ARID Intermediate Design Review Template (SEI)

ARID rehearsal and review phases, roles, RACI, seed scenarios, scenario votes, application log with pseudo-code, issue log, exit decision

Kiến trúcĐầy đủSEI ARID (CMU/SEI-2000-TN-009)ariddesignreview
Mở trong editorTải .md

Cách dùng: Use it when an interface or module design is usable but not yet frozen, and its future users should test it by writing code against it. Fill reviewers, the design briefing and seed scenarios first. The main pitfall is a review where reviewers only discuss slides instead of applying scenarios.

Xem trước

Intermediate Design Review (ARID): [Design or component name]

Plan and report of an active review of an intermediate design following Active Reviews for Intermediate Designs (ARID), described by Paul C. Clements of the Software Engineering Institute (SEI), Carnegie Mellon University, in technical note CMU/SEI-2000-TN-009 (August 2000). ARID combines scenario-based evaluation in the style of the ATAM with active design reviews: instead of asking reviewers whether a design looks right, it asks the engineers who will use the design to solve real problems with it. This template covers the rehearsal phase (reviewers, design briefing, seed scenarios, materials), the review meeting (scenario brainstorm, prioritisation, application), the issue log, the exit decision and follow-up. Replace every [bracketed] value and every row marked Example.

Document control

FieldValue
Document ID[ARD-001]
Design under review[Component, service, library or interface set]
Design version reviewed[Document or repository tag]
Lead designer[@designer]
Facilitator[@facilitator]
Review dateYYYY-MM-DD
Version[0.1]
Status[Planned / Rehearsed / Reviewed / Closed]
Owner[@facilitator]
Approvers/reviewers[@lead-designer], [@engineering-manager], [@architecture-lead]
Classification[Internal / Confidential]
Last updatedYYYY-MM-DD

Approvals

RoleNameDecisionDate
Lead designer[@name][Accept findings / Dispute, with reason]YYYY-MM-DD
Engineering manager[@name][Approve follow-up plan]YYYY-MM-DD
Architecture lead[@name][Proceed / Proceed with conditions / Redesign]YYYY-MM-DD

Revision history

VersionDateAuthorChange summary
0.1YYYY-MM-DD[@name]Review plan drafted
0.2YYYY-MM-DD[@name]Example: Rehearsal held; seed scenarios revised, briefing shortened
1.0YYYY-MM-DD[@name]Example: Review held; issue log and exit decision recorded
1.1YYYY-MM-DD[@name]Example: All severity 1 issues closed; review closed

Contents

1. Purpose, scope and method choice

1.1 Purpose of the review

[One paragraph: what the design provides, who will build on it, which decision the review feeds (proceed to detailed specification, release the interface to consumers, choose between two designs).]

Example: The payments team has designed a provider adapter layer (strategy AS-04 from the CBAM, architecture/cbam-analysis) that every new payment provider integration must use. Six teams will write adapters against it over the next year. The review checks that the port interfaces, error model and contract test kit are usable and sufficient before the interfaces are frozen and documented in the interface control document.

1.2 Scope

In scopeOut of scope
Example: PaymentProviderPort interface and its operationsInternal implementation of the core payments engine
Example: Error and retry model exposed to adaptersProvider commercial terms
Example: Contract test kit and its fixturesDeployment pipeline for adapters
Example: Configuration and secrets injection for adaptersFraud and risk scoring
[Item][Item]

1.3 Why ARID

QuestionAnswer for this designPoints to
Are the interfaces defined well enough to write calling code?[Yes / No]ARID if yes; wait if no
Is the main concern usability and fitness of the design for its users?[Yes / No]ARID
Is the main concern system-wide trade-offs between quality attributes?[Yes / No]ATAM (architecture/atam-evaluation)
Is a formal conformance assessment against a standard needed?[Yes / No]ISO/IEC/IEEE 42030 evaluation (architecture/architecture-evaluation-42030)
Is the design already implemented and in use?[Yes / No]Code review or architecture health check (architecture/architecture-health-check)
Is the budget about a day of reviewer time, not a multi-week evaluation?[Yes / No]ARID

1.4 Review objectives and exit criteria

IDObjectiveExit criterion
OBJ-01Example: Confirm reviewers can implement a typical adapter with the interfaces as designedAll top-priority scenarios solved or blocked only by logged issues
OBJ-02Example: Confirm the error model lets adapters express every provider failureNo unresolved severity 1 issue in the error model
OBJ-03Example: Confirm the contract test kit covers the agreed behaviourReviewers can write a passing and a failing test for each scenario
[OBJ-nn][Objective][Measurable criterion]

2. Roles and participants

2.1 Roles

RoleResponsibility
FacilitatorPlans the review with the designer, runs both phases, keeps the group on task, ensures reviewers write code rather than critique slides
ScribeRecords scenarios, votes, the code or pseudo-code produced, every issue and every question, with the time it arose
Lead designerBriefs the design, answers questions during application, does not defend or redesign during the meeting
Questioners (optional)Facilitation team members who probe areas reviewers skip, such as error paths and concurrency
ReviewersFuture users of the design who propose scenarios and solve them using the design
Observers (optional)Managers or other stakeholders who watch without voting

2.2 Participants

NameRoleTeamRepresents
[@name]Facilitator[Team]Independent of the design
[@name]Scribe[Team]
[@name]Lead designer[Team]Design owner
[@name]ReviewerExample: Card acquiring teamNext adapter to be built
[@name]ReviewerExample: Wallets teamAsynchronous provider flows
[@name]ReviewerExample: QA guildContract test kit users
[@name]ReviewerExample: SREOperability of adapters in production
[@name]Reviewer[Team][Perspective]

2.3 RACI

ActivityFacilitatorLead designerScribeReviewersEngineering manager
Select reviewersARIIC
Prepare design briefingCA, RIII
Prepare seed scenariosARICI
Run review meetingA, RRRRI
Record issuesACRCI
Resolve issuesIA, RICC
Approve follow-up planCRIIA

R: responsible, A: accountable, C: consulted, I: informed.

3. Phase 1: Rehearsal

3.1 Step plan

StepActivityOutputOwnerDone
1Identify the reviewersReviewer list in section 2.2, invitations sentFacilitator, lead designer[Yes / No]
2Prepare the design briefingBriefing of about two hours covering the design's purpose, interfaces, data, error handling and a worked example; summary in section 4Lead designer[Yes / No]
3Prepare seed scenariosSeed set in section 5Lead designer, facilitator[Yes / No]
4Prepare materialsBriefing copies, interface listings, seed scenarios, a shared workspace or repository branch for code, review agendaFacilitator[Yes / No]

3.2 Reviewer selection criteria

  • Choose people who will write code against the design within the next few months.
  • Cover every kind of consumer: synchronous and asynchronous callers, test authors, operations staff who will troubleshoot it.
  • Prefer reviewers who have not seen the design in detail; they find what the documentation leaves out.
  • Keep the group small enough to work (around a dozen) and large enough to produce varied scenarios.
  • Confirm each reviewer can attend the whole meeting. Partial attendance produces partial scenarios.

3.3 Materials checklist

ItemFormatReady
Design briefing slides or document[Format][Yes / No]
Interface listings with signatures, types and error codes[Format][Yes / No]
Example usage of the main operation[Format][Yes / No]
Seed scenario cards[Format][Yes / No]
Workspace for reviewer code (branch, sandbox, shared document)[Location][Yes / No]
Issue capture sheet (section 9 layout)[Location][Yes / No]
Room or call, timer, voting method[Details][Yes / No]

3.4 Rehearsal outcome

ObservationChange made
Example: Briefing spent 40 minutes on internal engine designCut to 5 minutes; focus on the port
Example: No seed scenario exercised asynchronous callbacksAdded SEED-04
Example: Error codes listed without meaningDesigner added one-line meaning per code
[Observation][Change]

4. Design briefing summary

4.1 Design overview

[One or two paragraphs: the design's responsibilities, its main abstractions and how a user is expected to use it.]

4.2 Elements under review

IDElementKindDescriptionDesign document reference
IF-01Example: authorise(request)OperationRequests authorisation of an amount; returns an outcome or a typed error[Section or file]
IF-02Example: capture(authorisationId, amount)OperationCaptures all or part of an authorised amount[Section or file]
IF-03Example: refund(captureId, amount)OperationRefunds all or part of a captured amount[Section or file]
IF-04Example: onProviderEvent(event)CallbackDelivers asynchronous provider notifications to the core[Section or file]
IF-05Example: ProviderErrorTypeError taxonomy: retryable, declined, invalid, unknown[Section or file]
IF-06Example: AdapterConfigTypeCredentials reference, endpoints, timeouts, feature flags[Section or file]
IF-07Example: Contract test kitToolingFixtures and assertions every adapter must pass[Section or file]
[IF-nn][Element][Operation / Type / Event / Tooling][Description][Reference]

4.3 Assumptions stated by the designer

IDAssumption
ASM-01Example: Every provider returns a stable reference per authorisation
ASM-02Example: Idempotency is the core's responsibility, not the adapter's
[ASM-nn][Assumption]

5. Seed scenarios

IDScenario (task for the reviewer)Elements exercisedWhy it matters
SEED-01Example: Implement a card authorisation that the provider declines for insufficient fundsIF-01, IF-05Most common non-success path
SEED-02Example: Capture 60 percent of an authorised amount, then capture the rest two days laterIF-02Split shipments in retail
SEED-03Example: Handle a provider timeout during capture without double captureIF-02, IF-05, ASM-02Money integrity
SEED-04Example: Process a delayed asynchronous settlement notification that arrives before the capture responseIF-04Out-of-order events
[SEED-nn][Task][IF IDs][Reason]

6. Phase 2: Review meeting

6.1 Agenda

StepActivityTime boxLead
5Present the ARID method: purpose, rules of the day, how issues are recorded15 minutesFacilitator
6Present the design: briefing from section 4, reviewers ask clarifying questions only1 to 2 hoursLead designer
7Brainstorm and prioritise scenarios: seeds shown, new scenarios proposed, votes cast45 minutesFacilitator
8Apply the scenarios: reviewers write code or pseudo-code using the design for each top scenario in priority order3 to 4 hoursFacilitator, reviewers
9Summarise: read back the issue list, ask reviewers how the design and the review worked, thank participants30 minutesFacilitator

6.2 Ground rules

  • Clarifying questions during the briefing are welcome; design debates wait for scenario application.
  • The designer answers "how would I do this with the design?" but does not change the design during the meeting.
  • When a reviewer cannot proceed, the scribe records an issue and the group moves on; nobody fixes the design in the room.
  • Code does not have to compile. It must be specific enough that another engineer could check it against the interfaces.
  • Every question the designer has to answer from memory is a candidate documentation issue.

7. Scenario brainstorm and prioritisation

Review scenarios use IDs RVS-nn (review scenario), distinct from the ARS- requirement IDs of the Architecture Requirements Specification (architecture/architecture-requirements-specification). Each of the [n] reviewers received [v] votes for [m] scenarios. Example: 12 reviewers, 7 scenarios, 3 votes each (30 percent of 7, rounded up), 36 votes in total.

IDScenarioProposed bySeed or newVotesPriority
RVS-01Example: SEED-03 capture timeout without double captureLead designerSeed91
RVS-02Example: Rotate provider credentials without restarting the adapterSRE reviewerNew72
RVS-03Example: SEED-04 out-of-order settlement notificationLead designerSeed63
RVS-04Example: Add a provider that supports authorisation only, no partial captureWallets reviewerNew54
RVS-05Example: Write a contract test proving a declined response maps to the declined error classQA reviewerNew45
RVS-06Example: SEED-02 split captureLead designerSeed36
RVS-07Example: Report adapter latency per operation to monitoringSRE reviewerNew27
[RVS-nn][Scenario][@name][Seed / New][n][n]

Example: Reviewers voted two new scenarios (RVS-02, RVS-04) into the top four. Neither was covered by the seeds, which shows the seeds were biased toward the happy path of the transaction lifecycle.

8. Scenario application log

8.1 Summary

ScenarioDriverElements usedOutcomeIssues raisedTime spent
RVS-01Example: [@reviewer]IF-02, IF-05BlockedARI-001, ARI-00250 minutes
RVS-02Example: [@reviewer]IF-06Solved with workaroundARI-00330 minutes
RVS-03Example: [@reviewer]IF-04SolvedARI-00440 minutes
RVS-04Example: [@reviewer]IF-01, IF-02BlockedARI-00535 minutes
RVS-05Example: [@reviewer]IF-05, IF-07SolvedARI-00625 minutes
RVS-06Example: [@reviewer]IF-02Not reachedNone0
[RVS-nn][@name][IF IDs][Solved / Solved with workaround / Blocked / Not reached][ARI IDs][Duration]

8.2 Application detail

Record one block per scenario applied.

RVS-01 (Example): capture timeout without double capture

// Reviewer pseudo-code written against the design during the review
result = port.capture(authId, amount)          // IF-02
on ProviderError.retryable:                     // IF-05
    // Question: may the core retry, or must the adapter check first?
    // Design is silent on whether capture is idempotent at the provider.
    retry? -> unknown, issue ARI-001
on timeout:
    // No error class distinguishes "timed out, outcome unknown"
    // from "failed, safe to retry". Issue ARI-002.

Observations: [what reviewers understood, where they hesitated, which documentation they asked for].

[RVS-nn]: [scenario title]

[Code or pseudo-code produced]

Observations: [Notes].

9. Issues and findings

9.1 Classification

CategoryMeaning
MissingThe design lacks an element, operation, type or rule that a scenario needs
AmbiguousThe design can be read in more than one way and reviewers disagreed
IncorrectUsing the design as specified gives the wrong result
Hard to useThe scenario can be solved, but only with effort or code that users are likely to get wrong
DocumentationThe design works, but its description does not say how
QuestionOpen question for the designer, not yet classified
SeverityMeaningRequired before freeze
1Blocks a top-priority scenario or risks data or money integrityFix and re-review the affected scenario
2Scenario solvable only with a workaround or likely misuseFix or document the accepted workaround
3Clarity or convenience improvementPlan; may follow the freeze

9.2 Issue log

IDScenarioElementCategorySeverityDescriptionOwnerStatus
ARI-001Example: RVS-01IF-02Ambiguous1Design does not say whether capture may be retried; reviewers wrote three different retry policies[@designer]Open
ARI-002Example: RVS-01IF-05Missing1No error class for "outcome unknown"; adapters cannot signal it, so the core may double capture[@designer]Open
ARI-003Example: RVS-02IF-06Hard to use2Credentials read once at start-up; rotation needs restart or custom reload code[@designer]Open
ARI-004Example: RVS-03IF-04Documentation3Ordering guarantee of callbacks not stated; reviewers inferred "none" correctly[@designer]Open
ARI-005Example: RVS-04IF-02Missing2No way for an adapter to declare unsupported operations; reviewers threw generic errors[@designer]Open
ARI-006Example: RVS-05IF-07Hard to use3Test kit fixtures hard-code currency; non-EUR providers need copies[@designer]Open
[ARI-nnn][RVS-nn][IF-nn][Category][1 / 2 / 3][Description][@owner][Open / In progress / Closed / Rejected]

9.3 Assumptions challenged

AssumptionChallengeOutcome
Example: ASM-02 idempotency is the core's jobRVS-01 showed the core cannot be idempotent without an "outcome unknown" signal from the adapterAssumption revised; linked to ARI-002
[ASM-nn][Challenge][Kept / Revised / Withdrawn]

10. Summary and exit decision

10.1 Results against objectives

ObjectiveResultEvidence
OBJ-01Example: Partly met: 3 of 5 applied scenarios solved, 2 blockedSection 8.1
OBJ-02Example: Not met: severity 1 gap in the error modelARI-002
OBJ-03Example: Met with frictionARI-006
[OBJ-nn][Met / Partly met / Not met][Reference]

10.2 Reviewer feedback

QuestionSummary of answers
Was the design briefing enough to start writing code?[Answers]
Which part of the design was hardest to use?[Answers]
What would you change about the review itself?[Answers]

10.3 Decision

FieldValue
Decision[Proceed to freeze / Proceed after severity 1 fixes and delta review / Redesign]
ConditionsExample: ARI-001 and ARI-002 closed; RVS-01 re-applied by two reviewers
Decided by[@architecture-lead]
DateYYYY-MM-DD
Delta review dateYYYY-MM-DD

11. Follow-up and traceability

11.1 Action plan

ActionClosesOwnerDueStatus
Example: Add ProviderError.outcomeUnknown and define core reconciliation behaviourARI-002[@designer]YYYY-MM-DD[Status]
Example: State capture retry rule in the interface contract; add ADRARI-001[@designer]YYYY-MM-DD[Status]
Example: Add capabilities() operation for unsupported operationsARI-005[@designer]YYYY-MM-DD[Status]
Example: Add credential reload hook to AdapterConfigARI-003[@designer]YYYY-MM-DD[Status]
[Action][ARI IDs][@owner]YYYY-MM-DD[Status]

11.2 Traceability matrix

ScenarioElementsIssuesDesign changeADRVerified by
RVS-01Example: IF-02, IF-05ARI-001, ARI-002Error model v2ADR-031Delta review, contract test CT-14
RVS-02Example: IF-06ARI-003Reload hookADR-032Contract test CT-15
RVS-04Example: IF-01, IF-02ARI-005Capability declarationADR-033Contract test CT-16
[RVS-nn][IF IDs][ARI IDs][Change][ADR ID][Evidence]

Record new or changed ADRs in the architecture decision log (architecture/architecture-decision-log). Where a scenario expresses a quality that should stay true after release, such as "adapters never call providers directly from the core", add a fitness function (architecture/fitness-functions).

12. Review effectiveness

MetricValueComment
Reviewer hours spentExample: 12 reviewers x 7 hours = 84
Scenarios proposed / appliedExample: 7 / 5RVS-06 and RVS-07 not reached
Issues by severity (1 / 2 / 3)Example: 2 / 2 / 2
Issues per applied scenarioExample: 6 / 5 = 1.2
Issues found later in implementation that a scenario would have exposed[n, after 3 months]Escaped issues
Lead time from review to interface freeze[Days]

Lessons for the next review:

  • [Lesson, for example "seed at least one operations scenario".]
  • [Lesson.]

13. Glossary and references

13.1 Glossary

TermMeaning in this document
Intermediate designA design detailed enough to use (interfaces, types, rules) but not yet fully specified or implemented
Active reviewA review in which reviewers must use the design to complete tasks, rather than comment on it
Rehearsal phasePreparation by facilitator and lead designer: reviewers, briefing, seed scenarios, materials
Review phaseMeeting in which the method and design are presented and scenarios are brainstormed, prioritised and applied
Seed scenarioA scenario prepared in advance as an example and to guarantee coverage
Scenario applicationWriting code or pseudo-code that solves a scenario using only the design as presented
Delta reviewA short follow-up review limited to scenarios affected by design changes

13.2 References

ReferenceVersion or date checkedUse
Clements, P. C. Active Reviews for Intermediate Designs. Technical note CMU/SEI-2000-TN-009, Software Engineering Institute, sei.cmu.eduAugust 2000, checked YYYY-MM-DDPhases, steps and roles of the method
Clements, P., Kazman, R., Klein, M. Evaluating Software Architectures: Methods and Case Studies, Addison-Wesley, 2002Background reading (inspiration only)Context among SEI evaluation methods
Parnas, D. L., Weiss, D. M. Active Design Reviews: Principles and Practices, Proceedings of ICSE 8, 1985Background readingOrigin of the active review idea
Architecture evaluation (ATAM) template (architecture/atam-evaluation)This collectionScenario-based evaluation for whole architectures
[Design document reviewed][Version]Subject of the review

Standard and licence note

Based on Active Reviews for Intermediate Designs (ARID) as described by Paul C. Clements in Software Engineering Institute technical note CMU/SEI-2000-TN-009 (August 2000): the rehearsal and review phases, their nine steps (identify reviewers, prepare the design briefing, prepare seed scenarios, prepare materials, present the method, present the design, brainstorm and prioritise scenarios, apply the scenarios, summarise) and the roles of facilitator, scribe, lead designer and reviewers. This template is original text written for this collection and reproduces no text from SEI publications or from books on the method; the worked example is invented and marked Example. Check the SEI digital library for the current version of the technical note before use. Carnegie Mellon, SEI and ATAM may be trademarks or service marks of Carnegie Mellon University; this template is not affiliated with or endorsed by the SEI. Template licence: MIT.