After-Action Review Template (AAR)

After-action review: objectives and intent, timeline, planned vs actual, causes, sustain and improve, SMART improvement plan, follow-up (TC 7-0.1, HSEEP AAR/IP)

BesprechungenStandardUS Army TC 7-0.1 After Action Reviews (2025); FEMA HSEEP Doctrine (2020)afteractionreview

Anleitung: Use it straight after an exercise, event or operation to learn what to sustain and improve. Fill the objectives and agree the timeline before discussing causes. The main pitfall is lessons with no owner or date, so nothing changes before the next event.

Vorschau

After-Action Review: [Event, exercise or operation name]

An after-action review (AAR) is a guided, candid discussion held during or straight after an event, exercise or operation to establish what was supposed to happen, what actually happened, why, and what to sustain and improve. This template follows the four-step approach (plan, prepare, conduct, follow up) in US Army Training Circular TC 7-0.1, After Action Reviews (13 February 2025), and the After-Action Report/Improvement Plan (AAR/IP) structure in FEMA's Homeland Security Exercise and Evaluation Program (HSEEP) Doctrine (January 2020). Both are US government publications, cited and summarised in original words. Replace every [bracketed] value and every row marked Example. Worked examples use Pellmoor Transit Authority, a fictional bus operator, reviewing a winter-storm service disruption exercise.

Document control

FieldValue
Document ID[AAR-YYYY-NNN]
Event[Name, type (exercise, live operation, project milestone, event)]
Event date and locationYYYY-MM-DD, [location]
AAR dateYYYY-MM-DD
AAR type[Informal / Formal]
Facilitator[@facilitator]
Sponsor or senior leader[@sponsor]
Status[Draft / Final / Closed]
Classification[Internal / Restricted]

Approvals

RoleNameDate
Sponsor[@sponsor]YYYY-MM-DD
Facilitator[@facilitator]YYYY-MM-DD

Revision history

VersionDateAuthorChange
0.1YYYY-MM-DD[@facilitator]Draft from the review session
1.0YYYY-MM-DD[@facilitator]Findings validated, improvement plan agreed

1. The AAR process

Informal AARFormal AAR
Led byThe team's own leaderA trained facilitator, often from outside the team
PreparationLittle; held on site, straight after the eventPlanned with the event; data, venue and aids prepared
Typical length15 to 45 minutesHalf a day or more
OutputNotes and a short action listThis full document

2. Event summary and objectives

IDObjectiveTarget or standard
OBJ-1 (Example)Notify customers of each route suspensionPublic alert within 15 minutes of the suspension decision
OBJ-2 (Example)Activate the operations coordination roomRoom staffed within 60 minutes of the severe weather warning
OBJ-3 (Example)Reassign drivers to the eight priority routesAll eight routes staffed within 2 hours of activation
[OBJ-N][objective][target]

Example intent: keep the eight priority routes to hospitals and schools running, suspend other routes early and safely, and tell customers before they reach a stop.

3. Participants and ground rules

Name or groupRole in the eventRole in the AAR
[@name][role][Participant / Evaluator / Scribe / Facilitator]

Ground rules: this is a professional discussion, not a critique; nobody has all the information, whatever their rank; everyone takes part and nobody dominates; differing views are welcome; we focus on what happened and how to improve, not on who to blame.

4. What happened

TimeEventSource
06:00 (Example)Severe weather warning injected by exercise controlExercise log
06:45 (Example)Operations coordination room staffed and activeRoom sign-in sheet
07:10 (Example)Decision to suspend route 14Duty manager log
07:48 (Example)Customer alert for route 14 publishedAlert system timestamp
08:40 (Example)Six of eight priority routes staffedDispatch system
09:25 (Example)Last two priority routes staffedDispatch system
[hh:mm][event][source]

5. Planned versus actual

ObjectiveTargetActualRating
OBJ-1 (Example)15 minutes38 minutes (07:10 to 07:48)Not met
OBJ-2 (Example)60 minutes45 minutes (06:00 to 06:45)Met
OBJ-3 (Example)8 routes in 2 hours6 routes in 1 hour 55 minutes, all 8 in 2 hours 40 minutesPartly met
[OBJ-N][target][actual][rating]

6. Why it happened

ObjectiveCauseEvidence
OBJ-1 (Example)Alerts needed approval from the communications manager, who was not on the exercise roster; the duty manager waited 30 minutes for a replyDuty manager log, alert system audit trail
OBJ-3 (Example)The standby driver list was a spreadsheet on one supervisor's laptop and was not visible in dispatchParticipant accounts, dispatch notes
OBJ-2 (Example)Room activation checklist was rehearsed last quarter and printed at the doorEvaluator notes
[OBJ-N][cause][evidence]

7. Sustain: strengths

IDStrengthWhy it worked
S-01 (Example)Coordination room active 15 minutes ahead of targetRecent rehearsal and a printed checklist
[S-NN][strength][reason]

8. Improve: areas for improvement

IDIssueAnalysisImpact
AFI-01 (Example)Customer alerts delayed by single-person approvalNo delegate named for the approval stepCustomers waited at suspended stops in freezing weather
AFI-02 (Example)Standby driver list not visible in dispatchList held offline by one supervisorTwo priority routes started 40 minutes late
[AFI-NN][issue][analysis][impact]

9. Improvement plan

Action IDLinked toCorrective actionOwnerDueStatus
IP-01 (Example)AFI-01Name two delegates who can approve service alerts and pre-approve wording for route suspensions[@comms-manager]YYYY-MM-DD[Open / Done]
IP-02 (Example)AFI-02Move the standby driver list into the dispatch system and test it in the next drill[@dispatch-lead]YYYY-MM-DD[Open / Done]
IP-03 (Example)S-01Keep the quarterly room activation rehearsal in the training calendar[@ops-manager]YYYY-MM-DD[Open / Done]
[IP-NN][AFI or S ID][action][@owner]YYYY-MM-DD[status]

10. Follow-up and sharing

  • Draft shared with participants for validation within [5] working days.
  • Improvement plan actions added to the team's tracker with the same IDs.
  • Progress reviewed at [meeting or date] by [@sponsor].
  • Each corrective action tested in the next exercise or event, and the result recorded.
  • Lessons shared with [other teams or sites] in a form that names no individuals.

11. References

Standard and licence note

Based on public US government guidance: Department of the Army TC 7-0.1, After Action Reviews (13 February 2025, approved for public release), which describes the plan, prepare, conduct and follow-up steps, formal and informal AARs, and the review of what was supposed to happen, what happened, why, and how to sustain and improve; and FEMA's Homeland Security Exercise and Evaluation Program Doctrine (January 2020), which describes the AAR/IP, strengths, areas for improvement and corrective actions. The earlier and widely cited Army guide, TC 25-20, A Leader's Guide to After-Action Reviews (1993), does not appear on the Army's current list of training circulars as checked on 2026-10-30. The text of this template is original and summarises these sources; check the current versions on the official sites. Template licence: MIT.