Architecture Roadmap and Transition Architectures Template (TOGAF E, F)

Consolidated gaps, work packages, Transition Architectures, dependencies, value and risk per increment, migration plan, costs, Phase G hand-off

Архітектура та системний дизайнПовнийThe TOGAF Standard, 10th Edition (2025 Update), ADM Phases E and Froadmaptransitionmath

Як використовувати: Use it once the Architecture Definition Document is approved to sequence the change into work packages and stable plateaus. Fill the consolidated gaps and work packages first, then define each Transition Architecture by the state it reaches, not by a date. The main pitfall is front-loading all enabling work so that no increment delivers visible value for a year.

Перегляд

Architecture Roadmap and Transition Architectures: [Architecture engagement name]

Architecture Roadmap, Transition Architectures and Implementation and Migration Plan for one engagement, the outputs of Phases E (Opportunities and Solutions) and F (Migration Planning) of the Architecture Development Method in The TOGAF Standard, 10th Edition (2025 Update). It consolidates the gaps, groups them into work packages, defines the plateaus between baseline and target, analyses dependencies, value and risk per increment, estimates resources and cost, and hands the plan to Phase G. Replace every [bracketed] value and every row marked Example.

Document control

FieldValue
Document ID[ARM-ENG-001]
Engagement[Architecture engagement name]
ADM phasesPhase E, Phase F
Based on[ADD-ENG-001, version]; [AV-ENG-001, version]
Planning baseline dateYYYY-MM-DD
Planning horizon[24 months]
Version[0.1]
Status[Draft / In review / Approved / Superseded]
Owner (lead architect)[@lead-architect]
Programme manager[@programme-manager]
Approvers / reviewers[Architecture Board, sponsor, portfolio board, finance]
Classification[Internal / Confidential]
Last updatedYYYY-MM-DD

Approvals

RoleNameDecisionConditionsDate
Sponsor[@sponsor][Approved / Approved with conditions / Rejected][Conditions]YYYY-MM-DD
Architecture Board chair[@chair][Decision][Conditions]YYYY-MM-DD
Portfolio board[@portfolio-lead][Decision][Conditions]YYYY-MM-DD
Finance partner[@finance][Decision][Conditions]YYYY-MM-DD

Revision history

VersionDateAuthorChange summary
0.1YYYY-MM-DD[@name]Consolidated gaps and first work package grouping
0.5YYYY-MM-DD[@name]Example: Transition Architectures, value and risk assessment, cost estimate
1.0YYYY-MM-DD[@name]Example: Approved at board gate 3; handed to implementation governance

Contents

1. Introduction

1.1 Purpose

This document turns the gaps between baseline and target architecture into an ordered set of work packages, grouped into Transition Architectures that each deliver measurable value. It is the basis for portfolio funding, for Architecture Contracts with delivery teams and for measuring progress toward the target.

1.2 Inputs

InputReferenceStatus
Architecture Vision[AV-ENG-001][Approved YYYY-MM-DD]
Architecture Definition Document[ADD-ENG-001][Approved YYYY-MM-DD]
Architecture Requirements Specification[Section 9 of ADD-ENG-001 or separate document][Status]
Current portfolio and capacity[Portfolio plan reference][Status]
Business constraintsExample: CNS-01 budget cap, CNS-03 contract renewal, CNS-04 year-end freezeConfirmed
[Input][Reference][Status]

2. Implementation factors

Factor IDFactorCategoryConsequence for the plan
IMF-01 (Example)Integration team is shared with two other programmesResourceBuild the integration platform first, before parallel streams start
IMF-02 (Example)Policy administration contract renewal date YYYY-MM-DDContractDecide on policy system C consolidation before month 12
IMF-03 (Example)Year-end claims peak in [month]OperationalNo cut-over in [month]; plan go-live windows around it
IMF-04 (Example)Data quality in policy system C is lowRiskStart remediation in the first Transition Architecture
IMF-05 (Example)Staff consultation needed for organisation changeOrganisationalStart consultation three months before the new teams go live
IMF-06 (Example)Capital budget phased over two financial yearsFinancialKeep year 1 spend below the approved year 1 envelope
[IMF-nn][Factor][Risk / Issue / Resource / Contract / Operational / Financial / Organisational][Consequence]

3. Consolidated gaps, solutions and dependencies

Gap IDsGap summaryProposed solutionSolution typeDepends onWork package
GAP-T-01, GAP-T-02, GAP-T-03, GAP-T-04 (Example)No modern integration or hosting for claimsManaged cloud hosting, API gateway, event streaming, observabilityReuse platform and configureNoneWP-01
GAP-D-01, GAP-D-03 (Example)No customer master or consent recordCustomer data hub with matching, stewardship and consentBuyWP-01WP-02
GAP-D-01 (quality) (Example)Poor data in policy system CData cleansing and stewardship routinesProcess and toolingNoneWP-02
GAP-A-01, GAP-B-01, GAP-B-04, GAP-B-05, GAP-D-02 (Example)Single manual claims path on aging system; monthly paper reportingClaims platform package with triage rules, structured loss data and a daily claims dashboardBuy and configureWP-01, WP-02WP-03
GAP-A-02, GAP-A-03, GAP-B-03 (Example)No self-service; handlers use five screensPortal, partner channel, handler workspaceBuild on platformWP-03WP-04
GAP-A-05 (Example)Policy system C end of lifeMigrate policies to consolidated policy administrationMigrateWP-02WP-05
GAP-B-02 (Example)Product-line teamsCross-product claims teams and trainingOrganisational changeWP-03WP-06
GAP-A-04, GAP-D-04 (Example)Legacy CRM still runningArchive, switch off and terminate licenceDecommissionWP-02, WP-04WP-07
[GAP-x-nn][Summary][Solution][Reuse / Buy / Build / Migrate / Decommission / Organisational][WP-nn][WP-nn]

4. Work packages

WP IDWork packageOutcomeCandidate componentsOwnerEstimate (kUSD)
WP-01 (Example)Cloud and integration foundationClaims domain can run in the cloud and integrate through APIs and eventsCRC-11, CRC-12, CRC-13[@platform-lead]260
WP-02 (Example)Customer data hub and data qualityOne golden customer record with consentCRC-04, CRC-05[@data-owner]420
WP-03 (Example)Claims platform and triageSimple claims decided automaticallyCRC-01, CRC-06, CRC-07[@claims-it-lead]520
WP-04 (Example)Digital channels and handler workspaceCustomers and partners self-serve; handlers use one workspaceCRC-03, CRC-08[@digital-lead]300
WP-05 (Example)Policy system C consolidationPolicy system C switched offCRC-09[@policy-it-lead]460
WP-06 (Example)Claims organisation changeCross-product teams working the new processCRC-02[@head-of-claims]80
WP-07 (Example)Legacy CRM decommissioningCRM switched off and archivedCRC-10[@application-owner]60
Total2,100

Use a project charter (business/project-charter) for each work package that becomes a project.

5. Transition Architectures

5.1 Plateau overview

Example: three plateaus over 24 months. Each arrow is crossed only when the exit criteria in section 8 are met and the Architecture Board has completed its compliance review for that state.

5.2 Transition Architecture definitions

IDNameWork packages completedArchitecture state reachedKPIs expected to move
TA-1 (Example)FoundationWP-01, WP-02Integration platform live; hub is master for customers from policy systems A and B; system C data cleansed and loaded read-onlyKPI-02 to 60%
TA-2 (Example)Digital claimsWP-03, WP-04, WP-06New claims platform with triage; portal, partner channel and workspace live; old claims system read-onlyKPI-01 to 50%, KPI-03 down 12%
Target (Example)ConsolidatedWP-05, WP-07Policy system C and legacy CRM retired; all customers mastered in the hubKPI-01 70%, KPI-02 98%, KPI-03 down 20%, KPI-04 met
[TA-n][Name][WP-nn][State][KPI movement]

5.3 State evolution by building block

Building blockBaselineTA-1TA-2Target
Example: IntegrationFile transferGateway and events (new); files remain for claimsFiles retired for claimsFiles retired
Example: Customer masterNoneHub for systems A and BHub for A, B and channelsHub for all sources
Example: Claims systemLegacyLegacyNew platform; legacy read-onlyLegacy archived
Example: Policy system CLiveLive, data cleansedLiveRetired
Example: Legacy CRMLiveLiveRead-onlyRetired
[Building block][State][State][State][State]

6. Dependency analysis

Dependency IDFromToTypeNote
DEP-01 (Example)WP-02WP-01TechnicalHub runs on the cloud platform and publishes events
DEP-02 (Example)WP-03WP-02DataTriage needs golden customer and cover data
DEP-03 (Example)WP-04WP-03TechnicalChannels call claims platform APIs
DEP-04 (Example)WP-06WP-03BusinessNew teams work on the new process only
DEP-05 (Example)WP-05WP-02DataMigrated policies reference golden customer IDs
DEP-06 (Example)WP-07WP-04BusinessService desk moves to the workspace before CRM switch-off
DEP-07 (Example)WP-03 and WP-05Integration teamResourceSame team; do not overlap their integration peaks
[DEP-nn][WP-nn][WP-nn or resource][Technical / Data / Business / Resource][Note]

Critical path (Example): WP-01, WP-02, WP-03, WP-04, WP-07.

7. Business value and risk per increment

IncrementBusiness valueValue score (1 to 5)Delivery riskRisk score (1 to 5)Annual benefit (kUSD)
TA-1 (Example)Customer data trusted for two policy lines; file transfer licence reduced3Matching accuracy, cloud readiness390
TA-2 (Example)Simple claims decided in 48 hours; handler productivity5Package fit, staff adoption4450
Target (Example)Two legacy systems retired; lower run cost4Policy migration complexity4290
Total830

Benefits are tracked after delivery in the benefits realization plan (project/benefits-realization-plan).

8. Architecture Roadmap

MilestoneDateGateExit criteria
TA-1 reached (Example)2027-08-30Board compliance reviewHub mastering A and B customers; integration platform in production; KPI-02 at least 60%
TA-2 reached (Example)2028-04-24Board compliance reviewTriage live for motor and home; KPI-01 at least 50%
Target reached (Example)2028-12-18Board compliance reviewPolicy system C and CRM retired; KPI targets met or plan agreed
[Milestone]YYYY-MM-DD[Gate][Criteria]

Publish a business-facing version of the roadmap with the product roadmap template (product/roadmap) when needed.

9. Implementation and Migration Plan

9.1 Delivery approach per work package

WP IDDelivery approachMigration strategyCoexistence periodRollback
WP-01 (Example)Platform team, iterativeNot applicable (new)NoneNot applicable
WP-02 (Example)Vendor plus internal data teamIncremental by source systemHub and local stores in sync for 6 monthsRevert consumers to local stores
WP-03 (Example)Package configuration, agile releasesNew claims on new platform; open claims run off on legacy4 monthsRoute new claims back to legacy
WP-04 (Example)Product teamsNew channels added beside phone and e-mailPermanent (channels coexist)Disable channel
WP-05 (Example)Migration factoryWave migration by product linePer waveWave rollback plan
WP-06 (Example)HR-led change programmeTeam by team2 months per teamReturn to old team structure
WP-07 (Example)Application ownerArchive then switch off1 month read-onlyRestore from archive
[WP-nn][Approach][Strategy][Period][Rollback]

Detail migration waves and cut-over runbooks in the migration wave plan (project/migration-wave-plan).

9.2 Decommissioning plan

SystemRetire afterData dispositionContract actionOwner
Example: Legacy claims systemTA-2 plus 4 monthsArchive closed claims for retention periodNot applicable (owned)[@claims-it-lead]
Example: Legacy CRMTargetArchive contact history; delete beyond retentionGive notice by YYYY-MM-DD[@application-owner]
Example: Policy system CTargetMigrate active policies; archive closed onesTerminate support contract[@policy-it-lead]
[System][Milestone][Disposition][Action][@owner]

9.3 Delivery risks

Risk IDRiskLikelihoodImpactMitigationOwner
RMR-01 (Example)Integration team overloaded when WP-03 and WP-05 overlapHighHighStagger integration peaks; add partner capacity[@programme-manager]
RMR-02 (Example)Package upgrade during WP-03 breaks configurationMediumMediumFreeze package version until TA-2[@claims-it-lead]
RMR-03 (Example)Contract notice date for CRM missedLowHighCalendar reminder and board milestone[@application-owner]
[RMR-nn][Risk][H / M / L][H / M / L][Mitigation][@owner]

Carry these into the programme RAID log (project/raid-log).

10. Resource and cost estimates

10.1 Cost per increment

IncrementWork packagesCost (kUSD)
TA-1 (Example)WP-01 (260), WP-02 (420)680
TA-2 (Example)WP-03 (520), WP-04 (300), WP-06 (80)900
Target (Example)WP-05 (460), WP-07 (60)520
Total2,100

10.2 Contingency, effort and payback

Example assumptions: contingency of 15%, labour at 60% of base cost, blended rate of 0.8 kUSD per person-day, and annual benefits of 830 kUSD once the target is reached (section 7).

Cbase=∑i=17CWPi=680+900+520=2100 kUSDC_{\text{base}} = \sum_{i=1}^{7} C_{\text{WP}_i} = 680 + 900 + 520 = 2100 \text{ kUSD}
Ctotal=Cbase×(1+0.15)=2100×1.15=2415 kUSDC_{\text{total}} = C_{\text{base}} \times (1 + 0.15) = 2100 \times 1.15 = 2415 \text{ kUSD}
E=0.60×Cbase0.8=12600.8=1575 person-daysE = \frac{0.60 \times C_{\text{base}}}{0.8} = \frac{1260}{0.8} = 1575 \text{ person-days}
Tpayback=CtotalBannual=2415830≈2.9 yearsT_{\text{payback}} = \frac{C_{\text{total}}}{B_{\text{annual}}} = \frac{2415}{830} \approx 2.9 \text{ years}

The total of USD 2,415 thousand stays within the capital cap of USD 2.5 million (constraint CNS-01). The simple payback ignores benefits realised before the target state; a full discounted analysis belongs in the business case (business/business-case) or the TCO analysis (architecture/tco-analysis).

10.3 Resource plan

RoleTA-1 (FTE)TA-2 (FTE)Target (FTE)Source
Example: Platform engineers311Internal platform team
Example: Integration engineers232Internal plus partner
Example: Data engineers and stewards312Internal data team
Example: Claims package specialists040Vendor
Example: Product team (channels)050Internal digital team
Example: Migration factory004Partner
[Role][FTE][FTE][FTE][Source]

11. Governance hand-off to Phase G

11.1 Architecture Contracts to issue

Contract IDWork packageDelivery partyKey architecture requirementsReview points
AC-01 (Example)WP-01Platform teamARS-TEC-01, ARS-DAT-02Design, pre-production
AC-02 (Example)WP-02Data hub vendor and data teamARS-DAT-01, ARS-INT-01Design, pre-production, TA-1
AC-03 (Example)WP-03Claims package vendorARS-BUS-01, ARS-APP-01Design, pre-production, TA-2
[AC-nn][WP-nn][Party][ARS IDs][Points]

Contracts and compliance reviews follow the Architecture Board charter (architecture/architecture-governance-charter). Delivery teams submit designs with the architecture review request (architecture/architecture-review-request).

11.2 Roadmap change control

Change typeDecided byRecord
Date change within an increment, no change to Transition ArchitectureProgramme managerProgramme log
Work package scope or cost change above [10%]Architecture Board and sponsorChange request and new roadmap version
Change to a Transition Architecture or the targetArchitecture BoardChange request; Phase H assessment
New gap or requirementLead architect, then BoardRequirements impact assessment

11.3 Monitoring after hand-off

[Describe how progress toward each Transition Architecture is reported to the board: KPI dashboard, quarterly roadmap review, and fitness functions where they can be automated (architecture/fitness-functions).] Track architecture debt accepted during delivery in the tech debt register (architecture/tech-debt-register).

12. Glossary and references

12.1 Glossary

TermMeaning in this document
Work packageA unit of change with one owner, an outcome and an estimate
Transition ArchitectureA stable, operable architecture state between baseline and target
PlateauA synonym for a stable intermediate architecture state, used in modelling
Architecture RoadmapThe ordered set of work packages and transitions from baseline to target
Implementation and Migration PlanHow the work packages are delivered and how the enterprise moves between states
Architecture ContractAgreement between the architecture function and a delivery party on what must be built and how compliance is checked
Critical pathThe chain of dependent work packages that sets the earliest completion date
[Term][Meaning]

12.2 References

IDReferenceVersion / date
REF-01The TOGAF Standard, 10th Edition (The Open Group), 2025 UpdateJune 2025
REF-02Architecture Vision (architecture/togaf-architecture-vision)[x.y]
REF-03Architecture Definition Document (architecture/architecture-definition-document)[x.y]
REF-04Architecture Board Charter (architecture/architecture-governance-charter)[x.y]
REF-05Migration wave plan (project/migration-wave-plan)[x.y]
REF-06Application portfolio rationalization (architecture/application-portfolio-rationalization)[x.y]
REF-07Business case (business/business-case)[x.y]

Standard and licence note

Structure aligned with The TOGAF Standard, 10th Edition (2025 Update), published by The Open Group: Phase E (Opportunities and Solutions) and Phase F (Migration Planning) of the Architecture Development Method, the Architecture Roadmap, Transition Architectures and the Implementation and Migration Plan, with consolidated gaps, dependencies and a value and risk assessment per increment. Only phase and deliverable names are used; this template is original text and reproduces no definitions, tables or other text from the standard. TOGAF is a registered trademark of The Open Group. Check the current edition at opengroup.org and obtain the standard for its full guidance. Template licence: MIT.