Resource Management Plan Template

Resource demand by role and period, team structure, RACI, acquisition and onboarding, capacity vs demand, training and release

Gestión de proyectosEstándarresourceplanmath

Cómo usar: Use after the schedule is drafted to secure people and equipment. Fill demand by role and month first, then compare with committed capacity. Main pitfall: treating a name in the plan as a commitment without written agreement from line managers.

Vista previa

Resource Management Plan: [Project name]

Plan for the people, skills and equipment the project needs: requirements by role and period, team structure, RACI, acquisition and onboarding, capacity against demand, training and release. Based on common project management practice. Replace every [bracketed] value and every row marked Example.

FieldValue
Document ID[RP-PROJECT-001]
Project[Project name]
Version[0.1]
Owner[@project-manager]
Approved by[@sponsor, @resource-manager]
Related[Schedule SCH-001, WBS-001]
Last updatedYYYY-MM-DD

1. Approach

Resource demand was estimated from the work packages in [WBS-001] and the activity durations in [SCH-001]. Internal staff are allocated by their line managers through [resource management process]; external staff are contracted through procurement. The project manager directs day-to-day work; line managers keep responsibility for performance reviews and well-being.

2. Resource requirements by role and period

Demand in full-time equivalents (FTE) by month:

RoleSkills requiredJanFebMarAprMayJunSource
Example: Project managerHybrid delivery, vendor management1.01.01.01.01.00.5PMO
Example: Business analystProcess mapping, KYC regulation1.01.00.50.50.20Operations
Example: DeveloperTypeScript, REST integration02.03.03.01.00.5Vendor
Example: TesterTest automation, accessibility00.51.02.01.00.2QA pool
Example: Change and training leadAdult learning, communications0.20.50.51.01.00.5HR
[Role][Skills][x][x][x][x][x][x][Source]

Non-staff resources:

ResourceQuantityPeriodOwner
Example: Test environment (cloud)2 instancesFeb to Jun[@tech-lead]
Example: Training room1 room, 20 seatsApr to May[@facilities]
[Resource][n][Period][@owner]

3. Team structure

The project team is organised by workstream.

4. RACI matrix

Responsibilities for key deliverables and decisions:

Deliverable or decisionSponsorProject managerBA leadTech leadTest leadChange leadOperations head
Project management planARCCCCI
Target process designICRCICA
Platform buildIACRCII
User acceptance testingIACCRIC
Training deliveryIACIIRC
Go-live decisionARCCCCC

5. Acquisition and onboarding

Resources are acquired according to the plan below.

RoleMethodLead timeRequest byStatus
Example: Developers (3)Vendor contract, named team6 weeksYYYY-MM-DDContract signed
Example: Tester (additional 0.5 FTE)Internal QA pool request3 weeksYYYY-MM-DDRequested
[Role][Method][Lead time]YYYY-MM-DD[Status]

Onboarding checklist for each new team member:

  • Access to repository, issue tracker, chat channel and test environments, approved by the system owners
  • Briefing on objectives, plan, ways of working and the RAID log
  • Security and data protection induction where personal data is handled
  • Buddy assigned for the first two weeks

6. Capacity versus demand

Committed capacity is compared with demand per month; negative values are gaps.

RoleMonthDemand (FTE)Committed capacity (FTE)GapAction
Example: DeveloperMar3.03.00None
Example: TesterApr2.01.5-0.5Request from QA pool; fallback: extend UAT by 5 days
Example: Business analystFeb1.00.6-0.4Backfill operations duties for 4 weeks
[Role][Month][x][x][x][Action]

Utilisation is checked to avoid planning people above sustainable load:

Utilisation=Allocated hoursAvailable hours×100%,target≤85%\text{Utilisation} = \frac{\text{Allocated hours}}{\text{Available hours}} \times 100\%, \quad \text{target} \le 85\%

7. Training and development

Skills gaps in the project team are closed as follows.

Skill gapWhoTrainingWhenCost
Example: Accessibility testingTesters (2)Two-day practical courseBefore test stage1,600 EUR
Example: Identity service APIDevelopers (3)Vendor workshopBuild week 1Included in contract
[Gap][Who][Training][When][Cost]

8. Team management and recognition

The project manager provides written performance input to line managers at the end of each stage and when a team member leaves the project. Workload conflicts are raised at the weekly project board; unresolved conflicts follow the escalation path in the communication plan. Contributions are recognised at stage gates and in the closure report.

9. Release plan

Resources are released when their work is complete and knowledge has been handed over.

Role or resourcePlanned releaseHandover requiredRelease toNotified by
Example: Vendor developersYYYY-MM-DD (end of hypercare)Code walkthrough, runbooks to IT operationsVendor4 weeks before
Example: Business analystYYYY-MM-DDProcess documents to operations ownerOperations2 weeks before
Example: Test environmentsYYYY-MM-DDData deleted per retention policyInfrastructure2 weeks before
[Resource]YYYY-MM-DD[Handover][Destination][Notice]

Standard and licence note

Based on common project management practice for resource planning, responsibility assignment (RACI) and team management. This template is original text written for this collection. Template licence: MIT.