Punch List and Handover Record Template (CDM, ISO 19650-6)

Construction completion: punch (snag) list with categories, commissioning evidence, O&M and handover set, health and safety file, sign-off, defects period

Xây dựngChuẩnUK CDM 2015 reg. 12 and HSE L153 App. 4; ISO 19650-2:2018 5.7-5.8; ISO 19650-6:2025punchlisthandover
Mở trong editorTải .md

Cách dùng: Use it from first area completion through handover and the defects period. Fill the punch list by area and agree the handover document set with the client first. The main pitfall is one late walk-round that produces a list nobody can close before handover.

Xem trước

Punch List and Handover Record: [Project name]

The completion and handover record for a building or infrastructure project: the punch list (snag list) of defects and incomplete work, the handover document set including operation and maintenance (O&M) manuals and the health and safety file, training and asset data, and the sign-off that the asset has been handed over. The health and safety file follows regulation 12 of the UK Construction (Design and Management) Regulations 2015 and the content topics in HSE guidance L153 Appendix 4; the information handover aligns with ISO 19650-6:2025 (health and safety information) and ISO 19650-2:2018 clause 5.7 and 5.8. Replace every [bracketed] value and every row marked Example. This is a documentation format, not legal or contractual advice: check your contract, the current official text and a qualified professional. Facts checked October 2026.

Document control

FieldValue
Document ID[HO-FHL-001]
Project[Project name and code]
Contract and completion test[Contract form; clause defining practical or substantial completion]
Version[1.0]
Status[Snagging / Pre-handover / Handed over / Defects period / Closed]
Owner[Principal contractor's project manager, @name]
Client representative[@name]
Planned handover dateYYYY-MM-DD
End of defects or rectification periodYYYY-MM-DD
Last updatedYYYY-MM-DD

Revision history

VersionDateAuthorChange summary
0.1YYYY-MM-DD[@name]Punch list opened, level 1 areas
1.0YYYY-MM-DD[@name]Example: Handover certificate signed; 6 minor items carried into the defects period

1. Punch list

IDLocationDescriptionCategoryRaised byRaisedResponsibleTargetEvidence of closureStatus
PL-001 (Example)Level 2, reading room, rooflight RL-02Water ingress at upstand after rainAClient representativeYYYY-MM-DDRoofing contractorYYYY-MM-DDFlood test record and photoClosed
PL-002 (Example)Level 1, accessible toilet WC-03Emergency pull cord not reaching floor levelABuilding control inspectorYYYY-MM-DDElectrical contractorYYYY-MM-DDPhoto and testClosed
PL-003 (Example)Level 1, corridor C1Fire door FD-118 not self-closing fullyAFire engineerYYYY-MM-DDJoinery contractorYYYY-MM-DDDoor check sheetOpen
PL-004 (Example)Level 3, study roomsPaint damage at four door framesCArchitectYYYY-MM-DDDecorating contractorYYYY-MM-DDPhotoOpen
[PL-nnn][Room, grid, level][Defect][A/B/C][Who]YYYY-MM-DD[Contractor]YYYY-MM-DD[Evidence][Open/Closed]

1.1 Punch list summary (snapshot two weeks before handover)

CategoryRaisedClosedOpenOpen at handover allowed?
A (Example)18171No
B (Example)64604Only with client agreement
C (Example)1211156Yes, with dated plan
Total (Example)20319211

2. Commissioning and testing evidence

SystemTest or certificateByWitnessed byDateReference
Example: Fire alarmCommissioning certificateElectrical contractorFire engineerYYYY-MM-DDCERT-FA-01
Example: Emergency lightingCommissioning and duration testElectrical contractorClient's facilities managerYYYY-MM-DDCERT-EL-01
Example: VentilationAir flow balancing reportMechanical contractorMEP designerYYYY-MM-DDCERT-AHU-01
Example: LiftThorough examination before useLift installer, inspectorClientYYYY-MM-DDCERT-LIFT-01
[System][Test][By][Witness]YYYY-MM-DD[Ref]

3. Handover document set

ItemContentFormatDeliveredAccepted by client
O&M manualSystem descriptions, operating instructions, maintenance schedules, spares, supplier contacts, warranties[PDF, indexed, plus asset data]YYYY-MM-DDYYYY-MM-DD
As-built (record) drawings and modelsFinal drawings and models with status CR or equivalent[PDF, IFC, native]YYYY-MM-DDYYYY-MM-DD
Asset registerMaintainable assets with attributes required by the client[Spreadsheet in agreed template]YYYY-MM-DDYYYY-MM-DD
Health and safety fileSee section 4[Agreed format]YYYY-MM-DDYYYY-MM-DD
Statutory approvals and certificatesBuilding control completion, fire, electrical, gas, liftPDFYYYY-MM-DDYYYY-MM-DD
Warranties and guaranteesProduct and workmanship warranties with start datesPDFYYYY-MM-DDYYYY-MM-DD
Keys, access cards and codesKey schedule, signed receiptPhysical and scheduleYYYY-MM-DDYYYY-MM-DD

4. Health and safety file

Topic (summary of HSE L153 Appendix 4)Content for this projectSourceIncluded
Brief description of the workExample: New three-storey steel-frame libraryPrincipal designer[Yes]
Residual hazards and how they were addressedExample: Rooflights not designed to bear weight, access only from the roof walkwayDesigners[Yes]
Key structural principles and safe working loadsExample: Roof plant zone load limit, floor loads by areaStructural engineer[Yes]
Hazardous materials usedExample: None of note; coatings listed in the O&M manualContractors[Yes]
Removing or dismantling installed plantExample: Lifting points for air handling unit replacementMEP contractor[Yes]
Equipment for cleaning or maintaining the structureExample: Roof fall-arrest anchors, test certificates and test intervalRoofing contractor[Yes]
Significant services, their nature, location and markingsExample: Diverted gas main and incoming electricity cable positionsGroundworks contractor[Yes]
As-built drawings, including safe access to service voidsRecord drawings setAll[Yes]

Retention: the client keeps the file available for anyone who needs it for later work, normally for the life of the structure, and passes it on if the building is sold.

Other jurisdictions: [name the equivalent handover duties, for example building-specific safety information required by your regulator]. In England, higher-risk buildings have additional "golden thread" information handover duties under the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023: check whether they apply.

5. Training and demonstrations

TopicAudienceDelivered byDateAttendance record
Example: Building management systemFacilities teamControls subcontractorYYYY-MM-DDSigned list
Example: Fire alarm operation and weekly testFacilities teamElectrical contractorYYYY-MM-DDSigned list
[Topic][Audience][Trainer]YYYY-MM-DD[Record]

6. Handover sign-off

CheckStatus
No category A items open[Yes / No]
Category B items open only with client agreement[Yes, n items, list attached]
Commissioning evidence complete[Yes / No]
Handover document set delivered[Yes / No]
Health and safety file passed to the client[Yes, date]
Information model accepted and archived (ISO 19650-2 5.7.4, 5.8.1)[Yes / Not applicable]
RoleNameDecisionDate
Principal contractor[@name][Offered for handover]YYYY-MM-DD
Contract administrator[@name][Completion certified]YYYY-MM-DD
Client[@name][Accepted]YYYY-MM-DD

7. Defects period tracking

IDReportedDescriptionResponsibleTargetStatus
PL-204 (Example)YYYY-MM-DDCondensation at rooflight RL-01 frameRoofing contractorYYYY-MM-DDOpen

Standard and licence note

Based on the UK Construction (Design and Management) Regulations 2015, regulation 12, and the health and safety file topics in HSE guidance L153 Appendix 4 (HSE), with information handover aligned to ISO 19650-2:2018 clauses 5.7 and 5.8 and ISO 19650-6:2025, as checked in October 2026. The text is original. ISO standards are paid: official text from ISO and national standards bodies, purchase or licensed access at ISO 19650-6 and ISO 19650-2. Related templates: construction/construction-phase-plan, construction/bim-execution-plan, project/project-closure-report, ops/operations-handover. Check your contract and the current official text; this is not legal advice. Template licence: MIT.