Construction RFI Log Template
Construction request for information log: drawing and spec references, required-by dates, answers, cost and time impact, change links
使い方: Use it to track site questions to designers from first issue to closed answer. Fill the drawing reference and required-by date for every RFI. The main pitfall is treating an answer that changes scope as an instruction without raising a change record.
プレビュー
Construction RFI Log: [Project name]
A register of construction requests for information (RFIs): questions from the site team or a contractor to the designers or contract administrator about drawings, specifications or site conditions, with the drawing and model references, the answer, the due dates and any cost or time impact. Based on common construction practice. This is the site RFI, not a procurement request for information (for that, see
business/rfi). Replace every[bracketed]value and every row marked Example.
Document control
| Field | Value |
|---|---|
| Log ID | [RFI-LOG-FHL] |
| Owner | [Contractor's design manager, @name] |
| Contractual response period | [Days stated in the contract, or agreed working days] |
| Last updated | YYYY-MM-DD |
1. RFI register
| RFI ID | Raised | Raised by | To | Subject and question | Drawing, revision, grid | Spec clause | Required by | Answered | Answer summary | Cost impact | Time impact | Change ref. | Status |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| RFI-041 (Example) | YYYY-MM-DD | Steel erector | Structural engineer | Connection detail for beam B12 at grid D/4 not shown; confirm bolt group | FHL-OKS-ST-02-DR-S-00220 rev C01, D/4 | [Clause] | YYYY-MM-DD | YYYY-MM-DD | Use standard detail SD-07 | None | None | Closed | |
| RFI-042 (Example) | YYYY-MM-DD | Roofing contractor | Architect | Client request for two extra rooflights: confirm sizes and trimming | FHL-MPA-01-R1-DR-A-00410 rev C01, C-D/4-5 | [Clause] | YYYY-MM-DD | YYYY-MM-DD | Revised drawing rev C02 issued | Yes | Yes | VO-007 | Closed |
| RFI-043 (Example) | YYYY-MM-DD | Groundworks | Architect | Existing drain found at grid A/1 clashing with pile cap PC-03; propose diversion | Survey drawing rev P02, A/1 | [Clause] | YYYY-MM-DD | Possible | Possible | Open | |||
| [RFI-nnn] | YYYY-MM-DD | [Who] | [Who] | [One question] | [Ref] | [Clause] | YYYY-MM-DD | YYYY-MM-DD | [Answer] | [None/Yes/Possible] | [None/Yes/Possible] | [VO-nnn] | [Status] |
2. Summary
| Measure | Value |
|---|---|
| Total raised | Example: 43 |
| Open | Example: 1 |
| Overdue (past required-by date, no answer) | Example: 0 |
| With cost or time impact | Example: 1 confirmed (RFI-042, linked to VO-007); 1 possible (RFI-043), change record to follow if confirmed |
Related: BIM issues tracked as BCF items in the BIM execution plan
(construction/bim-execution-plan), product approvals in
construction/submittal-register.
Standard and licence note
Based on common construction project practice for requests for information. The text is original. Check your contract for the formal procedure, response periods and notice requirements. Template licence: MIT.
関連テンプレート
BIM Execution Plan Template (ISO 19650)
ISO 19650 BIM execution plan: roles, EIR response, CDE workflow, naming and status codes, level of information need, TIDP and MIDP
建設Change Order and Variation Template (FIDIC, NEC4, AIA)
Construction change order or variation: instruction, cause, valuation build-up, time impact, approvals, running contract sum
建設Construction Phase Plan Template (CDM 2015, OSHA 1926)
Construction phase plan: dutyholders, site rules, significant hazards, Schedule 3 risks, welfare, emergency, incident reporting, inspections