations that were not part of the plan.

Example: The technician took 14 histories. Two patients were too unwell to be interviewed, so the GP record and the patient's own list were used. Median time per history was 18 minutes.

Study

Compare the results with the prediction. What did you learn?

MeasurePredictionResultMatches?
M-01 (Example)Above 55%58.5% (24 of 41)Yes
Time per history (Example)Under 20 minutesMedian 18 minutesYes

Act

Choose one: adopt, adapt or abandon, and define the next cycle.

DecisionReasonNext cycle
Example: AdaptWorked on weekdays, weekend admissions missedC2: extend to all weekday admissions, C3: test CI-03 at weekends

5. Ramp of cycles

CycleWeeksChangeScaleDecision
C1 (Example)9CI-01 technician historyOne bay, weekdaysAdapt
C2 (Example)10 to 11CI-01 plus CI-02Whole ward, weekdaysAdopt
C3 (Example)12 to 16CI-03 weekend rotaWhole ward, seven daysAdopt, hand over to business as usual

6. Run chart

WeekW1W2W3W4W5W6W7W8W9W10W11W12W13W14W15W16
Reconciled (Example)18201721191620182426272928303130
Admissions (Example)40423941403843404140394240414240
Percent (Example)45.047.643.651.247.542.146.545.058.565.069.269.070.073.273.875.0

Run chart rules (Perla, Provost and Murray 2011), applied to the example:

RuleSignal of non-random changeExample result
ShiftSix or more consecutive points all above or all below the median (points on the median are skipped)Met: weeks 9 to 16, eight points above the baseline median of 45.75%
TrendFive or more consecutive points all going up or all going downMet at the limit: weeks 12 to 16 are five consecutive points, each higher than the one before, from 69.0% to 75.0%
RunsToo few or too many runs for the number of points, read from the published tableNot used: the median was frozen at baseline
Astronomical pointA point obviously different from all others, agreed by people who know the processNone

Example summary: weeks 1 to 8 reconciled 149 of 323 admissions (46.1%); weeks 9 to 16 reconciled 225 of 325 (69.2%); the last four weeks reconciled 119 of 163 (73.0%). The shift shows a non-random improvement, but the 75% aim is not yet met in a sustained way.

7. Learning and next steps

  • What we learned: [Key learning in two or three lines]
  • Surprises: [What happened that you did not predict]
  • Next cycle or handover: [Next test, or how the change becomes standard work and who owns the measure]
  • Write-up: [Link to the quality improvement report, if the project will be reported]

References

ReferenceStatusUse
IHI, How to Improve: Model for Improvement, https://www.ihi.org/library/model-for-improvementChecked 2026-10-30Three questions, PDSA, credit to Associates in Process Improvement
Langley GJ, Moen RD, Nolan KM, Nolan TW, Norman CL, Provost LP. The Improvement Guide: A Practical Approach to Enhancing Organizational Performance. 2nd ed. San Francisco: Jossey-Bass; 2009Cited from IHI pageSource of the Model for Improvement. Official text: Jossey-Bass (Wiley), purchase or licensed access: https://www.wiley.com/
IHI, Plan-Do-Study-Act (PDSA) Worksheet, https://www.ihi.org/library/tools/plan-do-study-act-pdsa-worksheetChecked 2026-10-30One worksheet per test (free download after a form)
Perla RJ, Provost LP, Murray SK. The run chart: a simple analytical tool for learning from variation in healthcare processes. BMJ Qual Saf 2011;20(1):46-51, https://doi.org/10.1136/bmjqs.2009.037895Citation checked on PubMed 2026-10-30Run chart rules

Standard and licence note

Structure aligned with the Model for Improvement and PDSA cycle as described publicly by IHI (page checked 2026-10-30) and in The Improvement Guide (2nd edition, 2009), with run chart rules from Perla, Provost and Murray (2011). This template is original text written for this collection; it does not reproduce the IHI worksheet or the book. All names, wards and figures in examples are fictional. This is a quality improvement format, not medical advice; check the current official pages and follow local governance. Template licence: MIT.