Project Brief Template

Pre-initiation outline: background, objectives, scope, constraints, outline business case with cost range, product description, approach options, management team, initiation request

Quản lý dự ánChuẩnStructure aligned with PRINCE2 7 (PeopleCert, 2023)brief
Mở trong editorTải .md

Cách dùng: Use it to get a decision on whether to fund initiation, before any detailed plan exists. Fill the objectives and the outline business case with ranges first, and name the executive. The main pitfall is fixing the solution in the brief instead of leaving approach options for initiation.

Xem trước

Project Brief: [Project name]

A project brief is the short pre-initiation document that sets out what a proposed project is for, what it should deliver, roughly how and at what cost, and who will direct it. The project board (or investment committee) uses it to decide whether to spend money on initiation, where the detailed plan and full business case are written. The structure is aligned with the project brief management product of PRINCE2 7 (PeopleCert, 2023) and suits any stage-gated organisation. Replace every [bracketed] value and every row marked Example.

Document control

FieldValue
Document ID[PB-PROJ-001]
Project[Project name] ([project code, if assigned])
Source mandate[Mandate, strategy item or request ID]
Version[0.1]
Status[Draft / Submitted / Approved / Superseded by initiation documentation]
Author[@project-manager]
Executive (sponsor)[@executive]
Last updatedYYYY-MM-DD
Classification[Internal]

Approvals

RoleNameDecisionDate
Executive (sponsor)[@executive][Approve initiation / Reject / Revise]YYYY-MM-DD
Senior user[@senior-user][Agree / Disagree]YYYY-MM-DD
Senior supplier[@senior-supplier][Agree / Disagree]YYYY-MM-DD

Revision history

VersionDateAuthorChange
0.1YYYY-MM-DD[@author]First draft from mandate
1.0YYYY-MM-DD[@author]Approved for initiation

The worked example is the fictional Brackwell Vale Housing Trust, a housing association managing 18,500 homes, proposing a Tenant Services Portal to replace its ageing tenant website.

1. Background

[Background]

Example: Tenants can report repairs and check rent only by phone or at an office. The contact centre handles about 210,000 calls a year, and the legacy housing system's tenant module reaches end of vendor support next year. The board's digital strategy asks for self-service for the most common requests.

2. Project definition

2.1 Objectives

IDObjectiveMeasureTarget
OBJ-1[Objective][Measure][Target and date]
OBJ-1 (Example)Tenants report repairs and pay rent onlinePortal live for all tenanciesBy YYYY-MM-DD
OBJ-2 (Example)Reduce contact centre demandShare of calls moved to self-service25% within 12 months of go-live

2.2 Scope and exclusions

In scopeOut of scope
[Item][Item]
Example: Repairs reporting, rent statements and payment, tenancy detailsExample: Replacing the core housing management system
Example: Migration of current tenancy dataExample: Leaseholder service charges (separate project)

2.3 Constraints and assumptions

TypeStatement
Constraint[Fixed date, budget, policy or technology]
Assumption[What must be true; to be checked in initiation]
Example: ConstraintMust be live before legacy vendor support ends
Example: AssumptionLegacy data can be exported through the vendor's standard interface

2.4 Users and interested parties

[Tenants, contact centre, repairs contractors, finance, IT, regulator if relevant.]

3. Outline business case

ItemValue
Reasons[Problem or opportunity]
Options considered[Do nothing, do minimum, do something]
Estimated cost range[Low to high]
Expected annual benefit[Amount and basis]
Indicative payback[Range]
Main risks[Top three]

Example: Estimated cost 1,000,000 to 1,300,000 EUR. Annual benefit about 255,500 EUR net: 52,500 calls moved to self-service (25% of 210,000) at 4.20 EUR a call is 220,500 EUR, plus 95,000 EUR legacy licence saving, minus 60,000 EUR portal running cost. Indicative payback 3.9 to 5.1 years. Main risks: legacy data quality, tenant digital access, supplier capacity.

4. Project product description

ItemValue
Final product[What is handed over]
Composition[Main parts]
Customer quality expectations[Expectations]
Acceptance criteria[Measurable criteria]
Acceptance method and responsibility[Who accepts and how]

Example: Acceptance criteria include: all current tenancies available in the portal, WCAG 2.2 AA conformance for public pages, payment service compliant with the card industry standard required by the payment provider, and the contact centre trained.

5. Project approach

OptionDescriptionInitial view
[Option][Description][Preferred / Possible / Rejected, reason]
Example: Buy and configure a housing portal productSoftware as a service, supplier configuresPreferred: fastest, vendor supports
Example: Build in-houseOwn development teamRejected: no in-house team

Proposed stages: [Initiation, then stages for delivery].

Example: Initiation (6 weeks), Design and procurement, Build and migrate, Rollout. Delivery inside stages uses two-week iterations.

6. Project management team

RoleNameNote
Executive (sponsor)[@executive]Accountable for the business case
Senior user[@senior-user]Represents those who use the outcome
Senior supplier[@senior-supplier]Represents those who build it
Project manager[@project-manager]Day-to-day management
Project assurance[@assurance]Independent check for the board

7. Request for initiation

ItemValue
Initiation budget[Amount]
Duration[Weeks], YYYY-MM-DD to YYYY-MM-DD
Tolerances[Time, cost]
Outputs of initiation[Initiation documentation, full business case, first stage plan]
Example: Initiation budget60,000 EUR, tolerance +/-10%

8. Related templates

Glossary

  • Project mandate: the trigger for the project from corporate, programme or portfolio management.
  • Executive: the board member accountable for the business case, often called the sponsor.
  • Initiation: the first stage, which plans the project and builds the full business case.
  • Project product description: the customer's description of the final product and how it will be accepted.

Standard and licence note

Structure aligned with the project brief management product of PRINCE2 7 (Managing Successful Projects with PRINCE2, 7th edition, PeopleCert, 2023). PRINCE2 is cited by name only: no text, tables or figures from the publication are reproduced, and the headings, wording and the fictional Brackwell Vale example are original. Official text: PeopleCert, purchase or licensed access: https://www.peoplecert.org/prince2. PRINCE2 is a registered trademark of PeopleCert. Check the current edition and your organisation's investment rules before use. Template licence: MIT.