Steering Committee Report Template

Steering pack: executive summary, decisions requested, status dashboard, financials, escalated risks, change requests, roadmap

Gestión de proyectosEstándarsteeringcommitteereport

Cómo usar: Use before each steering committee meeting and send it three working days ahead. Fill decisions requested with options and a recommendation first. Main pitfall: a long status narrative that hides what the committee must decide.

Vista previa

Steering Committee Report: [Project name] – Meeting YYYY-MM-DD

Report to the project steering committee: executive summary, decisions requested, status dashboard, financials, escalated risks and issues, change requests, roadmap and next meeting. Based on common project governance practice. Replace every [bracketed] value and every row marked Example.

FieldValue
Project[Project name] ([code])
Meeting dateYYYY-MM-DD
Report number[5]
Prepared by[@project-manager]
Sponsor and chair[@sponsor]
Members[Names and roles]
Overall status[Green / Amber / Red], previous [Green / Amber / Red]
Stage[Build and test, gate G3 due YYYY-MM-DD]

1. Executive summary

[Three to five sentences on overall status, key achievements since last meeting, the main concern and what the committee is asked to decide.]

Example: The project is Amber. Design was approved and the vendor is building; go-live remains forecast for YYYY-MM-DD, but buffer use has reached 60% after the accessibility change. Cost forecast is 2% over the original baseline, within contingency. The committee is asked to approve CR-009 and to note the escalated vendor staffing risk.

2. Decisions requested

The committee is asked to make the following decisions.

#DecisionOptionsRecommendationImpactDeadline
D1Example: Approve CR-009, extend hypercare by 2 weeksA: approve (+12,000 EUR); B: rejectA, funded from contingencyCovers the first month-end cycle after go-liveYYYY-MM-DD
D2Example: Accept residual risk RSK-001 at score 12A: accept; B: fund backup developer (+20,000 EUR)A, with monthly reviewSaves 20,000 EUR; slight schedule exposureThis meeting
D3[Decision][Options][Recommendation][Impact]YYYY-MM-DD

Items for noting (no decision needed): [vendor change of account manager; training plan approved by HR].

3. Status dashboard

Status by dimension:

DimensionStatusTrendComment
ScheduleExample: AmberWorseM3 forecast +4 days; buffer 60% used
CostExample: GreenSteadyEAC 488,000 EUR vs BAC 478,500 EUR (+2%)
ScopeExample: GreenSteadyOne approved change (CR-007) this period
QualityExample: GreenBetterSeverity 1 and 2 defects down to 5
RisksExample: AmberSteadyOne High risk escalated (section 5)
BenefitsExample: GreenSteadyBaselines measured; targets unchanged

Milestones:

IDMilestoneBaselineForecastStatus
M2Design approvedYYYY-MM-DDAchieved YYYY-MM-DDAchieved
M3UAT completeYYYY-MM-DDYYYY-MM-DDAt risk
M4Go-liveYYYY-MM-DDYYYY-MM-DDOn track

4. Financials

Financial position at YYYY-MM-DD (EUR):

ItemApproved budgetActual to dateForecast at completionVariance
Cost baselineExample: 435,000241,000444,500-9,500
Contingency43,50018,000 used (CR-007)25,500 remainingn/a
Total budget478,500241,000488,000 incl. CR-009-9,500

Earned value indicators: CPI [0.97], SPI [0.94]. With EAC=BAC/CPIEAC = BAC / CPI, the cost forecast is consistent with the line above within [1%].

5. Risks and issues escalated

The following items are escalated.

IDDescriptionScore / priorityActions takenAsk of the committee
RSK-001Example: Vendor developers may be withdrawn for another client12 (Medium, was 16)Named-team clause enforced; extra developer addedAccept residual risk (D2)
DEP-002Example: CRM project needs our data feed earlier than plannedAt riskOptions analysed with CRM PMConfirm priority between the two projects
[ID][Description][Score][Actions][Ask]

6. Change requests

Change requests since the last meeting:

CR IDTitleImpactDecided byDecision
CR-007Example: Accessibility audit before UAT+18,000 EUR, +5 days (buffer)SponsorApproved with conditions
CR-009Example: Extend hypercare by 2 weeks+12,000 EURCommitteeFor decision (D1)
[CR-nnn][Title][Impact][Forum][Decision]

7. Benefits outlook

Expected benefits are unchanged from the business case. Baselines for B1 to B4 were measured on YYYY-MM-DD; the first post-go-live measurement is planned for YYYY-MM-DD.

8. Roadmap

The roadmap for the coming period is:

PeriodKey outcomesGate or decision
Next 4 weeksUAT complete, training 80% deliveredG3 readiness
4 to 8 weeksGo-live, hypercareGo-live decision
8 to 12 weeksHandover, closure reportG4 and closure

9. Actions from previous meeting

Status of actions from the last meeting:

#ActionOwnerDueStatus
A-12Example: Confirm HR release of staff for trainingHR directorYYYY-MM-DDDone
A-13Example: Agree data feed date with CRM projectProject managerYYYY-MM-DDOpen, see DEP-002
[A-nn][Action][@owner]YYYY-MM-DD[Status]

10. Next meeting

The next meeting is on YYYY-MM-DD. Expected decisions: [G3 gate approval, go-live date confirmation]. Pre-reads will be sent by YYYY-MM-DD.

Standard and licence note

Based on common project governance practice for steering committee reporting. This template is original text written for this collection. Template licence: MIT.