ISMS Budget and Resource Plan Template (ISO/IEC 27001)

Cost lines (effort, consultant, tooling, training, pentest, certification fees, remediation), 3-year budgets per tier, FTE by role, funding tranches

ISMS và ISO/IEC 27001Đầy đủISO/IEC 27001:2022 + Amd 1:2024 clauses 5.1, 6.2, 7.1 (cited only); ISO/IEC 27006-1:2024budgetresourceplan
Mở trong editorTải .md

Cách dùng: Use it with the business case so both show the same totals. Fill the assumptions (loaded FTE cost, contingency) and certification body quotes first, then the worked budget for your tier and the named time allocations. The main pitfall is budgeting only external spend and forgetting the recurring costs of years 2 and 3.

Xem trước

ISMS Budget and Resource Plan: [Organization name]

Budget and resource plan for establishing, certifying and running an information security management system (ISMS) under ISO/IEC 27001:2022 including Amendment 1:2024. It covers every cost line (internal effort, optional consultant, tooling, training and staff certification, penetration testing, certification body fees for the initial audit, surveillance years and recertification, and remediation), a 3-year view per size tier, a resource plan by role and the funding approval. It supports clause 7.1 (an ISMS with no people, time or money behind it is only paper) and clause 5.1 (leadership has to back the ISMS with real funding), and it gives clause 6.2 planning its "what resources" answer. Replace every [bracketed] value and every row marked Example. All money figures are Example values in USD: use your local currency and real quotes.

Document control

FieldValue
Document IDDOC-ISMS-031
Version[1.0]
Status[Draft / In review / Approved / Superseded]
Owner[@isms-manager]
Approvers/reviewers[@cfo], [@sponsor], [@ceo]
Last updatedYYYY-MM-DD
Classification[Confidential]
Standard and editionISO/IEC 27001:2022 + Amd 1:2024
Size tier used[Small / Medium / Large or multi-site]
Budget period[FY YYYY to FY YYYY, 3 years]
Currency and price basis[USD / local currency], [prices as of YYYY-MM-DD, excluding / including tax]
Business case referenceDOC-ISMS-029
Charter referenceDOC-ISMS-009
Next scheduled reviewYYYY-MM-DD [annual budget cycle and each phase gate]

Approvals

RoleNameDecisionDate
ISMS manager[@isms-manager][Prepared]YYYY-MM-DD
Finance[@cfo][Reviewed and funded]YYYY-MM-DD
Sponsor[@sponsor][Approved]YYYY-MM-DD
Top management[@ceo][Approved]YYYY-MM-DD

Revision history

VersionDateAuthorChange
1.0 (Example)YYYY-MM-DD[@isms-manager]Baseline approved with the business case
1.1 (Example)YYYY-MM-DD[@isms-manager]PCR-001: GRC tool deferred, year 1 tooling reduced
2.0 (Example)YYYY-MM-DD[@isms-manager]Year 2 run budget confirmed at management review

Contents

  1. Purpose and scope
  2. Assumptions
  3. Cost lines
  4. Worked budgets by tier
  5. 3-year view and recertification
  6. Resource plan by role
  7. Funding approval and release
  8. Budget monitoring and change
  9. Size tiers
  10. Records and evidence
  11. References

1. Purpose and scope

This plan sets out the money and people needed to establish the ISMS, complete the initial certification audit and run the ISMS through the first certification cycle. It covers the ISMS scope in DOC-ISMS-002.

IncludedExcluded
Internal effort of named roles on ISMS workBusiness-as-usual operations already funded (for example existing endpoint protection licences)
External advice, tooling, training, testing and auditsProduct development not driven by a risk treatment action
Remediation capital and one-off spend driven by the risk treatment planSpend for other management systems, except shared costs stated in section 9
Contingency on external project linesTax treatment and depreciation (finance applies its own rules)

2. Assumptions

IDAssumptionSmallMediumLarge
BA-001 (Example)Loaded cost per FTE per year (salary, benefits, overhead)USD 150,000USD 140,000USD 135,000
BA-002 (Example)Contingency on external project lines (not on internal effort)10%10%10%
BA-003 (Example)Certification body fees are based on written quotes; audit time is set by the certification body under ISO/IEC 27006-1:20242 quotes3 quotes3 quotes, integrated audit option
BA-004 (Example)Penetration test once a year, scope set by the risk assessmentWeb application and cloudPlatform, colocation network, external perimeterIT and OT, all 6 sites over the cycle
BA-005 (Example)Existing security tooling continues to be funded from operationsYesYesYes
BA-006 (Example)Year 1 starts at project kick-off, not at the start of a financial yearYesYesYes

The small tier uses a higher loaded cost because its ISMS effort falls mostly on senior engineering staff; the medium and large tiers spread it across a wider mix of roles. Replace all three with your finance team's figures.

Audit time and any audit-day figure in this plan are Example values. The certification body determines audit time from the number of persons doing work under the organization's control and complexity factors, so ask for its calculation in the quote.

3. Cost lines

CodeCost lineWhat it coversNature
CL-01Internal effortTime of the ISMS manager, project manager, security team, control owners and internal auditor on ISMS work, in FTE x loaded costRecurring, higher in year 1
CL-02Consultant (optional)Gap assessment support, coaching, template review, pre-audit check, external internal auditor where no independent staff existMostly year 1
CL-03ToolingGRC or ISMS platform, or the incremental cost of using existing tools (ticketing, wiki) for registers and evidenceRecurring subscription
CL-04Training and staff certificationAwareness platform, role training (risk, internal audit, secure development), professional certifications such as ISO/IEC 27001 lead implementer or lead auditor coursesRecurring
CL-05Penetration testingIndependent technical testing of in-scope systems; retests after fixesRecurring, usually annual
CL-06Certification body feesStage 1 and Stage 2 in year 1, surveillance audits in years 2 and 3, recertification before expiry; auditor travel where on siteRecurring by cycle
CL-07Remediation capex and one-off spendControls the treatment plan requires that do not exist yet: logging and monitoring, backup immutability, device management, network segmentation, physical accessMostly year 1
CL-08Contingency10% of CL-02 to CL-07 (Example)Each year

Cash cost is CL-02 to CL-08. Full economic cost adds CL-01.

CL-01 is the time of people already on the payroll, valued at loaded cost: an opportunity cost, not new spending. If you hire or backfill a role for the ISMS, move that cost into a cash line so it is not counted twice. Finance approves the cash budget; line managers approve the time (section 6). Never present the economic total as the cash request.

4. Worked budgets by tier

4.1 Small: Quillmere Analytics Ltd

46 staff (38 employees, 8 contractors), one office plus remote staff, production on one public cloud provider in two regions. Part-time ISMS manager (0.5 FTE, the Head of Engineering Operations). Target: certification in 6 months.

CodeCost lineYear 1Year 2Year 33-year total
CL-01Internal effort (0.8, 0.6, 0.6 FTE x 150,000)120,00090,00090,000300,000
CL-02Consultant, including external internal auditor25,0005,0005,00035,000
CL-03Tooling (lightweight GRC platform)12,00012,00012,00036,000
CL-04Training and staff certification7,0004,0004,00015,000
CL-05Penetration testing18,00018,00018,00054,000
CL-06Certification body fees (initial, surveillance 1, surveillance 2)16,0007,0007,00030,000
CL-07Remediation (device management, logging, backup immutability)30,0008,0008,00046,000
CL-08Contingency (10% of CL-02 to CL-07)10,8005,4005,40021,600
Total economic cost238,800149,400149,400537,600
of which cash (CL-02 to CL-08)118,80059,40059,400237,600

For Quillmere Analytics the money actually spent is USD 118,800 in year 1 and USD 59,400 in each later year (Example). The USD 300,000 of internal effort is mostly the ISMS manager's 0.5 FTE, which already sits in the Head of Engineering Operations' salary, plus control owners' time. Year 1 is a 6-month build followed by about 6 months of operation, so the year 1 FTE covers both.

4.2 Medium: Quillmere Health Systems

320 staff, two offices and one colocation suite. Full-time ISMS manager plus a 3-person security team. Target: ISO/IEC 27001 in 10 months, ISO/IEC 27701 the year after (the privacy add-on is costed separately in the business case, option D).

CodeCost lineYear 1Year 2Year 33-year total
CL-01Internal effort (3.5, 3.0, 3.0 FTE x 140,000)490,000420,000420,0001,330,000
CL-02Consultant60,00015,00015,00090,000
CL-03Tooling (GRC platform)30,00030,00030,00090,000
CL-04Training and staff certification25,00015,00015,00055,000
CL-05Penetration testing45,00045,00045,000135,000
CL-06Certification body fees (initial, surveillance 1, surveillance 2)35,00015,00015,00065,000
CL-07Remediation (SIEM onboarding, colocation access control, network segmentation)150,00040,00040,000230,000
CL-08Contingency (10% of CL-02 to CL-07)34,50016,00016,00066,500
Total economic cost869,500596,000596,0002,061,500
of which cash (CL-02 to CL-08)379,500176,000176,000731,500

4.3 Large or multi-site: Quillmere Group

2,400 staff, 6 sites in 4 countries (HQ, 3 plants, 1 service centre, 1 data centre), OT and IT, already certified to ISO 9001 and ISO 22301. CISO with a 14-person security office. Target: ISO/IEC 27001 for the group in 15 months, phased by site.

CodeCost lineYear 1Year 2Year 33-year total
CL-01Internal effort (12.0, 9.0, 9.0 FTE x 135,000)1,620,0001,215,0001,215,0004,050,000
CL-02Consultant (OT security and programme support)180,00040,00040,000260,000
CL-03Tooling (enterprise GRC, integrated with the existing management system)90,00090,00090,000270,000
CL-04Training and staff certification80,00050,00050,000180,000
CL-05Penetration testing, including OT assessments160,000140,000140,000440,000
CL-06Certification body fees (initial multi-site, surveillance 1, surveillance 2)110,00050,00050,000210,000
CL-07Remediation (OT segmentation, site physical controls, monitoring)900,000250,000250,0001,400,000
CL-08Contingency (10% of CL-02 to CL-07)152,00062,00062,000276,000
Total economic cost3,292,0001,897,0001,897,0007,086,000
of which cash (CL-02 to CL-08)1,672,000682,000682,0003,036,000

The 15-month programme spans parts of two budget years. To keep the three tiers comparable, year 1 above carries the whole build effort and the initial certification fee, although Stage 1 and Stage 2 fall in months 14 and 15 of the programme (Example). If your finance team budgets by financial year, move the Stage 2 fee and the matching effort into the year in which the audit happens, and shift the surveillance years with it.

5. 3-year view and recertification

5.1 Summary by tier (Example, USD)

TierYear 1Year 2Year 33-year economic cost3-year cash cost
Small: Quillmere Analytics Ltd238,800149,400149,400537,600237,600
Medium: Quillmere Health Systems869,500596,000596,0002,061,500731,500
Large: Quillmere Group3,292,0001,897,0001,897,0007,086,0003,036,000

5.2 Certification body fees across the cycle (Example, USD)

AuditTimingSmallMediumLarge
Initial certification (Stage 1 and Stage 2)Year 116,00035,000110,000
Surveillance 1No later than 12 months from the certification decision7,00015,00050,000
Surveillance 2Following calendar year7,00015,00050,000
Recertification (memo, outside the 3-year total)Planned and completed before the certificate expires, usually in year 4 of spend11,00025,00080,000

Surveillance audits take place at least once each calendar year, except in recertification years. A scope extension, a new site or a transfer between certification bodies changes these figures; plan them in isms/scope-extension-multisite-plan and isms/certification-cycle-plan.

5.3 Cost profile

Typical pattern (Example): year 1 is 40% to 50% of the 3-year total across the three worked tiers (small 238,800 of 537,600 is 44%; medium 869,500 of 2,061,500 is 42%; large 3,292,000 of 7,086,000 is 46%).

6. Resource plan by role

6.1 FTE by role and year (Example)

RoleSmall Y1Small Y2 and Y3Medium Y1Medium Y2 and Y3Large Y1Large Y2 and Y3
ISMS manager or ISMS core team0.50.51.01.04.03.5
Project manager0 (ISMS manager runs it)00.50Included in core teamIncluded in core team
Security team share001.21.3Included in core teamIncluded in core team
Site coordinators (6 sites)Not applicableNot applicableNot applicableNot applicable3.0 (6 x 0.5)1.5 (6 x 0.25)
Control owners (IT, HR, facilities, engineering, legal)0.30.10.60.53.52.5
Internal auditor0 (external, in CL-02)00.20.21.01.0
OT security leadNot applicableNot applicableNot applicableNot applicable0.50.5
Total FTE (CL-01)0.80.63.53.012.09.0

Top management time (policy approval, management review, risk acceptance) and all-staff time for awareness training (for example 46 staff x 2 hours a year in the small tier) are not costed here; they are absorbed in normal operations but are a real commitment. Schedule them in the annual calendar (isms/isms-annual-calendar).

6.2 Named allocations

PersonRoleAllocationPeriodLine manager agreement
[@isms-manager] (Example)ISMS manager100%Year 1 to year 3[@coo], YYYY-MM-DD
[@isms-project-manager] (Example)Project manager50%Kick-off to project closure[@pmo-lead], YYYY-MM-DD
[@security-engineer-1] (Example)Security team, risk and monitoring40%Year 1[@security-lead], YYYY-MM-DD
[@it-lead] (Example)Control owner, IT operations20%Year 1[@cto], YYYY-MM-DD
[@hr-lead] (Example)Control owner, people controls10%Year 1[@chro], YYYY-MM-DD
[@internal-auditor] (Example)Internal auditor20%Phase 7 onward[@cfo], YYYY-MM-DD

6.3 Capacity risks

  • If the ISMS manager also has an operational role (common in small organisations), protect fixed days each week for ISMS work.
  • Backfill delivery roles before releasing control owners; otherwise delivery work always wins.
  • Plan a deputy for the ISMS manager to avoid a single point of failure.

7. Funding approval and release

7.1 Year 1 tranches for the medium tier (Example, USD)

TrancheReleased atLines coveredAmount
T1Charter approval (phase 0 gate)Consultant 30,000; tooling 30,000; training 10,00070,000
T2Risk assessment, SoA and treatment plan approved (phase 3 gate)Remediation 150,000; penetration test 45,000; training 15,000; consultant 20,000230,000
T3Management review held (phase 8 gate)Certification body fees 35,000; consultant pre-audit check 10,00045,000
ContingencyOn sponsor approval, logged as a changeAny CL-02 to CL-07 line34,500
Year 1 cash total379,500

7.2 Approval flow

Finance checks the plan against the business case before the sponsor recommends it; money is then released tranche by tranche.

7.3 Funding decision record

FieldValue
Decision ID[DEC-ISMS-002]
Approved amount[Year 1 USD amount; years 2 and 3 indicative, confirmed in the annual budget cycle]
Approved by and date[@ceo / Board], YYYY-MM-DD
Conditions[Tranches as in 7.1; contingency drawn only with sponsor approval]
Cost centre[Cost centre code]

8. Budget monitoring and change

Month (Example)Planned cumulative cashActual cumulative cashVarianceComment
Month 370,00064,000-6,000Tooling discount
Month 6250,000270,000+20,000Segmentation work brought forward
Month 10379,500372,000-7,500Contingency partly unused

Rules:

  1. Report variance above 10% of a year budget to the sponsor within one week.
  2. Reallocation between lines follows the tolerances in the charter (isms/isms-project-charter, section 11).
  3. From year 2, present the actual spend and the next year's request at management review (compliance/management-review), so that resource decisions appear in its outputs.

9. Size tiers

AspectSmall: Quillmere Analytics LtdMedium: Quillmere Health SystemsLarge: Quillmere Group
Biggest cost lineInternal effort, then remediationInternal effort, then remediationInternal effort, then OT and site remediation
Tooling approachLightweight GRC platform or existing wiki and ticketingGRC platformEnterprise GRC shared with ISO 9001 and ISO 22301
Consultant useCoaching and external internal auditTargeted support and pre-audit checkOT expertise and programme support
Certification body feesSingle site plus remote; small audit teamTwo offices plus colocationMulti-site sampling under ISO/IEC 27006-1:2024 and IAF MD 1:2023 (now re-issued by Global ACI as Global ACI-TECH-3-001; check the current issue); integrated audit with existing certificates may reduce total audit time
Shared costsNoneShared with privacy programme in year 2Document control, internal audit, management review and corrective action shared with the integrated management system; show the saving (see isms/integrated-management-27013)
ApprovalCEOExecutive committeeGroup board, with site budgets

10. Records and evidence

RecordProvesOwnerLocationRetention (Example)
Approved budget and resource plan (this document)Resources determined[@isms-manager][Document management system]Life of the ISMS plus 3 years
Funding decision record (section 7.3)Resources provided by top management[@cfo][Board portal / finance system]As corporate records policy requires
Named allocations with line manager agreement (section 6.2)People made available[@isms-manager][HR or project system]3 years
Monthly spend reports (section 8)Budget controlled[@finance-business-partner][Finance system]As finance rules require
Certification body quotes and contractBasis for CL-06[@procurement-lead][Contract repository]Contract term plus 6 years (Example)

Map these records in the control evidence matrix (isms/control-evidence-matrix) and list the plan in the documented information register (isms/isms-documented-information-register).

11. References

ReferenceEditionUse
ISO/IEC 27001:2022, information security management systems requirements2022, with Amd 1:2024 (published 2024-02-23)Clauses 5.1, 6.2 and 7.1. https://www.iso.org/standard/82875.html, https://www.iso.org/standard/88435.html
ISO/IEC 27006-1:2024, requirements for ISMS certification bodies2024How audit time is determined. https://www.iso.org/standard/82908.html
ISO/IEC 17021-1:2015, requirements for certification bodies2015Certification cycle, surveillance and recertification. https://www.iso.org/standard/61651.html
ISO/IEC 27003:2017, ISMS guidance2017 (a revision is in progress; check for a newer edition)Resource planning guidance. https://www.iso.org/standard/63417.html
IAF MD 1:2023, audit and certification of a multi-site management system, now re-issued by Global ACI as Global ACI-TECH-3-001IAF MD 1 issue 3 (2023). Global Accreditation Cooperation Incorporated (Global ACI) replaced IAF and ILAC on 2026-01-01; Global ACI-TECH-3-001 v1.0 issued 2026-07-10, in force 2026-08-28: check the current issueMulti-site sampling (large tier); accredited certification under the Global ACI MRA (formerly IAF MLA)

Related templates: isms/isms-business-case, isms/isms-project-charter, isms/isms-implementation-roadmap, isms/isms-roles-raci, isms/isms-competence-training-matrix, isms/certification-body-selection, isms/certification-cycle-plan.

Standard and licence note

Structure aligned with ISO/IEC 27001:2022 including Amd 1:2024 (clauses 5.1, 6.2 and 7.1) and the certification cycle in ISO/IEC 17021-1:2015 and ISO/IEC 27006-1:2024. The cost lines, figures, tables and examples are original; no ISO/IEC text is reproduced. You need the official standards for the requirements themselves: https://www.iso.org/standard/82875.html. Check the current edition of every standard and accreditation document before use. All figures are Example values, not benchmarks or quotes, and certification decisions belong to the accredited certification body. This is a documentation format, not financial advice. Template licence: MIT.