Change Request and Change Log Template
Project change request with impact on scope, schedule, cost, quality and risk, options, CCB decision record, change log and flow
How to use: Use whenever a change to an approved project baseline is proposed. Fill the description and justification first, then assess every impact dimension. Main pitfall: approving a change without updating the baselines and plans it affects.
Preview
Change Request and Change Log: [Project name]
Change request form for proposing a change to an approved project baseline, with impact analysis, options and a recommendation, plus the change control board (CCB) decision record, the change log and the change flow. Based on common project management practice. Replace every
[bracketed]value and every row marked Example.
| Field | Value |
|---|---|
| Document ID | [CC-PROJECT-001] |
| Project | [Project name] |
| Change manager | [@project-manager] |
| Change control board | [Sponsor (chair), finance, architecture, operations representative] |
| Version | [0.1] |
| Last updated | YYYY-MM-DD |
1. Change control rules
Any stakeholder may raise a change request. The project manager logs it within [2] working days, completes the impact analysis within [5] working days and routes it for decision using these thresholds.
| Category | Threshold | Decision by | Target decision time |
|---|---|---|---|
| Minor | Cost under [5,000 EUR], schedule under [5] days, no scope reduction, no benefit impact | Project manager | 3 working days |
| Significant | Cost under [25,000 EUR], schedule under [10] days | Sponsor | 5 working days |
| Major | Above sponsor tolerance, changes objectives or benefits | Change control board | Next CCB or extraordinary session |
| Emergency | Needed to prevent immediate harm or a hard deadline miss | Sponsor, ratified by CCB | 1 working day |
2. Change request form
Complete one form per change request.
| Field | Value |
|---|---|
| CR ID | [CR-007] |
| Title | Example: Add accessibility audit before UAT |
| Raised by | [@name], [role] |
| Date raised | YYYY-MM-DD |
| Category | [Minor / Significant / Major / Emergency] |
| Baselines affected | [Scope / Schedule / Cost / Quality] |
| Priority | [High / Medium / Low] |
| Related items | [RSK-014, requirement REQ-NFR-012] |
2.1 Description of the change
[What exactly would change: deliverables, requirements, dates or budget lines.]
Example: Add an external accessibility audit of the onboarding front end against WCAG 2.2 AA, followed by remediation, before user acceptance testing starts.
2.2 Justification
[Why the change is needed and what happens if it is not made.]
Example: The legal team confirmed that the service falls under the national accessibility regulation from YYYY-MM-DD. Without an audit the bank cannot publish the required accessibility statement, and a later fix would cost about three times as much.
2.3 Impact analysis
Assess every dimension; write "None" where there is no impact.
| Dimension | Impact | Detail |
|---|---|---|
| Scope | Example: Added | New work package 1.3.4 Accessibility audit and remediation |
| Schedule | Example: +5 working days | UAT start moves; go-live protected by buffer (buffer use rises from 40% to 90%) |
| Cost | Example: +18,000 EUR | Audit 8,000 EUR, remediation 10,000 EUR |
| Quality | Example: Improved | Accessibility defects found before release |
| Risk | Example: Reduces RSK-014; buffer exhaustion raises schedule risk | Residual score 4 for RSK-014 |
| Resources | Example: +1 front-end developer for 2 weeks | From vendor |
| Benefits | Example: None negative | Supports adoption by users of assistive technologies |
| Other projects | [Impact] | [Detail] |
2.4 Options
| Option | Description | Cost | Schedule | Main risk |
|---|---|---|---|---|
| A | Example: Do nothing | 0 | 0 | Regulatory non-compliance at go-live |
| B | Example: Full audit and remediation before UAT | 18,000 EUR | +5 days | Buffer nearly exhausted |
| C | Example: Audit before UAT, remediation in hypercare | 18,000 EUR | +2 days | Release with known accessibility defects |
2.5 Recommendation
[Recommended option and reasoning, including funding source.]
Example: Option B, funded from contingency. It is the only option that meets the regulation at go-live; the schedule impact stays inside the project buffer.
3. CCB decision record
The decision on each change request is recorded here.
| Field | Value |
|---|---|
| CR ID | [CR-007] |
| Decision forum | [CCB / Sponsor / Project manager] |
| Decision date | YYYY-MM-DD |
| Decision | [Approved / Approved with conditions / Rejected / Deferred / More information needed] |
| Option chosen | [B] |
| Conditions | Example: Audit vendor must be on the approved supplier list; report to CCB if remediation exceeds 10,000 EUR |
| Funding source | [Contingency reserve] |
| Decided by | [@sponsor, @finance, @architect] |
| Baselines to update | [WBS v1.2, schedule v1.3, cost baseline v1.1] |
| Communicated to | [Project team, vendor, steering committee] |
4. Change log
All change requests are tracked in the log.
| CR ID | Title | Raised | Category | Cost impact | Schedule impact | Decision | Decision date | Implemented | Status |
|---|---|---|---|---|---|---|---|---|---|
| CR-005 | Example: Add Spanish language to forms | YYYY-MM-DD | Significant | +12,000 EUR | +0 days | Rejected | YYYY-MM-DD | n/a | Closed |
| CR-006 | Example: Move training delivery one week earlier | YYYY-MM-DD | Minor | 0 | 0 | Approved | YYYY-MM-DD | YYYY-MM-DD | Closed |
| CR-007 | Example: Accessibility audit before UAT | YYYY-MM-DD | Significant | +18,000 EUR | +5 days | Approved with conditions | YYYY-MM-DD | In progress | |
| [CR-nnn] | [Title] | YYYY-MM-DD | [Category] | [Cost] | [Days] | [Decision] | YYYY-MM-DD | YYYY-MM-DD | [Status] |
5. Cumulative change impact
The cumulative effect of approved changes is:
| Measure | Original baseline | Approved changes | Current baseline |
|---|---|---|---|
| Budget | Example: 435,000 EUR | +18,000 EUR | 453,000 EUR |
| Go-live date | YYYY-MM-DD | +0 days (buffer used 5 days) | YYYY-MM-DD |
| Work packages | 32 | +1 | 33 |
| Contingency remaining | 43,500 EUR | -18,000 EUR | 25,500 EUR |
6. Change flow
Change requests move through the following steps.
Standard and licence note
Based on common project management practice for integrated change control and change control boards. This template is original text written for this collection. Template licence: MIT.
Related templates
Benefits Realization Plan Template
Benefits map, benefit profiles with measure, baseline, target, timing and owner, tracking schedule, dependencies and dis-benefits
Project ManagementProject Communication Management Plan Template
Communication matrix (audience, purpose, channel, frequency, owner), meeting cadence, escalation path, repository and feedback
Project ManagementLessons Learned Register Template
Lessons workshop method, register with category, impact, root cause, recommendation, owner and where applied, plus actions