# Daily Site Report: [Project name], YYYY-MM-DD

> A one-day record of a construction site: weather, labour and plant on
> site, work done against the programme, deliveries, visitors,
> inspections, health and safety events, delays and instructions
> received. Based on common construction practice. Daily records are
> often the main evidence when a delay, change or claim is assessed
> later, so complete it the same day. Replace every `[bracketed]` value
> and every row marked *Example*.

<!--
Guidance: How to use this template
- Record facts, times and numbers, not opinions. "Rain 10:20 to 13:45,
  concrete pour stopped" is evidence; "bad weather" is not.
- Photographs: reference them by file name in the sections where they
  apply.
- Report incidents here and in the incident log on the same day; this
  report does not replace any statutory report (see the construction
  phase plan, `construction/construction-phase-plan`, section 12).
- Fictional example: Fernhollow Library and Learning Centre (code FHL),
  principal contractor Quillmere Construction. All names are invented.
-->

## Document control

| Field | Value |
|---|---|
| Report number | [DSR-FHL-0187] |
| Date and shift | YYYY-MM-DD, [07:30 to 17:00] |
| Prepared by | [Site manager, @name] |
| Distributed to | [Project manager, client representative] |

## 1. Weather and site conditions

| Time | Conditions | Temperature | Wind | Effect on work |
|---|---|---|---|---|
| 08:00 *(Example)* | Overcast, dry | 9 C | 15 km/h | None |
| 10:20 to 13:45 *(Example)* | Heavy rain | 8 C | 30 km/h | Roof work stopped; crane lifts paused per lift plan weather limits |

## 2. Labour on site

<!-- Guidance: Count people by contractor and trade from the sign-in record. Hours feed daywork and productivity checks. -->

| Contractor | Trade | Workers | Hours each | Total hours |
|---|---|---|---|---|
| Quillmere Construction *(Example)* | Management and labourers | 6 | 9 | 54 |
| Roofing contractor *(Example)* | Roofers | 4 | 8 | 32 |
| Steel erector *(Example)* | Erectors | 5 | 8 | 40 |
| MEP contractor *(Example)* | Electricians, fitters | 12 | 8 | 96 |
| **Total** *(Example)* | | **27** | | **222** |

## 3. Plant and equipment

| Item | Number | Hours worked | Hours idle | Reason idle |
|---|---|---|---|---|
| Mobile crane 50 t *(Example)* | 1 | 5.5 | 3.5 | Rain 10:20 to 13:45 |
| Telehandler *(Example)* | 1 | 7 | 1 | |

## 4. Work done and progress

| Area or activity | Programme ID | Work done today | Status |
|---|---|---|---|
| Roof zone 2 *(Example)* | 3.4.2 | Rooflight RL-01 opening cut, trimmers fixed | Behind 1 day, weather |
| Level 2 first fix electrical *(Example)* | 5.2.1 | Containment 60% complete | On programme |

## 5. Deliveries, visitors and inspections

| Time | Type | Detail |
|---|---|---|
| 09:10 *(Example)* | Delivery | Two rooflight units, delivery note DN-55812, checked and stored |
| 14:00 *(Example)* | Inspection | Scaffold weekly inspection, register signed |
| 15:30 *(Example)* | Visitor | Client representative, escorted |

## 6. Health, safety and environment

| Item | Count | Detail and reference |
|---|---|---|
| Accidents | *Example:* 0 | |
| Near misses | *Example:* 1 | Unsecured cover near roof opening, corrected; NM-FHL-022 |
| Toolbox talks and RAMS briefings | *Example:* 1 | RAMS-FHL-011 briefed to roofing team |
| Environmental events | *Example:* 0 | |

## 7. Delays, instructions and issues

| Item | Detail | Reference |
|---|---|---|
| Delay | *Example:* Roof works stopped 3.4 hours for rain | Programme 3.4.2 |
| Instruction received | *Example:* Proceed with two extra rooflights | EI-031, VO-007 |
| RFI raised | *Example:* Drain found at grid A/1 | RFI-043 (`construction/rfi-log`) |

## Standard and licence note

Based on common construction site management practice for daily
records. The text is original. Check your contract for any required
record format or submission period. Template licence: MIT.