How to use: Use it to set one resilience standard for a portfolio or platform before individual DR plans are written. Fill the tier model and objectives with the business first, then assign workloads and patterns. The main pitfall is treating multi-zone HA or replication as DR, which leaves no recovery from regional loss, corruption or ransomware.

Preview

Resilience Tiering and HA/DR Design: [Organisation, portfolio or platform]

Design document that classifies workloads into business criticality tiers, sets recovery and availability objectives per tier (MTD, RTO, RPO, availability target), and assigns a high availability (HA) and disaster recovery (DR) pattern, a data protection method, a topology and a test cadence to each tier. It defines the rules for tier inheritance across dependencies, failover and failback design, cost per tier and the exception process. The terms and the business impact analysis link follow NIST SP 800-34 Rev. 1 (Contingency Planning Guide for Federal Information Systems, public domain); the ICT readiness view follows the structure of ISO/IEC 27031:2025; the DR pattern names are those of the AWS Well-Architected Reliability pillar (backup and restore, pilot light, warm standby, multi-site active/active), with the equivalent Azure and Google Cloud terms. Replace every [bracketed] value and every row marked Example.

Document control

FieldValue
Document ID[RTD-001]
Scope[Organisation / Platform / Portfolio name]
Business impact analysis reference[BIA ID, version, date]
Hosting[Cloud provider(s), regions, data centres]
Version[0.1]
Status[Draft / In review / Approved / Superseded]
Owner[@resilience-architect]
Approvers/reviewers[@cio], [@business-continuity-manager], [@ciso], [@platform-lead], [@finance-partner]
Last updatedYYYY-MM-DD
Next reviewYYYY-MM-DD
Classification[Internal / Confidential]

Approvals

RoleNameDecisionDate
Business continuity manager[@name][Approve / Approve with conditions / Reject]YYYY-MM-DD
Chief information officer[@name][Decision]YYYY-MM-DD
Chief information security officer[@name][Decision]YYYY-MM-DD
Platform lead[@name][Decision]YYYY-MM-DD
Finance[@name][Decision]YYYY-MM-DD

Revision history

VersionDateAuthorChange summary
0.1YYYY-MM-DD[@name]First draft: tier model and objectives
0.2YYYY-MM-DD[@name]Example: Pattern catalogue and cost per tier added
1.0YYYY-MM-DD[@name]Example: Approved; 42 workloads assigned

Contents

1. Introduction and scope

1.1 Purpose

This design sets a small number of resilience tiers for [scope], the recovery and availability objectives each tier must meet, and the standard architecture patterns that achieve them. Workload teams pick their tier through the assignment process in section 4 and then build the pattern for that tier, instead of inventing a recovery approach per system. A shared set of patterns allows common tooling, common tests and comparable evidence, which is the practical benefit that public cloud reliability guidance also stresses.

1.2 HA and DR

  • High availability keeps a service running through frequent, local failures (an instance, a disk, a zone) without declaring a disaster. It is measured as availability over a period.
  • Disaster recovery restores a service after a rare, large disruption (loss of a region or site, destructive attack, major data corruption). It is measured per event, against RTO and RPO.
  • A design needs both. Replication improves availability but copies corruption and deletion; only point-in-time and isolated copies recover from those.

1.3 Scope

In scopeOut of scope
Example: All production workloads hosted on [cloud provider] and the two company data centresEnd-user devices and office networks
Example: Shared platform services: identity, DNS, network, secrets, CI/CD, observabilitySupplier SaaS beyond the contractual DR evidence collected in section 10
[Item][Item]

1.4 Design principles

IDPrincipleConsequence
RTP-001 (Example)Objectives come from business impact, not from current capabilityA workload that cannot meet its tier records an exception (section 14) with a remediation date
RTP-002 (Example)Use the cheapest pattern that meets the objectivesHigher tiers are justified by impact, and over-engineering is reviewed like under-engineering
RTP-003 (Example)A dependency is at least as resilient as what depends on itShared services sit in the highest tier they support (section 10)
RTP-004 (Example)Recovery relies on data plane operationsFailover does not depend on creating resources through a control plane that may be impaired
RTP-005 (Example)Untested recovery is assumed not to workEvery tier has a mandatory test cadence and evidence (section 12)
[RTP-NNN][Principle][Consequence]

2. Criticality tier model

2.1 Impact categories and scale

Rate impact for each category at each time interval on a 1 to 5 scale (1 negligible, 2 minor, 3 moderate, 4 major, 5 severe). Define each level in money, people or regulatory terms for your organisation.

CategoryWhat to considerLevel 4 means (Example)
FinancialLost revenue, penalties, extra costLoss above USD 500,000 or a contractual penalty
Customer and operationsCustomers or internal processes unable to actMost customers unable to pay or order
Regulatory and legalBreach of licence, reporting or statutory dutyReportable incident to a regulator
Safety and wellbeingHarm to peopleRisk of injury or loss of an essential service to vulnerable people
ReputationPublic and partner confidenceNational media coverage

2.2 Tier definitions

TierNameDefinitionTypical workloads (Example)
T0FoundationShared services without which no other tier can operate or recoverIdentity provider, DNS, core network, key management, secrets, backup platform
T1Mission criticalImpact reaches level 4 or 5 in any category within 4 hoursPayments, customer-facing ordering, trading, clinical systems
T2Business criticalImpact reaches level 4 within 24 hoursOrder fulfilment, customer service, warehouse operations
T3Business operationalImpact reaches level 4 within 5 daysReporting, analytics, internal workflow
T4DeferrableImpact stays below level 4 for 30 daysArchives, wikis, sandbox and training environments

The tier is the highest tier triggered by any category at any interval. T0 is assigned by role (section 10), not by impact scoring.

3. Recovery and availability objectives per tier

TierMTDRTORPOAvailability target (monthly)Allowed downtime per 30-day monthYearly equivalentMBCO during recovery (Example)
T0 (Example)2 h30 minNear zero (seconds)99.99%4.32 min52.6 minFull authentication; read-only admin
T1 (Example)4 h1 h5 min99.95%21.6 min4.38 hCore transactions at 50% of peak
T2 (Example)24 h8 h1 h99.9%43.2 min8.76 hCritical queues processed; reports deferred
T3 (Example)5 days72 h24 h99.5%3.6 h43.8 hRead access to last good copy
T4 (Example)30 days14 days7 days99.0%7.2 h87.6 hNone
[Tier][MTD][RTO][RPO][%][min or h][h][MBCO]

Allowed downtime in a 30-day month at availability AA is (1−A)×43,200(1 - A) \times 43{,}200 minutes, and the yearly equivalent is (1−A)×8760(1 - A) \times 8760 hours. Example: (1−0.9995)×43,200=21.6(1 - 0.9995) \times 43{,}200 = 21.6 minutes per month and (1−0.9995)×8760=4.38(1 - 0.9995) \times 8760 = 4.38 hours per year for T1, and (1−0.9999)×525,600=52.56(1 - 0.9999) \times 525{,}600 = 52.56 minutes per year for T0. Because the target is monthly, each month must stay within its own allowance; the yearly figure is not a budget that one bad month can spend.

Consistency rules (check each tier):

  1. RTO is shorter than MTD, leaving time for detection, the decision to invoke and verification. Example: T1 leaves 3 hours of margin.
  2. RPO is met by the data protection method of the pattern (section 8): worst-case data loss is roughly the backup or snapshot interval plus replication lag.
  3. Compare one DR event at full RTO with the downtime allowance. Example: a T1 event at the 1-hour RTO uses 1 / 4.38 = 23% of the yearly equivalent but is almost three times the T1 monthly allowance (21.6 minutes); a T2 event at 8 hours uses 8 / 8.76 = 91% of the yearly equivalent and about 11 times the monthly allowance (43.2 minutes). A monthly target is therefore missed in any month with a declared disaster. Decide whether declared DR events count against the availability SLO, or are reported separately against RTO, and write the rule in the SLO document (dev/slo-doc).
  4. Objectives apply to the business service, end to end, not to each component. Component objectives are derived in section 10.

4. Workload tier assignment

Workload IDWorkloadBusiness ownerHighest impact (category, interval, level)TierPattern (section 6)Meets objectives todayNotes
WL-001 (Example)Identity provider[@iam-lead]Role: all tiers depend on itT0Active-active across zones plus warm standby regionYesTested quarterly
WL-002 (Example)Payments API[@payments-owner]Financial, 1 h, level 5T1Warm standbyNo: RPO measured 12 minException EXC-RT-001
WL-003 (Example)Customer web shop[@ecommerce-owner]Customer, 4 h, level 4T1Warm standbyYes
WL-004 (Example)Order management[@ops-owner]Operations, 24 h, level 4T2Pilot lightYes
WL-005 (Example)Data warehouse[@data-owner]Financial reporting, 5 days, level 4T3Backup and restoreYesRestore measured at 30 h
WL-006 (Example)Team wiki[@it-ops]Operations, 30 days, level 2T4Backup and restoreYes
[WL-NNN][Workload][@owner][Category, interval, level][T0 to T4][Pattern][Yes / No][Notes]

Re-assess every workload when its business use changes and at least [annually], in line with the BIA review cycle.

5. Failure scenarios and scope of protection

Scenario IDScenarioTypical causeHA or DRT0T1T2T3T4
FS-001 (Example)Instance or node failureHardware, kernel, out-of-memoryHAYesYesYesYesBest effort
FS-002 (Example)Zone or data hall failurePower, cooling, networkHAYesYesYesRestoreRestore
FS-003 (Example)Region or site lossLarge outage, natural eventDRYesYesYesYesYes, slow
FS-004 (Example)Logical corruption or accidental deletionBug, operator errorDR from point-in-time copyYesYesYesYesYes
FS-005 (Example)Destructive attack (ransomware, wiper)Compromised credentialsDR from isolated, immutable copyYesYesYesYesYes
FS-006 (Example)Failed releaseChange defectHA through progressive delivery and rollbackYesYesYesYesYes
FS-007 (Example)Critical supplier or SaaS outageProvider incidentDepends on supplier evidenceAssessedAssessedAssessedAcceptedAccepted
FS-008 (Example)Cloud provider control plane impairmentProvider incidentDesign rule RTP-004YesYesPartlyAcceptedAccepted
[FS-NNN][Scenario][Cause][HA / DR][ ][ ][ ][ ][ ]

Accepted scenarios are listed here so that the business has approved the gap, not discovered it.

6. Pattern catalogue

6.1 HA patterns

Pattern IDPatternDescriptionProtects against
HA-01Redundant instances behind a load balancerN+1 or more instances with health checks; failed instances replaced automaticallyFS-001
HA-02Multi-zone deploymentInstances and data replicas spread across at least [two / three] zones in one region, each zone able to carry the load of a lost zoneFS-001, FS-002
HA-03Synchronous replicated data storeWrites committed in more than one zone before acknowledgement; automatic promotion of a standbyFS-002 with zero data loss
HA-04Progressive deliveryCanary or blue-green releases with automatic rollback on health signalsFS-006

6.2 DR patterns

The four DR strategies below are named and ordered as in the AWS Well-Architected Reliability pillar (best practice REL13-BP02), from lowest cost and complexity with the longest recovery to highest cost with the shortest recovery. Microsoft Azure Well-Architected uses "active-passive cold standby" and "active-passive warm standby" for the middle patterns, and the Google Cloud DR planning guide uses cold, warm and hot. The indicative ranges in the table are the ones the AWS pillar gives; use them only for first selection and replace them with your measured results.

Pattern IDPatternClosest Azure and Google terms (mapping is approximate)What runs in the recovery locationDataIndicative RPO and RTO (AWS pillar)Action at failover
DR-01Backup and restoreAzure: cold standby with no infrastructure running; Google: coldNothing; infrastructure defined as codeBackups copied to the recovery locationRPO hours, RTO 24 h or lessDeploy infrastructure and code, restore data
DR-02Pilot lightAzure: active-passive cold standby with minimal infrastructure; Google: between cold and warmCore services and data stores only; no application computeContinuous replication plus backupsRPO minutes, RTO tens of minutesCreate and scale compute, promote replicas, switch traffic
DR-03Warm standbyAzure: active-passive warm standby; Google: warmA scaled-down, fully working copy that can take trafficContinuous replication, live in recovery locationRPO seconds, RTO minutesScale up, promote replicas, switch traffic
DR-04Multi-site active/activeAzure: active-active; Google: hotFull capacity serving traffic in all locationsMulti-writer or partitioned replication with conflict handlingRPO near zero, RTO potentially zeroEvacuate the failed location; remaining locations absorb load

A warm standby scaled to full capacity is a hot standby. A point-in-time or immutable backup (section 8) is required with every pattern, because replication alone also replicates corruption and deletion. NIST SP 800-34 Rev. 1 describes the same spectrum for physical alternate sites (cold, warm, hot, mobile and mirrored sites); use those terms for data-centre recovery.

6.3 Pattern selection rule

Choose the lowest-cost pattern whose measured RTO and RPO meet the tier. Example: a T2 workload with RTO 8 h and RPO 1 h can use pilot light; backup and restore fails the RPO unless backups run at least hourly and the restore of all data stores is proven to finish inside 8 hours.

7. Reference design per tier

TierHA patternsDR patternData protectionRecovery locationFailover decisionMandatory evidence
T0 (Example)HA-01, HA-02, HA-03DR-04 or DR-03 at full scaleSynchronous in region, asynchronous across regions, immutable daily copySecond region in the same jurisdictionPre-approved, automated with human confirmationQuarterly regional failover test
T1 (Example)HA-01, HA-02, HA-03, HA-04DR-03Synchronous in region; asynchronous cross-region; point-in-time recovery 35 days; immutable copySecond regionIncident commander invokes with business ownerSemi-annual failover test with RTO and RPO measured
T2 (Example)HA-01, HA-02, HA-04DR-02Asynchronous cross-region replica; daily backups 35 daysSecond regionDR manager invokesAnnual failover test
T3 (Example)HA-01, HA-02 where cheapDR-01Daily backup copied cross-region; 90 daysSecond region or data centreDR manager invokesAnnual restore test
T4 (Example)HA-01 optionalDR-01Weekly backup; 90 daysAnyOwner requestsRestore test every two years

Example: the diagram shows the T1 reference design: HA-02 and HA-03 in the primary region, DR-03 in the recovery region and an immutable copy in a separate security boundary.

8. Data protection and replication

TopicRule (Example)
Synchronous versus asynchronousSynchronous replication within a region (zones are close enough for latency); asynchronous across regions, where distance makes synchronous writes too slow
RPO checkWorst-case loss is roughly backup interval plus replication lag; for asynchronous replicas, alert when lag exceeds half the tier RPO
Point-in-time recoveryEnabled for every T0 to T2 data store, retention at least [35] days
Immutable and isolated copiesDaily copy to a vault in a separate account or subscription, with write-once retention and separate administrators, for T0 to T3
Consistency across storesStores that reference each other are recovered to a common point (a consistency group or a recorded timestamp); reconcile messages and events after recovery
Encryption keysKeys are available in the recovery location and not deleted with the primary; key recovery is part of the test
Configuration and secretsInfrastructure code, images, configuration and secrets are replicated with the same RPO as the data

Example RPO check: a T1 database with continuous asynchronous replication and a p99 lag of 20 seconds meets an RPO of 5 minutes; a T2 store backed up every 4 hours does not meet an RPO of 1 hour and needs a replica or hourly snapshots.

Cross-reference: retention periods and restore steps for each data set are in the Backup and Restore Procedure (ops/backup-restore-procedure).

9. Zonal and regional topology

Location IDLocationRoleTiers hostedConstraints
LOC-01 (Example)[Provider] [Region A], 3 zonesPrimaryT0 to T4None
LOC-02 (Example)[Provider] [Region B], 3 zonesRecovery for T0 to T3T0 standby, T1 warm, T2 pilot lightSame jurisdiction; all required managed services available (checked YYYY-MM-DD)
LOC-03 (Example)Company data centre 1Primary for legacy systemsT2, T3Tape backup offsite
[LOC-NN][Location][Role][Tiers][Constraints]

Capacity in the recovery location: reserve or pre-approve capacity for T0 and T1 so that recovery does not compete with other customers of the same provider during a regional event. Record quotas and reservations with dates. Where data residency allows only one region, state the accepted regional risk explicitly and strengthen zonal design and isolated backups instead; check residency rules with the Data Residency and Sovereignty Assessment (compliance/data-residency-sovereignty-assessment).

10. Dependencies and tier inheritance

10.1 Inheritance rules

  1. A hard dependency of a tier-N workload must be tier N or higher, or the workload must keep working without it (a soft dependency with a documented degradation).
  2. Recovery order follows dependencies: T0 first, then each workload after the services it needs.
  3. Shared services used by T1 workloads are T0: identity, DNS, certificates and keys, secrets, network, logging needed for recovery, the deployment pipeline and the backup platform.
  4. External suppliers on a T1 or T2 path provide DR evidence (test reports, contractual RTO and RPO); record it in the supplier register, for example the ICT Third-Party Register (compliance/dora-ict-third-party-register) for financial entities.

10.2 Dependency check

WorkloadDependencyTypeDependency tierRule metAction
WL-002 Payments API (Example)WL-001 Identity providerHardT0YesNone
WL-002 Payments API (Example)Fraud scoring SaaSHardSupplier, RTO 4 hNo: T1 needs 1 hAdd fallback rule-based scoring as soft dependency
WL-003 Web shop (Example)Product search clusterHardT2NoRaise to T1 or degrade to category browse
WL-004 Order management (Example)WL-005 Data warehouseSoftT3YesNone
[WL-NNN][Dependency][Hard / Soft][Tier][Yes / No][Action]

10.3 Composite availability

A service that needs all of several components in series has an availability of roughly the product of theirs, assuming independent failures:

Aservice=∏i=1nAiA_{\text{service}} = \prod_{i=1}^{n} A_i

Example: three components at 99.95% each give 0.99953≈0.998500.9995^3 \approx 0.99850, that is 99.85%, below the T1 target of 99.95%. Redundancy raises component availability: two independent copies at 99.9% each give 1−(0.001)2=0.9999991 - (0.001)^2 = 0.999999. Independence is an assumption; shared zones, shared configuration and shared releases break it, so treat the result as an upper bound.

11. Failover and failback design

TopicDesign decision (Example)
Disaster thresholdDeclared when the business service is below its MBCO and in-place recovery is not expected within half the RTO
DecisionHuman-initiated, automated execution: one approved command or runbook step per tier; automatic failover only for HA within a region
Split brain preventionSingle writer enforced by a fencing step: the old primary is isolated before the replica is promoted
Traffic switchGlobal traffic manager or DNS with low time to live for T0 and T1; client caches tested for the actual switch time
Data plane relianceFailover uses pre-provisioned resources and data plane calls; no resource creation in an impaired control plane for T0 and T1
VerificationSynthetic transactions and reconciliation of in-flight messages before declaring recovery
FailbackSeparate, rehearsed procedure: rebuild the primary, resynchronise from the recovery location, switch in a planned window; or promote the recovery location permanently

The step-by-step activation, notification and recovery procedure for each system belongs in the IT Disaster Recovery Plan (ops/disaster-recovery-plan), sections 5 to 7.

12. Testing and validation

TierTest typeMinimum frequency (Example)What is measuredEvidence
T0Regional failover and failback in productionQuarterlyRTO, RPO, dependent workloads recoveringTest report, timings, issues
T1Failover of the full service to the recovery regionEvery 6 monthsEnd-to-end RTO, data loss against RPO, MBCO achievedTest report signed by business owner
T2Failover in production or a production-like copyAnnuallyRTO, RPOTest report
T3Full restore of data and rebuild from codeAnnuallyRestore duration, data integrityRestore log, checksums
T4Sample restoreEvery 2 yearsRestorabilityRestore log
AllTabletop exercise of decision makingAnnuallyDecision time, communicationExercise notes
T0 to T2Fault injection of zone loss and dependency failureQuarterlyHA behaviour, alertsExperiment records using the Chaos Experiment (ops/chaos-experiment)

Measured results replace the indicative ranges in section 6. A test that misses an objective opens a remediation item with an owner and a date, and the workload is reported as not meeting its tier until a retest passes. Exercise planning in NIST SP 800-34 Rev. 1 (testing, training and exercises) is a useful structure for the test programme.

13. Cost per tier

TierPatternAdditional annual cost per workload as share of primary run cost (Example)Main cost drivers
T0DR-04 or full-scale DR-0390% to 110%Duplicate capacity, cross-region data transfer, quarterly tests
T1DR-0335% to 60%Scaled-down standby, replication, reserved capacity, semi-annual tests
T2DR-0215% to 30%Replicated data stores, annual tests
T3DR-015% to 10%Backup storage and copies
T4DR-01Under 5%Backup storage

Example: a T1 workload with a primary run cost of USD 400,000 per year at a 45% uplift adds USD 180,000 per year for DR; moving it to T2 at a 20% uplift would add USD 80,000 but extend RTO from 1 hour to 8 hours. Put both options in front of the business owner with the impact scores from section 4.

Charge or show the resilience cost to the owning business unit, for example through the FinOps Cost Review (ops/finops-cost-review).

14. Exceptions and waivers

Exception IDWorkloadGapRisk accepted byCompensating measureRemediationExpires
EXC-RT-001 (Example)WL-002 Payments APIRPO measured 12 min against 5 min[@payments-owner], [@cio]Transaction journal replicated separately allows replayMove to synchronous journal replication, project [ID]YYYY-MM-DD
EXC-RT-002 (Example)Legacy billing (T2)No recovery region; data centre only; measured restore 30 h against the T2 RTO of 8 h[@finance-owner]Daily offsite backup, tested restore 30 hReplatform in wave [n]YYYY-MM-DD
[EXC-RT-NNN][Workload][Gap][@owner][Measure][Plan][Date]

Approval rule: exceptions for T0 and T1 are approved by [the CIO and the business continuity manager]; T2 and below by [the platform lead]. No exception lasts longer than [12] months without re-approval.

15. Governance, roles and traceability

15.1 RACI

ActivityBusiness ownerBusiness continuity managerResilience architectPlatform teamWorkload teamSecurity
BIA and impact scoringARCICC
Tier model and objectivesCARCIC
Tier assignment per workloadACRIRI
Pattern catalogue and reference designsICARCC
Implementation of the patternIICCAC
Testing and evidenceCACRRC
ExceptionsARCIRC

R: responsible, A: accountable, C: consulted, I: informed.

15.2 Traceability

BIA processWorkloadTierObjectivesPatternLast testResult
Example: Take customer paymentsWL-002T1RTO 1 h, RPO 5 minHA-02, HA-03, DR-03YYYY-MM-DDRTO 42 min met; RPO 12 min not met (EXC-RT-001)
Example: Ship ordersWL-004T2RTO 8 h, RPO 1 hHA-02, DR-02YYYY-MM-DDRTO 3.5 h, RPO 10 min, met
[Process][WL-NNN][Tier][Objectives][Patterns][Date][Result]

Map regulatory duties that apply, for example ISO/IEC 27001:2022 Annex A controls 5.29 and 5.30 on continuity and ICT readiness, or sector rules on operational resilience, to the rows above.

16. Risks and open decisions

IDTypeDescriptionOwnerDue
RTR-001 (Example)RiskRecovery region capacity not guaranteed for T1 during a regional event[@platform-lead]Capacity reservations agreed by YYYY-MM-DD
RTR-002 (Example)RiskShared CI/CD runs only in the primary region, blocking deployments during failover[@devops-lead]Pipeline in both regions by YYYY-MM-DD
RTD-OD-001 (Example)DecisionWhether DR events count against the availability SLO[@cio]YYYY-MM-DD
RTD-OD-002 (Example)DecisionWhether to rotate primary and recovery regions on a schedule[@resilience-architect]YYYY-MM-DD
[ID][Risk / Decision][Description][@owner][Date]

17. Glossary and references

17.1 Glossary

TermMeaning
MTDMaximum tolerable downtime: the longest a business process can be unavailable before the impact is unacceptable
RTORecovery time objective: the target maximum time to restore the service after a disruption
RPORecovery point objective: the maximum acceptable age of the data restored, measured back from the disruption
MBCOMinimum business continuity objective: the reduced service level accepted during recovery
HAHigh availability: continued service through local component or zone failures
DRDisaster recovery: restoration of service after a major disruption, usually in another location
Pilot lightRecovery location with data and core services running but no application compute
Warm standbyRecovery location with a scaled-down, working copy that can take traffic at once
FailbackReturning service to the primary location after a failover
Split brainTwo copies both accepting writes after a partition, causing divergent data

17.2 References

ReferenceVersion or date checkedUse
NIST SP 800-34 Rev. 1, Contingency Planning Guide for Federal Information Systems, csrc.nist.govMay 2010, updated 11 November 2010; checked 2026-10-23BIA, MTD, RTO and RPO terms, alternate site types, testing and exercises
ISO/IEC 27031:2025, Cybersecurity: Information and communication technology readiness for business continuity, iso.orgEdition 2, May 2025ICT readiness structure; MBCO, RPO and RTO as ICT continuity objectives
AWS Well-Architected Framework, Reliability pillar, REL13-BP01 and REL13-BP02, docs.aws.amazon.comChecked 2026-10-23DR strategy names and indicative ranges
Microsoft Azure Well-Architected Framework, Reliability, RE:09 Architecture strategies for disaster recovery, learn.microsoft.comPage dated November 2025, checked 2026-10-23Criticality tiers, cold and warm standby terms, failback as a separate process
Google Cloud Architecture Center, Disaster recovery planning guide, docs.cloud.google.comLast updated July 2024, checked 2026-10-23Cold, warm and hot pattern terms
ISO 22301:2019 with Amendment 1:2024, Business continuity management systems, iso.org2019, Amd 1 February 2024Business continuity management context
NIST SP 800-160 Vol. 2 Rev. 1, Developing Cyber-Resilient Systems, csrc.nist.govDecember 2021Cyber resiliency perspective for FS-005
[Internal BIA, SLO policy][Version][Use]

Standard and licence note

Based on NIST SP 800-34 Rev. 1 (public domain) for contingency planning terms and the link to the business impact analysis, and on the disaster recovery strategies described in the AWS Well-Architected Framework Reliability pillar, with the equivalent terms from the Microsoft Azure Well-Architected Framework and the Google Cloud DR planning guide. Structure aligned with ISO/IEC 27031:2025, which is a copyrighted standard: only its title, edition and the names of the continuity objectives it uses are cited, and no text, definitions or tables are reproduced. AWS, Microsoft Azure and Google Cloud are trademarks of their owners; this template is not affiliated with or endorsed by them. This template is original text written for this collection; tier objectives, cost ratios and results are examples, not normative values. Check the current official versions before use. Template licence: MIT.

Related templates