Project Initiation Document Template

Integrated project baseline: definition, approach, business case summary, organisation, quality, change, risk and communication approaches, plan, tolerances, tailoring, benefits

プロジェクト管理フルStructure aligned with PRINCE2 7 (PeopleCert); ISO 21502:2020 clause 6.5initiationdocument

使い方: Use it at the end of initiation to get the project board to baseline the project and authorise the first delivery stage. Fill the project definition, organisation and tolerances first, then the approaches and plan. The main pitfall is tolerances without numbers, which pushes every deviation to the board.

プレビュー

Project Initiation Document: [Project name]

Project initiation document (PID): the integrated baseline that a project board approves at the end of initiation, before it authorises the first delivery stage. It brings together in one place what the project will deliver and why, how it will be organised and controlled, the approaches for quality, change, risk, communication and benefits, the project plan with its stages and tolerances, and how the method has been tailored. The structure is aligned with the initiation documentation of a staged, product-focused project method (see the standard and licence note) and with the initiating guidance of ISO 21502:2020. It suits any sector and any delivery approach, including agile delivery inside managed stages. Replace every [bracketed] value and every row marked Example.

Document control

FieldValue
Document ID[PID-PROJECT-001]
Project name and code[Project name], [PRJ-NNNN]
Version[0.1]
Status[Draft / Submitted / Approved / Updated / Closed]
Owner[Project manager]
Approver[Project board: executive, senior user, senior supplier]
Built from[Project brief or charter ID and version, mandate reference]
Current stage[Initiation / Stage N name]
Last updatedYYYY-MM-DD
Next planned review[End of stage N, YYYY-MM-DD]
Classification[Internal / Confidential]

Approvals

RoleNameDecisionReferenceDate
Executive (chair of the project board)[Name][Approved / Approved with conditions / Rejected][Board minutes ref]YYYY-MM-DD
Senior user[Name][Decision][Ref]YYYY-MM-DD
Senior supplier[Name][Decision][Ref]YYYY-MM-DD
Project assurance (review)[Name][Reviewed, findings closed][Ref]YYYY-MM-DD

Revision history

VersionDateAuthorChangeApproved by
0.1 (Example)YYYY-MM-DD[Project manager]First draft from approved project briefn/a
1.0 (Example)YYYY-MM-DD[Project manager]Baselined, stage 2 authorisedProject board
1.1 (Example)YYYY-MM-DD[Project manager]End of stage 2 update: plan, business case, risksProject board

Contents

1. Project definition

1.1 Background

[Two or three paragraphs: the problem or opportunity, why now, and the decision that started the project.]

Example: Varrowby Libraries Trust runs 14 branch libraries. Its library management system reaches the end of vendor support on YYYY-MM-DD, and staff spend about a quarter of counter time on routine issue and return. The trustees approved a project brief on YYYY-MM-DD to replace the system and introduce self-service lending in every branch.

1.2 Objectives

IDObjectiveMeasureTargetBy
OBJ-01 (Example)Replace the library management system before support endsNew system live in all branches14 of 14 branchesMonth 11
OBJ-02 (Example)Move routine lending to self-serviceShare of issues and returns made at kiosks70%3 months after go-live
OBJ-03 (Example)Deliver within the approved budgetOutturn against budgetGBP 1,180,000 within toleranceProject close
[OBJ-NN][Objective][Measure][Target][Date]

1.3 Scope and exclusions

In scopeOut of scope
Library management system, data migration from the old system (Example)Replacement of public access computers
42 self-service kiosks and security gates in 14 branches (Example)Building alterations beyond kiosk power and network points
Staff training and revised counter procedures (Example)Changes to opening hours
[Item][Item]

1.4 Constraints, assumptions and interfaces

IDTypeStatementOwner
CON-01 (Example)ConstraintGo-live must be before vendor support ends on YYYY-MM-DDExecutive
CON-02 (Example)ConstraintNo branch may close for more than two working days for installationSenior user
ASM-01 (Example)AssumptionBorrower records can be migrated without re-registrationSenior supplier
INT-01 (Example)InterfaceRegional library consortium catalogue (shared records)Consortium technical lead
[ID][Type][Statement][Owner]

2. Project approach

DecisionOptions consideredChoice and reason
Sourcing (Example)Build, buy a hosted system, join the consortium's shared systemBuy a hosted system: lowest risk to the support deadline, shared catalogue still possible through the consortium interface
Rollout (Example)All branches at once, phased by branch groupThree waves (pilot of 2 branches, then 6, then 6): lets the pilot inform training before 12 branches go live
Delivery method (Example)Fully predictive, iterative configuration in sprints inside stagesConfiguration and reports in two-week iterations; hardware rollout planned predictively
[Decision][Options][Choice and reason]

Standards the products must meet: [accessibility standard, data protection rules, organisational security policy, supplier contract terms]. Operational and maintenance considerations: [who runs the system after handover and what they need from the project].

3. Business case summary

ElementSummary (Example)
ReasonsSystem support ends; counter time spent on routine lending
Preferred optionHosted system with self-service, three waves
Expected benefits1.9 FTE of staff time released to reader development; old system support costs avoided (GBP 85,000 a year); longer self-service hours
Expected dis-benefitsFewer staff contacts for some borrowers during the first months
Project costGBP 1,180,000 (section 9.3)
Ongoing costHosting and kiosk maintenance GBP 96,000 a year from year 2
Timescale10 months to last branch live, project closed in month 11, benefits measured to month 24
Investment appraisal[Method and result from the business case]
Major risksData migration quality, kiosk supply lead times, staff adoption
Viability at end of initiation[Still viable / Viable with conditions / Not viable]

Full business case: [BC-NNN] (business/business-case).

4. Project organisation

RoleNameResponsibilities (summary)Time commitment
Executive (Example)[Name]Owns the business case, chairs the board, final decision maker1 day a month
Senior user (Example)[Name]Represents branches and borrowers, specifies needs, confirms benefits2 days a month
Senior supplier (Example)[Name]Commits supplier resources, accountable for the quality of what is supplied1 day a month
Project assurance (Example)[Name]Independent check on business, user and supplier interests for the board2 days a month
Change authority (Example)Project manager up to limits in section 10Decides requests for change within delegated limitsAs needed
Project manager (Example)[Name]Day-to-day management within stage tolerancesFull time
Team managers (Example)[Names]Deliver agreed work packagesFull time
Project support (Example)[Name]Configuration management, plan and log maintenance50%

Role descriptions: [link to the agreed descriptions]. Responsibility for each product: business/raci. Stakeholders and their interests: project/stakeholder-register.

5. Quality management approach

ItemApproach (Example)
Customer quality expectationsKiosks work for borrowers with limited sight or mobility; no loss of borrower or loan history
Project acceptance criteria100% of active borrower records migrated and reconciled; kiosks meet accessibility checks; 95% of test scripts passed with no open severity 1 defects
Quality methodsProduct descriptions with quality criteria for every major product; peer review of configuration; supplier factory test; user acceptance test per wave
Quality recordsQuality register maintained by project support
AcceptanceSenior user accepts each wave; executive accepts the final product at closure
RolesQuality reviews chaired by team managers; project assurance samples records each stage

Detailed plan: project/quality-management-plan.

6. Change control approach

ItemApproach (Example)
Issue typesRequest for change, off-specification, problem or concern
ProcedureCapture, assess impact on time, cost, quality, scope, benefits and risk, propose, decide, implement
Change authorityProject manager: changes up to GBP 5,000 and no milestone move; senior user and executive jointly: up to GBP 25,000; project board: above that
Change budgetGBP 30,000 held by the board for approved requests
Configuration managementProduct baselines and versions recorded in the configuration register; supplier configuration under its own control with monthly status exchange
RecordsIssue register, change log, daily log for informal issues

Detailed procedure and forms: project/change-control.

7. Risk management approach

ItemApproach (Example)
ProcedureIdentify, assess, plan responses, implement, communicate; review at every weekly checkpoint
ScalesProbability 1 to 5 and impact 1 to 5 on time, cost and service, defined in the risk register
Risk toleranceAny risk scoring 15 or above, or any risk to the support deadline, is escalated to the executive within two working days
Risk budgetIncluded in the plan contingency of GBP 70,000 (section 9.3)
RolesRisk owners named on the board or team; project manager maintains the register
ReportingTop risks in every highlight report; full review at each stage boundary

Top initiation risks:

IDRiskProbabilityImpactOwnerResponse
RSK-01 (Example)Borrower data quality causes migration rework, delaying wave 134Senior supplierData cleansing sprint before trial migration
RSK-02 (Example)Kiosk lead time exceeds 10 weeks, delaying waves 2 and 324Senior supplierOrder at end of stage 2, framework supplier as fallback
RSK-03 (Example)Staff resist self-service, low kiosk use33Senior userBranch champions, early involvement in pilot
[RSK-NN][Risk][1 to 5][1 to 5][Owner][Response]

Register: compliance/risk-register or the RAID log project/raid-log. For a probabilistic view of schedule and cost risk on a large project, see project/schedule-risk-analysis.

8. Communication management approach

AudienceInformationMethodFrequencyOwner
Project board (Example)Highlight reportEmail, board portalEvery two weeksProject manager
Trust leadership team (Example)Stage summaryLeadership meetingAt each stage boundaryExecutive
Branch managers (Example)Rollout schedule, training datesBriefing callMonthly, weekly during their waveTeam manager: rollout
Branch staff (Example)What changes, trainingIntranet page, drop-in sessionsMonthlyTeam manager: training
Borrowers (Example)Kiosk introduction, short closuresPosters, website, newsletterFour weeks before each waveCommunications officer
[Audience][Information][Method][Frequency][Owner]

Full plan: project/communication-plan. Stakeholder analysis: project/stakeholder-register.

9. Project plan

9.1 Stages and major products

StagePurposeMajor productsEnds with
1 Initiation (Example)Plan and baselineThis PID, stage 2 planBoard authorises stage 2
2 Design and procurement (Example)Configure the system, contract kiosksConfigured system (release 1), kiosk contract, data migration designBoard authorises stage 3
3 Pilot (Example)Prove in 2 branchesMigrated pilot data, 6 kiosks live, revised proceduresBoard authorises stage 4
4 Rollout (Example)12 branches in two waves36 kiosks live, trained staff, final migrationBoard authorises closure
5 Closure (Example)Hand over and closeAcceptance, lessons report, end project reportBoard closes project

9.2 Milestones

IDMilestoneBaseline dateOwner
MS-01 (Example)PID approvedMonth 1Executive
MS-02 (Example)Kiosk contract signedMonth 3Senior supplier
MS-03 (Example)Pilot branches liveMonth 6Senior user
MS-04 (Example)Wave 2 live (6 branches)Month 8Senior user
MS-05 (Example)Wave 3 live (6 branches), old system offMonth 10Senior user
MS-06 (Example)Project closedMonth 11Executive

9.3 Budget

ItemCost (Example, GBP)
Library management system implementation and first-year hosting410,000
42 kiosks and 14 sets of security gates, installed380,000
Data migration and cleansing90,000
Internal staff time (project team and backfill)160,000
Training and communication40,000
Base cost1,080,000
Contingency for identified risks (held by the project manager within tolerance)70,000
Change budget (held by the board, section 6)30,000
Total project budget1,180,000

Planning assumptions: [resource availability, supplier lead times, calendar, rates]. Detailed schedule: project/project-schedule. Resources: project/resource-plan. Work breakdown: project/work-breakdown-structure.

10. Project controls and tolerances

ToleranceProject level (set by corporate)Stage level (set by the board)Work package (set by the project manager)
Time (Example)+4 weeks on MS-05, none on the support deadline+2 weeks per stage+5 working days
Cost (Example)+5% of total budget+8% of stage budget, within project tolerance+10% of package cost
Scope (Example)Must-have requirements: noneShould-have: may defer up to 3 with senior user consentAs in the work package
Quality (Example)Acceptance criteria in section 5: noneSeverity 2 defects open at stage end: up to 5As in product descriptions
Benefits (Example)Self-service share at least 60% (target 70%)n/an/a
Risk (Example)No risk with score 20 or above unescalatedScore 15 or above escalatedReport any new risk at checkpoint
ControlWhenContentTo
Stage boundary review (Example)End of each stageEnd stage report, next stage plan, updated PIDProject board
Highlight report (Example)Every two weeksProgress against stage plan and tolerancesProject board
Checkpoint report (Example)WeeklyWork package progressProject manager
Exception report (Example)When a forecast breaches stage toleranceCause, options, recommendationProject board
End project report (Example)ClosurePerformance against PID, benefits statusProject board

Templates: highlight report project/highlight-report, exception report project/exception-report, end stage report project/end-stage-report, work package project/work-package, closure project/project-closure-report, cost and schedule performance project/earned-value-report.

11. Tailoring

ElementStandard practice in the organisationTailoring for this projectReason
Stage count (Example)Initiation plus at least two delivery stagesInitiation, three delivery stages, closureRollout waves need board go or no-go decisions
Reports (Example)Monthly highlight reportEvery two weeks during stages 3 and 4Short waves
Configuration delivery (Example)Predictive work packagesTwo-week iterations with a product backlog inside stage 2Configuration needs fast user feedback
Senior supplier (Example)Single personShared by Head of Digital and the supplier account directorExternal supplier delivers most of the system
Logs (Example)Separate issue, risk and quality registersSingle RAID log plus quality registerProject size
[Element][Practice][Tailoring][Reason]

12. Benefits management approach

IDBenefitMeasureBaselineTargetWhen measuredAccountable
BEN-01 (Example)Staff time released from routine lendingFTE equivalent from counter time study01.9 FTEMonths 3 and 12 after last waveSenior user
BEN-02 (Example)Support cost avoidedAnnual support costGBP 85,000 a year0Year 1 after closureExecutive
BEN-03 (Example)Self-service useShare of issues and returns at kiosks0%70%Monthly from go-live to month 12Senior user
[BEN-NN][Benefit][Measure][Baseline][Target][When][Owner]

Full plan: project/benefits-realization-plan. Post-project review: project/post-implementation-review.

13. Further approaches

ApproachNeededSummary or link
Commercial management (procurement, supplier contracts) (Example)YesTwo contracts (system, kiosks), monthly supplier reviews; project/procurement-plan
Sustainability (Example)YesKiosk energy rating criterion in tender; old hardware sent to certified reuse partner
Digital and data (Example)YesBorrower data handled under the Trust's data protection policy; data protection impact assessment before trial migration
Health and safety (Example)YesSupplier installation method statements approved by facilities before each wave
[Approach][Yes / No][Summary or link]

14. Initiation exit criteria and authorisation

CheckAnswer (Example)
Business case viable and consistent with the plan costsYes, BC v1.1 matches section 9.3
Every role in section 4 filled by a named person who has agreedYes
Tolerances set at every levelYes, section 10
Next stage plan ready for approvalYes, stage 2 plan v1.0
Top risks owned with responsesYes, section 7
Approaches agreed by the people who must apply themYes, team managers and supplier signed off
Tailoring recordedYes, section 11
DecisionDetail
Project board decision[Approve PID and authorise stage 2 / Approve with conditions / Ask for changes / Close the project]
Conditions[Conditions, owners, dates]
Stage 2 budget and tolerance released[Amount, tolerance]
Signed[Executive], YYYY-MM-DD

15. Glossary and references

TermMeaning in this document
Project boardThe group with authority to direct the project: executive, senior user, senior supplier
ExecutiveBoard member accountable for the business case and the project's success
Senior userBoard member representing those who will use the products and realise the benefits
Senior supplierBoard member representing those who design and build the products
StageA section of the project the board authorises one at a time
TolerancePermitted deviation from a plan target before escalation
Product descriptionSpecification of a product with its quality criteria and acceptance method
Change authorityPerson or group delegated to decide requests for change within limits
TailoringAdapting the method to the project's context, recorded with reasons
ReferenceTitleUse
[Doc ID]Project brief or charter (project/project-brief, project/project-charter)Input to initiation
BC-NNNBusiness case (business/business-case)Section 3
[Doc ID]Project management plan (project/project-management-plan)Alternative format for organisations that use a single plan document
[Doc ID]RAID log (project/raid-log)Section 7
[Doc ID]Communication plan (project/communication-plan)Section 8
[Doc ID]Kickoff meeting (meetings/kickoff)Start of stage 2
PRINCE2 7Managing Successful Projects with PRINCE2, 7th edition (PeopleCert)Structure aligned only (cited)
ISO 21502:2020Project, programme and portfolio management, guidance on project managementClause 6.5 initiating a project (cited only)

Standard and licence note

Structure aligned with the project initiation documentation of PRINCE2 7 (Managing Successful Projects with PRINCE2, 7th edition, PeopleCert; the current version of the method, launched in 2023) and with ISO 21502:2020, Project, programme and portfolio management: Guidance on project management (first edition, December 2020, currently under revision), clause 6.5 (initiating a project). This template is original text written for this collection. It uses generic role and product names and reproduces no text, tables, figures or product descriptions from either publication. The section order follows common practice for an initiation document and is not a copy of the method's product outline. PRINCE2 is a registered trademark of the PeopleCert group; this template is not endorsed by or affiliated with PeopleCert, and the name is used only to identify the source. Check the current editions before relying on them.