Markdown Editor

ISMS Worked Walkthrough Template (ISO/IEC 27001 in 6 Months)

Worked example, 46-person SaaS from decision to certificate: filled scope, risk, SoA, objective, audit finding, review decision, Stage 2 finding

ISMS và ISO/IEC 27001Đầy đủISO/IEC 27001:2022 + Amd 1:2024 clauses 4 to 10 and Annex A (cited only); ISO/IEC 17021-1:2015; ISO/IEC 27006-1:2024workedwalkthrough
Mở trong editorTải .md

Cách dùng: Use it at the start of an ISMS project to show what each record looks like and how they link, and again before the internal audit. Fill your own project diary in section 17 first. The main pitfall is copying the fictional extracts as your own records instead of using them as a model of depth.

Xem trước

ISMS Worked Walkthrough: [Organization name]

Narrative worked example that follows one fictional small company, Quillmere Analytics Ltd, from the decision to build an information security management system (ISMS) to an ISO/IEC 27001:2022 + Amd 1:2024 certificate in about six months. At each step it shows a filled extract of the key record (scope statement, risk entry, Statement of Applicability rows, objective, internal audit finding, management review decision, Stage 2 finding and closure) and points to the library template that holds the full format. Use it to see how the documents connect, then write your own project diary in section 17. Every company detail, date, figure and ID is fictional and marked Example. Replace every [bracketed] value and every row marked Example when you reuse a format.

Document control

FieldValue
Document IDLRN-ISMS-09
Version[1.0]
Status[Draft / Approved / Superseded]
Owner[@isms-manager]
Approvers/reviewers[@project-sponsor], [@internal-audit-lead]
Last updatedYYYY-MM-DD
Classification[Internal]
Standard and editionISO/IEC 27001:2022 + Amd 1:2024; certification process per ISO/IEC 17021-1:2015 and ISO/IEC 27006-1:2024
Fictional organizationQuillmere Analytics Ltd (small tier) (Example)
Narrative period2027-01-04 to 2027-06-15 (Example)
Next scheduled review[Yearly, or when the linked templates change]

Approvals

RoleNameDecisionDate
ISMS manager[@isms-manager][Prepared]YYYY-MM-DD
Project sponsor[@ceo][Approved for team briefings]YYYY-MM-DD

Revision history

VersionDateAuthorChange
1.0 (Example)2027-01-11[@isms-manager]Walkthrough shared with the project team at kick-off
[x.y]YYYY-MM-DD[@author][Change]

Contents

  1. About Quillmere Analytics Ltd
  2. Timeline at a glance
  3. Month 1: decide and start
  4. Month 1: context and scope
  5. Month 2: risk assessment and treatment
  6. Month 2 to 3: Statement of Applicability
  7. Month 2 to 3: objectives and control implementation
  8. Month 3: internal audit
  9. Month 4: management review
  10. Month 4: Stage 1 audit
  11. Month 5: Stage 2 audit
  12. Month 6: findings closure and certification decision
  13. After the certificate
  14. Lessons learned
  15. Size tiers: the same story at other sizes
  16. Records and evidence
  17. Your own project diary
  18. References

1. About Quillmere Analytics Ltd

Quillmere Analytics Ltd (Example) sells a business-to-business SaaS analytics platform to retail customers. It has 46 staff: 38 employees and 8 contractors. Everyone works from one office or remotely. Production runs on one public cloud provider in two regions, a primary region and a disaster recovery (DR) region. The platform holds customer datasets that include personal data, which Quillmere processes as a processor under data processing agreements; GDPR is one example of the data protection law its customers rely on.

Two enterprise customers made an accredited ISO/IEC 27001 certificate a condition of their contract renewals, due in the summer of 2027. The CEO decided on 2027-01-04 to build an ISMS and seek certification within six months. The Head of Engineering Operations became ISMS manager for half of their time (0.5 FTE). No consultant ran the project; an external auditor was contracted for the internal audit only.

Quillmere was not starting from nothing. It already had single sign-on for most tools, encrypted laptops, cloud backups, a leaver process run by HR and an engineering metrics dashboard reviewed monthly. The ISMS project gave these practices owners, documents and records, and filled the gaps around them.

2. Timeline at a glance

Milestone (Example)DateRecord
Decision to certify2027-01-04Business case DOC-ISMS-029, project charter DOC-ISMS-009
Scope approved2027-01-29DOC-ISMS-002 v1.0
Risk treatment plan drafted2027-02-26DOC-ISMS-013 (not yet signed by risk owners; see section 11)
SoA approved2027-03-10DOC-ISMS-011 v1.1
Internal audit report issued2027-03-29DOC-ISMS-084, IA-2027-01
Management review held2027-04-06DOC-ISMS-085, MR-2027-01
Stage 1 (1.5 audit days)2027-04-12 to 2027-04-13CB Stage 1 report, received 2027-04-16
Stage 1 areas of concern closed2027-05-07DOC-ISMS-091 section 9
Stage 2 (3.5 audit days)2027-05-10 to 2027-05-12CB Stage 2 report, findings CBF-2027-01 to 08
Major nonconformity verified closed2027-06-09DOC-ISMS-093
Certification decision2027-06-15Certificate, expiry 2030-06-14

From decision to certification decision took 162 days, a little over five months, inside the six-month target.

3. Month 1: decide and start

In the first week the CEO signed a two-page business case (isms/isms-business-case, DOC-ISMS-029) built on the two contract renewals and a list of security questionnaires that took engineers about a day each. The project charter (isms/isms-project-charter, DOC-ISMS-009) named the CEO as sponsor, the Head of Engineering Operations as ISMS manager and project lead, and the leadership team as the steering committee meeting every two weeks.

A gap assessment against clauses 4 to 10 and Annex A (compliance/iso-27001-gap-assessment, DOC-ISMS-098) took the ISMS manager four days. The main gaps were the ones most young companies share: no documented scope, no risk methodology or register, no SoA, no internal audit, no management review, an informal process for contractor leavers and a supplier list that covered only paid infrastructure services.

Quillmere compared three accredited certification bodies with isms/certification-body-selection (DOC-ISMS-090), checked that each held ISO/IEC 27001 accreditation from a signatory of the Global ACI MRA (formerly IAF MLA), and selected the one shown as Bidder B in that template's worked example. The CB set audit time from ISO/IEC 27006-1: 1.5 days for Stage 1 and 3.5 days for Stage 2, 5.0 audit days for the initial audit (Example). The roadmap (isms/isms-implementation-roadmap, DOC-ISMS-030) was then fixed around the CB's available dates.

4. Month 1: context and scope

The context and interested parties record (isms/isms-context-interested-parties, DOC-ISMS-003) listed issues such as customer demands for certification, dependence on one cloud provider, a tight labour market for security skills and data protection obligations as processor. Following Amd 1:2024 to clause 4.1, the team considered whether climate change was a relevant issue; they judged it relevant only through the cloud provider's regional resilience, already covered by the DR region.

Extract 1: scope statement and interfaces (Example). Full format: compliance/ms-scope (DOC-ISMS-002), sections 4 and 5.

Scope statement (Example): "The information security management system covering the development, operation and support of the Quillmere Analytics SaaS platform, including the office, remote staff and the production and DR environments hosted by a public cloud provider."

IDInterface or dependencyDirectionPartyControl
INT-01 (Example)Infrastructure, platform services and physical data centres for production and DRInto scopePublic cloud providerShared responsibility matrix, provider assurance report review, A.5.23
INT-02 (Example)Customer datasets uploaded for analysisInto scopeCustomers (controllers)Data processing agreements, A.5.34, encryption A.8.24
INT-03 (Example)Payroll and accountingOut of scope, outsourcedAccounting firmSupplier agreement, no access to customer data
INT-04 (Example)Support ticketing and code repository toolsInto scopeSaaS suppliersSupplier register DOC-ISMS-066, A.5.19 to A.5.22

The scope was approved at the steering committee on 2027-01-29 as DOC-ISMS-002 v1.0. Every person working on the platform, all 46, fell inside it.

5. Month 2: risk assessment and treatment

The ISMS manager adapted the methodology (compliance/risk-methodology, DOC-ISMS-010): likelihood 1 to 5 times impact 1 to 5, score 1 to 25, bands Low 1-4, Medium 5-9, High 10-16, Critical 17 to 25 (in practice 20 and 25). Risk criteria and appetite went into isms/isms-risk-appetite-criteria (DOC-ISMS-015), and workshops with each team produced the register (compliance/risk-register, DOC-ISMS-016) using the threat and vulnerability catalogue (isms/isms-threat-vulnerability-catalogue, DOC-ISMS-018).

Extract 2: risk register entry (Example). Full format: compliance/risk-register (DOC-ISMS-016), section 3; acceptance in isms/isms-risk-acceptance-record (DOC-ISMS-019), worked example ACC-001.

IDCategoryAsset or processSourceRisk description (cause, event, consequence)AppetiteInherent LInherent IInherent score and levelTreatmentControls (Annex A)Residual LResidual IResidual score and levelOwnerAccepted on and expiryStatus
R-018 (Example)Confidentiality of customer and personal dataLegacy scheduled export serviceTHR-006, VUL-013, VUL-001The service uses local accounts instead of the identity provider, so a leaver's account could stay usable and export customer datasets (confidentiality)Averse3412 HighModify with compensating controls, then accept; replace the service in Q3 2027 (RTP-019)A.8.5 secure authentication, A.5.18 access rights review, A.8.16 monitoring activities, A.8.3 information access restriction248 MediumHead of Product2027-03-31, expires 2027-09-30 (ACC-001)Accepted

Because the category appetite was Averse, the appetite rules escalated acceptance one level, and the CEO accepted the residual risk on 2027-03-31 after the ISMS manager's review. The scores add up on the 5 x 5 scale: 3 x 4 = 12 (High) before, 2 x 4 = 8 (Medium) with the compensating controls, and a target of 1 x 4 = 4 (Low) once the service is replaced.

R-018 was the one acceptance that was fully documented at this stage. The treatment plan (compliance/risk-treatment-plan, DOC-ISMS-013) was drafted on 2027-02-26, but the team did not obtain risk owners' approval of the plan or their acceptance of the other residual risks. That gap returns in section 11.

6. Month 2 to 3: Statement of Applicability

The SoA compared the controls chosen in risk treatment with all 93 Annex A controls (37 organizational, 8 people, 14 physical, 34 technological). Each row gives a basis code: R (risk), L (law), C (contract), B (business need).

Extract 3: Statement of Applicability rows (Example). Full format: compliance/statement-of-applicability (DOC-ISMS-011), section 4.

ControlShort label (not official title)ApplicableBasisJustificationStatusReference documentEvidence
A.5.18 (Example)Access rights provisioning and reviewYesR, CLeaver and privilege risks (R-018); customer contracts require timely removal of accessImplementedAccess control policy DOC-ISMS-041Quarterly access review records, HR leaver list reconciliation
A.5.23 (Example)Security for cloud service use (new in 2022)YesR, CProduction and DR hosted on one public cloud provider (INT-01)ImplementedCloud services security policy DOC-ISMS-044Provider assurance report review
A.7.4 (Example)Physical security monitoring (new in 2022)YesROffice holds network equipment and laptops in storage; data centres are covered by the cloud provider under A.5.23ImplementedPhysical security policy DOC-ISMS-055Badge access logs, alarm monitoring contract
A.8.13 (Example)Information backupYesR, CCustomer datasets and configuration must be recoverable in the DR regionImplementedBackup policy DOC-ISMS-061Backup and restore test log DOC-ISMS-071
A.8.30 (Example)Outsourced developmentNoBAll code is written by staff under Quillmere's direct supervision; no development is outsourced (confirmed against the supplier register)Not applicableSoA section 5Supplier register DOC-ISMS-066

The SoA was approved as DOC-ISMS-011 v1.1 on 2027-03-10. The evidence column was the start of the control evidence matrix (isms/control-evidence-matrix, DOC-ISMS-033), which later saved hours at Stage 2.

7. Month 2 to 3: objectives and control implementation

Six objectives went into the objectives register (compliance/objectives-register, DOC-ISMS-024) in February. Most work in months 2 and 3 went into implementing treatment actions: connecting more tools to single sign-on, writing the access control policy (isms/access-control-policy, DOC-ISMS-041), the backup policy, the supplier register and the security event reporting procedure, and running awareness training for all staff.

Extract 4: objective and plan (Example). Full format: compliance/objectives-register (DOC-ISMS-024), sections 1 and 2.

IDObjectiveSource (policy or risk)MetricBaselineTargetDueOwnerStatus
OBJ-IS-02 (Example)Remove all access of leavers within 1 business dayAccess control policy DOC-ISMS-041; risk R-018Percentage of leavers whose access to every in-scope system is removed within 1 business day of the last working day78% (7 of 9 leavers, 2026-09-01 to 2027-02-28)100%2027-09Head of Engineering OperationsAt risk (April 2027)
ObjectiveWhat will be doneResourcesWhoWhenHow results are evaluated
OBJ-IS-02 (Example)Route contractor leaver requests through HR; connect remaining tools to single sign-on; reconcile the HR leaver list with active accounts monthly10 engineer days, ISMS manager timeHead of Engineering Operations2027-04 to 2027-09Monthly reconciliation report, quarterly access review

The baseline was added after the internal audit (section 8): at first, four of the six objectives had targets but no baseline.

8. Month 3: internal audit

An external contract auditor carried out the first internal audit (IA-2027-01) from 2027-03-15 to 2027-03-17 against clauses 4 to 10 and 30 Annex A controls, using isms/isms-internal-audit-checklist (DOC-ISMS-083). The report, issued on 2027-03-29, recorded 0 major nonconformities, 2 minor nonconformities, 1 observation and 1 opportunity for improvement.

Extract 5: internal audit finding (Example). Full format: isms/isms-internal-audit-report (DOC-ISMS-084), section 7; tracked in isms/audit-findings-register (DOC-ISMS-086).

FieldContent (Example)
FindingAF-2027-002, minor nonconformity, control A.5.18 as implemented by the access control policy
RequirementSoA DOC-ISMS-011 marks A.5.18 Implemented; DOC-ISMS-041 requires all access of a leaver to be removed within 1 business day of the last working day
EvidenceHR leaver list and identity provider audit log export of 2027-03-16. Seven employee leavers removed on the last working day; two contractor leavers removed 4 and 6 business days late, requested by the engineering manager, not HR
Extent2 of 9 leavers (both contractors, 2 of 2 contractor leavers)
StatementAccess of departing contractors is not removed within the time the policy requires
Risk or effectFormer contractors kept access to the code repository and the support tool after leaving; linked risk R-018
Owner and dueHead of Engineering Operations, with Finance for contractor contracts; response due 2027-04-28
Follow-upCorrective action NC-2027-005 (contractor leavers routed through HR); closure verified by the lead auditor on 2027-05-20

The other minor nonconformity (AF-2027-001) found that monthly metric results were collected but not analysed for three months; the opportunity for improvement (AF-2027-004) produced the objective baselines shown in section 7.

9. Month 4: management review

The first management review (MR-2027-01) took place on 2027-04-06, a week after the internal audit report, with the CEO, the leadership team and the ISMS manager. Inputs included the audit results, the risk register summary, objective status, supplier issues and the first security events.

Extract 6: management review decisions (Example). Full format: compliance/management-review (DOC-ISMS-085), sections 4 and 5.

IDResult typeDecisionOwnerDue
MR-D-01 (Example)Continual improvementFix the monthly metric review in the ISMS calendar with a named deputy, so that AF-2027-001 cannot recurISMS manager2027-04-30
MR-D-02 (Example)Change to the management systemApprove access control policy DOC-ISMS-041 v1.1: contractor leaver requests come from HR, not from line managersHead of Engineering Operations2027-04-15
MR-D-03 (Example)Resource needsApprove 10 engineer days to connect the remaining tools with local accounts to single sign-on, scheduled for Q3 2027CEO2027-09-30
MR-D-04 (Example)Change to the management systemConfirm readiness for Stage 1 on 2027-04-12CEO2027-04-12

Two weaknesses in this review shaped later events. The agenda did not record a review of the climate change decision from clause 4.1, which the Stage 1 auditor noted (section 10). And MR-D-03 scheduled the single sign-on work for Q3, after Stage 2, so tools with local accounts stayed outside the leaver process during the audit (section 11).

10. Month 4: Stage 1 audit

Stage 1 ran on 2027-04-12 and 2027-04-13 (1.5 audit days), largely remotely. The ISMS manager had assembled the documents with isms/stage-1-readiness-pack (DOC-ISMS-091): scope, policy, methodology, risk register and treatment plan, SoA, objectives, competence records, the internal audit report and the management review minutes.

The auditor confirmed the scope, the 46 persons in scope and the Stage 2 plan: 3.5 audit days from 2027-05-10 to 2027-05-12 (for example a lead auditor for three days and a second auditor for half a day), on site at the office with remote demonstrations of the cloud environment. The Stage 1 report, received on 2027-04-16, raised three areas of concern: the climate change decision from clause 4.1 was neither recorded in the context record nor reviewed at the management review (AOC-01), the management review had not covered feedback from interested parties (AOC-02), and two persons in scope had not completed awareness training (AOC-03). Quillmere copied them into the tracker in section 9 of the readiness pack, logged the climate change item as AF-2027-005 in the audit findings register, updated the context record and the management review agenda, and closed all three by 2027-05-07, before Stage 2.

The auditor did not raise the unsigned treatment plan at Stage 1. Stage 1 is a readiness review, not a complete audit; silence at Stage 1 is not clearance.

11. Month 5: Stage 2 audit

The CB audit team spent 3.5 audit days over three calendar days, 2027-05-10 to 2027-05-12, interviewing the CEO, the ISMS manager, engineers, HR and support staff, and sampling records across the SoA, guided by isms/stage-2-audit-evidence-index (DOC-ISMS-092). At the closing meeting the lead auditor reported 1 major nonconformity, 3 minor nonconformities and 4 opportunities for improvement, and recommended certification subject to verified closure of the major.

Extract 7: Stage 2 findings and closure (Example). Full format: isms/certification-findings-action-plan (DOC-ISMS-093), sections 4 and 6.

ElementCBF-2027-01, major (Example)
FindingClause 6.1.3: no record that risk owners approved the risk treatment plan or accepted residual risks; 14 High risks without acceptance
CorrectionRisk owners reviewed DOC-ISMS-013 v1.0 on 2027-05-19; top management accepted the 14 High residual risks with treatment decisions on 2027-05-21, each recorded as an acceptance record (ACC-NNN) in DOC-ISMS-019
Extent checkAll 62 risks in DOC-ISMS-016 checked: 14 High lacked acceptance (the finding), 48 Low and Medium had acceptance recorded at the DOC-ISMS-010 authority (risk owner for Low, risk owner plus department head for Medium), 0 Critical open. 14 + 48 = 62
Root causeThe procedure described the approval step but named no one to trigger it and no deadline; the project plan ended risk work at "plan drafted"
Corrective actionsCA-01 approval step with a named trigger added to DOC-ISMS-010; CA-02 "risk owner approval and acceptance" fixed in the ISMS calendar DOC-ISMS-032 and the management review agenda; CA-03 all 9 risk owners briefed
Effectiveness criterionNext two plan updates approved within 10 working days, checked by internal audit in Q4 2027
CB resultVerified by document review on 2027-06-09
ElementCBF-2027-02, minor (Example)
FindingControl A.5.18: 1 of 10 sampled leavers kept access to the support ticketing tool for 9 days
CorrectionAccount disabled on 2027-05-12 during the audit; tool audit log reviewed, no activity after the leaving date
Extent check11 leavers in 12 months checked across 6 systems with customer data: 2 late removals out of 66 leaver-system pairs (11 x 6 = 66)
Root causeThe offboarding checklist listed only systems connected to single sign-on; the ticketing tool and code repository used local accounts
Corrective actionsCA-04 connect both tools to single sign-on by 2027-06-30 (brought forward from Q3); CA-05 "systems with local accounts" line added to isms/offboarding-security-checklist; CA-06 monthly HR leaver reconciliation from 2027-07-01
CB resultPlan accepted 2027-06-03; implementation to be checked at surveillance 1

The second finding is the same story as R-018, AF-2027-002 and MR-D-03: the internal audit fixed the contractor route, but tools outside single sign-on were still invisible to the leaver process. Following one risk through every record would have found it earlier.

12. Month 6: findings closure and certification decision

The CB's Example deadlines were 30 days for the plan (2027-06-11) and 90 days for evidence of the major (2027-08-10). Quillmere submitted the plan on 2027-05-26 and the major's evidence on 2027-06-02, both well inside the limits. The CB verified the major closed on 2027-06-09, and its independent decision maker, who had not been on the audit team, granted certification on 2027-06-15. The certificate expires on 2030-06-14 and references the SoA version the CB audited.

The first certification-year CB fees in the Example came to USD 8,100 for 5.0 audit days and the annual fee (see isms/certification-cycle-plan, section 11; use local currency). Quillmere then published its certificate under the CB's mark rules (isms/certification-mark-usage, DOC-ISMS-097) and sent it to both enterprise customers ahead of renewal.

13. After the certificate

The certification cycle plan (isms/certification-cycle-plan, DOC-ISMS-094) set the next steps (Example):

EventPlanned date (Example)Why
CA-04 to CA-06 implemented2027-07-01Minor nonconformity CBF-2027-02 checked at surveillance 1
R-018 acceptance review2027-09-01Acceptance ACC-001 expires 2027-09-30; legacy service replacement due Q3 2027
Internal audit cycle 12028-02-01Includes the effectiveness check of CA-01 to CA-03
Management review2028-03-20Inputs include all certification findings
Surveillance 12028-05-15 to 2028-05-16Before 2028-06-15, 12 months from the decision date
Surveillance 22029-05-14 to 2029-05-15Surveillance in calendar year 2029
Recertification audit2030-03-11 to 2030-03-13Decision needed before expiry on 2030-06-14

Eight weeks before surveillance 1, the ISMS manager runs isms/surveillance-readiness-health-check (DOC-ISMS-096).

14. Lessons learned

Lesson (Example)What Quillmere would do differentlyTemplate that helps
Approval is part of the risk processPut risk owner approval and acceptance on the project plan as tasks with dates, not as a side effect of draftingcompliance/risk-treatment-plan, isms/isms-risk-acceptance-record
Follow one risk through every recordBefore Stage 1, trace two or three High risks from register to SoA, controls, records, audit and reviewisms/control-evidence-matrix
Fix the class, not the instanceWhen the internal audit found contractor leavers, check every route out of the leaver process, including tools with local accountscompliance/capa-nonconformity
Resource decisions have audit datesSchedule work that closes a known gap before Stage 2, not aftercompliance/management-review
Cover every management review inputCompare the agenda with clause 9.3.2 before the meetingcompliance/management-review
Stage 1 silence is not clearanceSelf-check every clause before Stage 2 even if Stage 1 did not raise itisms/stage-2-audit-evidence-index
Baselines make progress visibleRecord a baseline when each objective is setcompliance/objectives-register

15. Size tiers: the same story at other sizes

StepSmall: Quillmere Analytics Ltd (Example)Medium: Quillmere Health Systems (Example)Large or multi-site: Quillmere Group (Example)
Profile46 staff, one office plus remote staff, SaaS on one public cloud in two regions320 staff, two offices and one colocation suite, processor and controller2,400 staff, 6 sites in 4 countries, OT and IT, ISO 9001 and ISO 22301 certified
TargetCertificate in 6 monthsISO/IEC 27001 in 10 months, ISO/IEC 27701 the year afterGroup certificate in 15 months, phased by site
TeamPart-time ISMS manager (0.5 FTE)Full-time ISMS manager plus a 3-person security teamCISO with a 14-person security office, integrated management system
Scope extractOne paragraph, four interfacesBoth offices, colocation suite, managed service; privacy roles statedGroup scope with a site list and wave plan (isms/scope-extension-multisite-plan)
Risk assessmentTeam workshops, one registerRegister per service with a central roll-upSite registers including OT, group roll-up to the integrated risk process
Internal auditOne external auditor, three daysInternal audit programme over several monthsRolling programme covering every site before certification
Management reviewLeadership meetingSecurity steering committee feeding the reviewIntegrated review with ISO 9001 and ISO 22301
Typical findingsMissing approvals, one person holding many rolesDifferent practice between the two officesSites at different maturity, OT exceptions

16. Records and evidence

StepRecord (Example)OwnerWhere keptRetention (Example)
DecideBusiness case DOC-ISMS-029, charter DOC-ISMS-009CEOISMS repository3 years after project close
ScopeDOC-ISMS-002 v1.0 and steering minute of 2027-01-29ISMS managerISMS repositoryCurrent plus superseded for 3 years
RiskDOC-ISMS-016 export, DOC-ISMS-013, acceptance ACC-001 in DOC-ISMS-019Risk owners, ISMS managerGRC folder3 years after the risk is closed
SoADOC-ISMS-011 v1.1ISMS managerISMS repositoryCurrent plus superseded for 3 years
ObjectivesDOC-ISMS-024 with monthly resultsISMS managerISMS repository3 years
Internal auditDOC-ISMS-084 IA-2027-01, DOC-ISMS-086Lead auditor, ISMS managerAudit folderCertification cycle plus 3 years
Management reviewDOC-ISMS-085 MR-2027-01 and action logCEOISMS repositoryCertification cycle plus 3 years
CertificationStage 1 and 2 reports, DOC-ISMS-093, decision letter, certificateISMS managerCertification folderCertificate validity plus 3 years

Map each record to its clause or control in isms/control-evidence-matrix (DOC-ISMS-033) and list it in isms/isms-documented-information-register (DOC-ISMS-028).

17. Your own project diary

MilestonePlanned dateActual dateRecord (ID and version)OwnerLesson or issue
Decision to certifyYYYY-MM-DDYYYY-MM-DDDOC-ISMS-029 [v][@sponsor][note]
Scope approvedYYYY-MM-DDYYYY-MM-DDDOC-ISMS-002 [v][@isms-manager][note]
Risk assessment and treatment plan approved by risk ownersYYYY-MM-DDYYYY-MM-DDDOC-ISMS-016, DOC-ISMS-013 [v][@risk-owners][note]
SoA approvedYYYY-MM-DDYYYY-MM-DDDOC-ISMS-011 [v][@isms-manager][note]
Objectives set with baselinesYYYY-MM-DDYYYY-MM-DDDOC-ISMS-024 [v][@isms-manager][note]
Internal audit report issuedYYYY-MM-DDYYYY-MM-DDDOC-ISMS-084 [ref][@lead-auditor][note]
Management review heldYYYY-MM-DDYYYY-MM-DDDOC-ISMS-085 [ref][@ceo][note]
Stage 1YYYY-MM-DDYYYY-MM-DDDOC-ISMS-091, CB report[@isms-manager][note]
Stage 2YYYY-MM-DDYYYY-MM-DDDOC-ISMS-092, CB report[@isms-manager][note]
Findings closedYYYY-MM-DDYYYY-MM-DDDOC-ISMS-093[@isms-manager][note]
Certification decisionYYYY-MM-DDYYYY-MM-DDCertificate [number]CB[note]

18. References

ReferenceEdition and linkUse
ISO/IEC 27001:2022 + Amd 1:2024https://www.iso.org/standard/82875.html ; Amd 1: https://www.iso.org/standard/88435.htmlRequirements followed in the walkthrough
ISO/IEC 27002:2022https://www.iso.org/standard/75652.htmlControl guidance behind the SoA rows
ISO/IEC 27005:2022https://www.iso.org/standard/80585.htmlRisk management guidance behind the risk entry
ISO/IEC 17021-1:2015https://www.iso.org/standard/61651.htmlCertification stages, findings and decision
ISO/IEC 27006-1:2024https://www.iso.org/standard/82908.htmlAudit time and ISMS-specific CB rules
ISO 19011:2026https://www.iso.org/standard/88984.htmlAuditing guidance for the internal audit

Related templates: isms/certification-audit-explained (LRN-ISMS-07), isms/isms-business-case (DOC-ISMS-029), isms/isms-project-charter (DOC-ISMS-009), compliance/iso-27001-gap-assessment (DOC-ISMS-098), isms/certification-body-selection (DOC-ISMS-090), isms/isms-implementation-roadmap (DOC-ISMS-030), isms/isms-context-interested-parties (DOC-ISMS-003), compliance/ms-scope (DOC-ISMS-002), compliance/risk-methodology (DOC-ISMS-010), isms/isms-risk-appetite-criteria (DOC-ISMS-015), compliance/risk-register (DOC-ISMS-016), compliance/risk-treatment-plan (DOC-ISMS-013), isms/isms-risk-acceptance-record (DOC-ISMS-019), compliance/statement-of-applicability (DOC-ISMS-011), compliance/objectives-register (DOC-ISMS-024), isms/isms-internal-audit-report (DOC-ISMS-084), isms/audit-findings-register (DOC-ISMS-086), compliance/management-review (DOC-ISMS-085), isms/stage-1-readiness-pack (DOC-ISMS-091), isms/stage-2-audit-evidence-index (DOC-ISMS-092), isms/certification-findings-action-plan (DOC-ISMS-093), isms/certification-cycle-plan (DOC-ISMS-094), isms/control-evidence-matrix (DOC-ISMS-033).

Standard and licence note

Structure aligned with ISO/IEC 27001:2022 + Amd 1:2024 and with the certification process that ISO/IEC 17021-1:2015 and ISO/IEC 27006-1:2024 set for certification bodies. The narrative, extracts and lessons are original; Quillmere Analytics Ltd and every figure, date and ID are fictional. No ISO or IEC text is reproduced; control labels are short descriptions, not official titles. Read the official standards (purchase or licensed access from ISO, IEC or your national standards body) before relying on any statement here, and check the current edition of each standard before use. Certification decisions are made only by the accredited certification body. This is a learning example, not certification or legal advice. Template licence: MIT.

Template liên quan