Change Request and Change Log Template

Project change request with impact on scope, schedule, cost, quality and risk, options, CCB decision record, change log and flow

프로젝트 관리표준changecontrol

사용법: Use whenever a change to an approved project baseline is proposed. Fill the description and justification first, then assess every impact dimension. Main pitfall: approving a change without updating the baselines and plans it affects.

미리보기

Change Request and Change Log: [Project name]

Change request form for proposing a change to an approved project baseline, with impact analysis, options and a recommendation, plus the change control board (CCB) decision record, the change log and the change flow. Based on common project management practice. Replace every [bracketed] value and every row marked Example.

FieldValue
Document ID[CC-PROJECT-001]
Project[Project name]
Change manager[@project-manager]
Change control board[Sponsor (chair), finance, architecture, operations representative]
Version[0.1]
Last updatedYYYY-MM-DD

1. Change control rules

Any stakeholder may raise a change request. The project manager logs it within [2] working days, completes the impact analysis within [5] working days and routes it for decision using these thresholds.

CategoryThresholdDecision byTarget decision time
MinorCost under [5,000 EUR], schedule under [5] days, no scope reduction, no benefit impactProject manager3 working days
SignificantCost under [25,000 EUR], schedule under [10] daysSponsor5 working days
MajorAbove sponsor tolerance, changes objectives or benefitsChange control boardNext CCB or extraordinary session
EmergencyNeeded to prevent immediate harm or a hard deadline missSponsor, ratified by CCB1 working day

2. Change request form

Complete one form per change request.

FieldValue
CR ID[CR-007]
TitleExample: Add accessibility audit before UAT
Raised by[@name], [role]
Date raisedYYYY-MM-DD
Category[Minor / Significant / Major / Emergency]
Baselines affected[Scope / Schedule / Cost / Quality]
Priority[High / Medium / Low]
Related items[RSK-014, requirement REQ-NFR-012]

2.1 Description of the change

[What exactly would change: deliverables, requirements, dates or budget lines.]

Example: Add an external accessibility audit of the onboarding front end against WCAG 2.2 AA, followed by remediation, before user acceptance testing starts.

2.2 Justification

[Why the change is needed and what happens if it is not made.]

Example: The legal team confirmed that the service falls under the national accessibility regulation from YYYY-MM-DD. Without an audit the bank cannot publish the required accessibility statement, and a later fix would cost about three times as much.

2.3 Impact analysis

Assess every dimension; write "None" where there is no impact.

DimensionImpactDetail
ScopeExample: AddedNew work package 1.3.4 Accessibility audit and remediation
ScheduleExample: +5 working daysUAT start moves; go-live protected by buffer (buffer use rises from 40% to 90%)
CostExample: +18,000 EURAudit 8,000 EUR, remediation 10,000 EUR
QualityExample: ImprovedAccessibility defects found before release
RiskExample: Reduces RSK-014; buffer exhaustion raises schedule riskResidual score 4 for RSK-014
ResourcesExample: +1 front-end developer for 2 weeksFrom vendor
BenefitsExample: None negativeSupports adoption by users of assistive technologies
Other projects[Impact][Detail]

2.4 Options

OptionDescriptionCostScheduleMain risk
AExample: Do nothing00Regulatory non-compliance at go-live
BExample: Full audit and remediation before UAT18,000 EUR+5 daysBuffer nearly exhausted
CExample: Audit before UAT, remediation in hypercare18,000 EUR+2 daysRelease with known accessibility defects

2.5 Recommendation

[Recommended option and reasoning, including funding source.]

Example: Option B, funded from contingency. It is the only option that meets the regulation at go-live; the schedule impact stays inside the project buffer.

3. CCB decision record

The decision on each change request is recorded here.

FieldValue
CR ID[CR-007]
Decision forum[CCB / Sponsor / Project manager]
Decision dateYYYY-MM-DD
Decision[Approved / Approved with conditions / Rejected / Deferred / More information needed]
Option chosen[B]
ConditionsExample: Audit vendor must be on the approved supplier list; report to CCB if remediation exceeds 10,000 EUR
Funding source[Contingency reserve]
Decided by[@sponsor, @finance, @architect]
Baselines to update[WBS v1.2, schedule v1.3, cost baseline v1.1]
Communicated to[Project team, vendor, steering committee]

4. Change log

All change requests are tracked in the log.

CR IDTitleRaisedCategoryCost impactSchedule impactDecisionDecision dateImplementedStatus
CR-005Example: Add Spanish language to formsYYYY-MM-DDSignificant+12,000 EUR+0 daysRejectedYYYY-MM-DDn/aClosed
CR-006Example: Move training delivery one week earlierYYYY-MM-DDMinor00ApprovedYYYY-MM-DDYYYY-MM-DDClosed
CR-007Example: Accessibility audit before UATYYYY-MM-DDSignificant+18,000 EUR+5 daysApproved with conditionsYYYY-MM-DDIn progress
[CR-nnn][Title]YYYY-MM-DD[Category][Cost][Days][Decision]YYYY-MM-DDYYYY-MM-DD[Status]

5. Cumulative change impact

The cumulative effect of approved changes is:

MeasureOriginal baselineApproved changesCurrent baseline
BudgetExample: 435,000 EUR+18,000 EUR453,000 EUR
Go-live dateYYYY-MM-DD+0 days (buffer used 5 days)YYYY-MM-DD
Work packages32+133
Contingency remaining43,500 EUR-18,000 EUR25,500 EUR

6. Change flow

Change requests move through the following steps.

Standard and licence note

Based on common project management practice for integrated change control and change control boards. This template is original text written for this collection. Template licence: MIT.