Project Closure Report: [Project name]

Formal report that closes a project: summary, objectives versus outcomes, scope, schedule and cost performance, quality results, benefits status and handover, transfer of open items, lessons, contract closure, resource release, archive and sign-off. Based on common project management practice. Replace every [bracketed] value and every row marked Example.

Document control

FieldValue
Document ID[PCR-PROJECT-001]
Project[Project name] ([code])
Sponsor[@sponsor]
Project manager[@project-manager]
Project startYYYY-MM-DD
Project endYYYY-MM-DD
Version[0.1]
Status[Draft / In review / Approved]
Classification[Internal]
Last updatedYYYY-MM-DD

Approvals

RoleNameDecisionDate
Project sponsor[@name][Project closed / Closed with conditions]YYYY-MM-DD
Steering committee chair[@name][Decision]YYYY-MM-DD
Receiving operations owner[@name][Handover accepted]YYYY-MM-DD
Finance controller[@name][Accounts closed]YYYY-MM-DD

Revision history

VersionDateAuthorChange summary
0.1YYYY-MM-DD[@name]Draft during hypercare
1.0YYYY-MM-DD[@name]Example: Approved by sponsor; project formally closed

Contents

1. Closure summary

[Project name] ran from YYYY-MM-DD to YYYY-MM-DD to [purpose]. This section gives the overall verdict; the following sections provide the evidence.

Example: The project delivered the digital onboarding service, which went live on YYYY-MM-DD, 3 working days after the original baseline and within the approved schedule tolerance. Final cost was 468,200 EUR against a budget at completion of 478,500 EUR (2.2% under), after 30,000 EUR of contingency was allocated to approved change requests. All Must-have scope was delivered; one Should-have item was deferred to the service roadmap. Early benefit measurements show onboarding time down from 11 to 4 days, with the 3-day target expected by month 3.

DimensionResultRating
ScopeAll Must-have delivered; 1 Should-have deferredExample: Met
ScheduleGo-live +3 days vs original baselineMet within tolerance
Cost2.2% under BACMet
Quality0 severity 1 or 2 defects at go-liveMet
BenefitsOn track at first measurementOn track

2. Objectives versus outcomes

Each approved objective is compared with the measured outcome.

IDObjectiveTargetOutcomeEvidenceStatus
OBJ-01Example: Reduce onboarding cycle time3 days median4 days at month 1Onboarding system report YYYY-MMPartially met, on track
OBJ-02Example: Reduce abandonmentBelow 8%9.5% at month 1Web analytics (first-party, aggregated)Partially met, on track
OBJ-03Example: Go live before regulatory deadlineBefore YYYY-MM-DDLive YYYY-MM-DDRelease recordMet
[OBJ-nn][Objective][Target][Outcome][Evidence][Met / Partially met / Not met]

3. Scope delivered versus planned

Deliverables are listed against the original and current scope baselines.

DeliverablePlannedDeliveredAccepted byDateNotes
D1 Process designYesYesHead of operationsYYYY-MM-DD
D2 Onboarding platformYesYesProduct ownerYYYY-MM-DD
D3 Accessibility audit and remediationAdded by CR-007YesProduct ownerYYYY-MM-DDApproved change
D4 Joint application for two customersShould-haveNon/an/aExample: Deferred to roadmap item RM-14, accepted by sponsor
[Deliverable][Planned][Delivered][@acceptor]YYYY-MM-DD[Notes]

4. Schedule performance

Milestone performance against the original and the current (re-baselined) schedule:

IDMilestoneOriginal baselineCurrent baselineActualVariance vs original (days)
M1Plan baselinedYYYY-MM-DDYYYY-MM-DDYYYY-MM-DD0
M2Design approvedYYYY-MM-DDYYYY-MM-DDYYYY-MM-DDExample: +2
M3UAT completeYYYY-MM-DDYYYY-MM-DDYYYY-MM-DD+6
M4Go-liveYYYY-MM-DDYYYY-MM-DDYYYY-MM-DD+3
M5HandoverYYYY-MM-DDYYYY-MM-DDYYYY-MM-DD+3

Schedule variance at completion is expressed in days and as a share of planned duration:

Δt=tactual−tbaseline,Δt %=ΔtTplanned×100%\Delta t = t_{\text{actual}} - t_{\text{baseline}}, \qquad \Delta t\,\% = \frac{\Delta t}{T_{\text{planned}}} \times 100\%

Example: go-live 3 working days late on a planned duration of 160 working days gives Δt %≈1.9%\Delta t\,\% \approx 1.9\%, within the 10-day tolerance. Main causes: late vendor staffing (LL-01) and the accessibility change (CR-007), partly absorbed by the project buffer.

5. Cost performance

Final cost by category, reconciled with [finance system] on YYYY-MM-DD (EUR):

CategoryOriginal budgetApproved changesFinal budgetActual costVariance
Internal labourExample: 210,0000210,000216,400-6,400
External services140,000+18,000 (CR-007)158,000158,0000
Licences and infrastructure60,000060,00057,800+2,200
Training and change25,000+12,000 (CR-009)37,00036,000+1,000
Contingency43,500-30,00013,5000n/a
Total478,5000478,500468,200+10,300 (under budget)

The final cost indicators are:

CV=EV−ACCPI=EVACVAC=BAC−ACCV = EV - AC \qquad CPI = \frac{EV}{AC} \qquad VAC = BAC - AC

At completion EV=BACEV = BAC, so CPI=BAC/ACCPI = BAC / AC. [State the values and explain the main drivers of any variance, separating approved changes from overruns.]

Example: with BACBAC = 478,500 EUR and ACAC = 468,200 EUR, VACVAC = +10,300 EUR and CPI≈1.02CPI \approx 1.02. Of the 43,500 EUR contingency, 30,000 EUR funded two approved changes (CR-007 accessibility audit, CR-009 extended hypercare); 13,500 EUR was not needed and is returned to the portfolio. Internal labour overran by 6,400 EUR because business analysts supported UAT longer than planned; licences came in 2,200 EUR under budget after a negotiated discount. No costs remain open: the last vendor invoice was paid on YYYY-MM-DD and all project cost codes were closed on YYYY-MM-DD.

6. Quality results

Quality outcomes against the objectives in the quality management plan:

ObjectiveTargetResultStatus
Open severity 1 or 2 defects at go-live0Example: 0Met
WCAG 2.2 AA findings open at go-live00 (re-audit YYYY-MM-DD)Met
Migration field-level error rateBelow 0.1%0.04%Met
Defect removal efficiencyAt least 90%93.8% at 30 daysMet
Training assessment pass rateAt least 80%86%Met

Known defects released: [n] severity 3 and [n] severity 4, listed in [defect tracker query], transferred to the service owner (section 9).

7. Benefits status and handover

Benefit status at closure, against the benefits realization plan [BRP-001]:

BenefitBaselineTargetLatest actualDateStatusOwner after closure
B1 Onboarding time11 days3 daysExample: 4 daysYYYY-MM-DDOn trackHead of operations
B2 Cost per onboarding64 EUR28 EUR47 EURYYYY-MM-DDOn trackFinance director
B3 Abandonment18%Below 8%9.5%YYYY-MM-DDOn trackHead of digital
B4 Products per customer1.41.8Not yet measurablen/aMeasured at +3 monthsHead of retail

Benefit owners have accepted continued measurement and reporting to [operations board] on YYYY-MM-DD. Benefit reviews are scheduled at go-live + 6 and + 12 months.

8. Operational handover

The service was handed over to [IT operations and the onboarding operations team] on YYYY-MM-DD after a [4]-week hypercare period. Handover criteria and their status:

CriterionStatusEvidence
Runbooks and support documentation acceptedMet[Link]
Service desk trained, scripts in placeMetTraining records
Monitoring and alerting liveMetDashboard [link]
Service level met for 10 consecutive working daysMetSLA report YYYY-MM-DD
Support contract with vendor in forceMetContract C-2027-15

9. Transfer of open items

Open items are transferred as follows.

IDTypeDescriptionTransferred toAccepted onTarget date
RSK-030RiskExample: Identity vendor price review at contract anniversaryProcurement category managerYYYY-MM-DDYYYY-MM-DD
DEF-0412DefectExample: Date picker not localised for one languageService owner backlogYYYY-MM-DDNext release
RM-14Deferred scopeExample: Joint applicationsProduct owner roadmapYYYY-MM-DDYYYY-Qn
ACT-02Lesson actionRequirements template checklistHead of business analysisYYYY-MM-DDYYYY-MM-DD
[ID][Type][Description][@owner]YYYY-MM-DDYYYY-MM-DD

10. Lessons learned summary

The full register is in [LL-001]. The most important lessons are:

IDTypeLessonApplied to
LL-01NegativeExample: Supplier contracts need enforceable named-team clausesContract template v4.2
LL-02PositiveExample: Co-design with affected managers turned resistance into supportPMO lifecycle guide
LL-03NegativeExample: Regulatory and accessibility needs must be checked at requirements stageRequirements template

Recommendations for future projects of this type: plan an explicit project buffer and report its use from the first status report; involve compliance and accessibility specialists in requirements elicitation rather than design review; and agree environment service levels with infrastructure before the test stage starts. These recommendations have been sent to the PMO for inclusion in the project lifecycle guide.

11. Contract closure

All project contracts have been reviewed for closure.

ContractSupplierDeliverables acceptedFinal paymentOpen claimsSupplier evaluationStatus
C-2027-14Example: Front-end vendorYesPaid YYYY-MM-DDNone3.8 of 5, recordedClosed
C-2027-15Example: Front-end vendor (support)n/aOngoingNonen/aTransferred to IT operations
C-2027-21Example: Accessibility auditorYesPaid YYYY-MM-DDNone4.5 of 5Closed
[Contract][Supplier][Yes / No][Status][Claims][Score][Status]

12. Resource release

Project resources have been released.

ResourceReleased onReleased toAccess removedPerformance input given
Example: Business analystYYYY-MM-DDOperationsProject folders read-onlyYes
Example: Vendor developers (3)YYYY-MM-DDVendorAll accounts disabledn/a
Example: Test environmentsYYYY-MM-DDInfrastructureData deleted per retention policyn/a
[Resource]YYYY-MM-DD[Destination][Yes / No][Yes / No / n/a]

13. Archive and records

Project records are archived in [repository and path], read-only from YYYY-MM-DD, and retained for [7] years under [records policy]. The archive contains the charter, plans and baselines, decisions and change log, RAID log, test and acceptance evidence, contracts, financial reconciliation, lessons register and this report. Archive contact: [@pmo-records].

14. Closure checklist

The following closure activities are complete:

  • All deliverables accepted by their named acceptors
  • Operational handover accepted by the receiving owner
  • Open risks, issues, defects and actions transferred and accepted
  • Benefits ownership accepted by benefit owners
  • Contracts closed or transferred; final invoices paid
  • Financial accounts reconciled and cost codes closed
  • Resources released and access removed
  • Lessons learned register published
  • Records archived
  • Closure communicated to stakeholders

15. Sign-off

By signing, the parties confirm that the project is closed on the terms stated in this report. Conditions, if any: [none / list].

RoleNameSignature or approval referenceDate
Project sponsor[@name][Reference]YYYY-MM-DD
Project manager[@name][Reference]YYYY-MM-DD
Operations owner[@name][Reference]YYYY-MM-DD
Finance controller[@name][Reference]YYYY-MM-DD