Risk Assessment and Method Statement (RAMS): [Activity]

A task-level document for one construction activity: the risk assessment (hazards, who is at risk, controls, residual risk) and the method statement (the safe sequence of work, people, plant, permits and emergency arrangements), with a briefing record signed by the people doing the work. It follows the five steps HSE describes for risk assessment under the UK Management of Health and Safety at Work Regulations 1999, and the job hazard analysis approach of OSHA publication 3071 with the hierarchy of controls OSHA recommends. Replace every [bracketed] value and every row marked Example. This is a documentation format, not legal or safety advice: check the current official text and a competent health and safety adviser. Facts checked October 2026.

Document control

FieldValue
RAMS ID[RAMS-FHL-011]
Activity[Install two rooflights to roof zone 2, grid C-D/4-5]
Project and location[Project name, area, level]
Contractor[Company carrying out the work]
Author[@name, role]
Version[1.0]
Status[Draft / Submitted / Accepted / Accepted with comments / Rejected]
Planned start and durationYYYY-MM-DD, [4 days]
Reviewed by (principal contractor)[@name]
Last updatedYYYY-MM-DD

Revision history

VersionDateAuthorChange summary
0.1YYYY-MM-DD[@name]First submission
1.0YYYY-MM-DD[@name]Example: Accepted after adding rescue plan and exclusion zone drawing

1. Scope of the activity

Example: Cut openings in roof zone 2 deck as marked on drawing FHL-MPA-01-R1-DR-A-00410 rev C02, install steel trimmers, upstands and two rooflight units lifted by the site crane, and make weathertight. Excludes the internal ceiling work below, which has its own RAMS.

Change reference: [VO-007, see construction/change-order-variation].

2. Risk rating method

Risk = likelihood (1 to 5) x severity (1 to 5). Ratings: 1 to 6 low, 8 to 12 medium, 15 to 25 high. Work does not start while any residual rating is high.

3. Risk assessment

IDHazard and how harm occursWho is at riskLSInitialControls (hierarchy level)LSResidual
H1 (Example)Fall through the new roof opening while cut and before the unit is fixedRoofers, others on roof3515Openings cut only immediately before fixing, to shorten exposure (administrative); edge protection around the work area and a fixed cover over the opening when unattended (engineering); permit and supervisor present (administrative)155
H2 (Example)Fall from the roof edgeRoofers2510Existing perimeter guardrails checked before start (engineering); no work outside the protected zone (administrative)155
H3 (Example)Struck by a load during the crane lift of the rooflight unitsRoofers, slinger, people below2510Lift plan by the appointed person; exclusion zone below; tag lines; lift outside school arrival and departure times (administrative)155
H4 (Example)Cuts and dust from cutting the deckRoofers326Cutter with blade guard and on-tool extraction (engineering); gloves and eye protection (PPE)224
H5 (Example)Fire from hot work on upstandsRoofers, building248Cold-applied detail where the specification allows (substitute); otherwise hot work permit, extinguisher at the work, fire watch for 60 minutes (administrative)144
H6 (Example)Manual handling of rooflight units on the roofRoofers339Units landed by crane next to the opening (eliminate carry); team lift of four for final positioning (administrative)224
[Hn][Hazard][Who][1-5][1-5][n][Controls and level][1-5][1-5][n]

Example check: H1 initial 3 x 5 = 15 (high); residual 1 x 5 = 5 (low).

4. Method statement

StepActionControls appliedResponsible
1Brief the team on this RAMS, lift plan and permits; sign section 8AllSupervisor
2Inspect perimeter guardrails and set up edge protection around the work areaH1, H2Supervisor
3Set exclusion zone below the openings and confirm the area is clearH3Supervisor with site manager
4Mark out openings from the drawing; check against the structureRoofer
5Cut the first opening with extraction; fit temporary cover until trimmers are inH1, H4Roofer
6Install steel trimmers and upstandsH1Roofer
7Crane lift of the rooflight unit to the landing position under the lift planH3, H6Appointed person, slinger
8Position and fix the unit; seal and flashH5, H6Roofers
9Repeat steps 5 to 8 for the second openingAllRoofers
10Remove the exclusion zone, clear waste, close permits, report to the site managerSupervisor

5. People, competence and supervision

RoleNumberCompetence evidence
Supervisor1[Supervisory safety training, experience]
Roofers3[Trade qualification, work at height training]
Slinger and signaller1[Lifting qualification]
Appointed person (lifting)1[Principal contractor's appointed person]

6. Plant, equipment, materials and permits

ItemCheck before useRecord
Example: Mobile crane and lifting accessoriesThorough examination certificates in date; pre-use checkLift plan LP-FHL-004
Example: Deck cutter with extractionGuard and extraction workingPre-use checklist
Example: Sealant and primerSafety data sheets read; ventilationSubstance assessment SA-FHL-021
PermitsExample: Hot work permit, lift plan approvalPermit register

7. Emergency and rescue arrangements

  • First aid: [first aider name and location of kit on the roof level].
  • Rescue from height: [method, equipment and who is trained].
  • Fire: follow the site fire plan in the construction phase plan section 11.
  • Emergency contact: [site manager phone]; incidents recorded in the daily site report (construction/daily-site-report).

8. Briefing record

NameCompanyRoleDateSignature
[Name][Company][Role]YYYY-MM-DD
[Name][Company][Role]YYYY-MM-DD

9. Review and acceptance

ReviewerDecisionCommentsDate
Principal contractor, site manager[Accepted / with comments / rejected][Comments]YYYY-MM-DD
Health and safety adviser[Decision][Comments]YYYY-MM-DD

Review again when: the method, team, plant or location changes; after any incident or near miss on this activity; or before restarting after a pause of more than [two weeks].

Standard and licence note

Based on the risk assessment steps HSE describes for the UK Management of Health and Safety at Work Regulations 1999 (HSE; HSE notes that an employer with five or more employees must record the significant findings), HSE guidance L153 on CDM 2015 (HSE), OSHA publication 3071 Job Hazard Analysis (2002, revised) and OSHA's hierarchy of controls (OSHA), with US construction rules in 29 CFR Part 1926, as checked in October 2026. The text is original. Check the current official guidance and your jurisdiction's rules; this is not legal or safety advice. Template licence: MIT.