Go-Live Readiness Review Template

Go/no-go review: scope, test completion, operational acceptance, data migration, cutover, dependencies, business and support readiness, scorecard, conditions

Project ManagementFullDynamics 365 go-live checklist; NISTA Gate Review 4 (2026); ISTQB OATlivereadinessreview

How to use: Use it to decide, on evidence, whether a release or migration wave can go live on the planned date. Fill the rating rules and blocker definition first, then rate each area with linked artefacts. The main pitfall is averaging ratings so that one unready blocker hides behind an overall amber.

Preview

Go-Live Readiness Review: [Solution or release name]

Evidence-based review that decides whether a solution, release or migration wave is ready to go live on the planned date. It confirms scope, test completion, operational acceptance, data migration, cutover rehearsal, external dependencies, organisational readiness, support readiness, security and compliance, and open defects and risks, then records a go, conditional go or no-go decision with owners and dates. Structure aligned with the go-live checklist areas in the Microsoft Dynamics 365 implementation guide and with the readiness-for-service questions of the UK Gate Review 4 (NISTA, guidance updated August 2026), written for any technology. Replace every [bracketed] value and every row marked Example.

Document control

FieldValue
Document ID[GLR-001]
Solution or release[Solution name] [Release, wave or rollout]
Planned go-live (T-0)[YYYY-MM-DD HH:MM time zone]
Review type[Dry run / Formal (T-14) / Confirmation (T-1) / Re-review after no-go]
Review dateYYYY-MM-DD
Decision forum[Steering committee / Change advisory board / Programme board]
Version[0.1]
Status[Draft / Under review / Decided]
Owner[@programme-director]
Approvers/reviewers[@business-owner], [@service-owner], [@solution-architect], [@independent-reviewer], [@security-lead]
Classification[Internal / Confidential]
Last updatedYYYY-MM-DD
Related documents[Cutover plan], [Test completion report], [Hypercare plan], [RAID log]

Approvals

RoleNameDecisionDate
Business owner (decision owner)[@name][Go / Conditional go / No-go]YYYY-MM-DD
Programme director[@name][Recommendation]YYYY-MM-DD
Receiving service owner[@name][Accept into hypercare / Do not accept]YYYY-MM-DD
Independent reviewer[@name][Rating agreed / Dissent recorded]YYYY-MM-DD
Security and compliance[@name][Decision]YYYY-MM-DD

Revision history

VersionDateAuthorChange summary
0.1YYYY-MM-DD[@name]Dry-run review at T-6 weeks
1.0YYYY-MM-DD[@name]Example: Formal review at T-14; conditional go with seven conditions (GLC-01 to GLC-07)
1.1YYYY-MM-DD[@name]Example: T-1 confirmation; six conditions closed, one waived by the business owner

Contents

1. Review scope and timing

1.1 What goes live

ItemValue
Business capabilityExample: Order-to-cash and procure-to-pay for two legal entities
Users at go-liveExample: 640 named users in 4 sites; 120 warehouse device users
Systems replacedExample: Legacy ERP sales, purchasing and finance modules for entities DE01 and FR01
IntegrationsExample: 23 interfaces (14 outbound, 9 inbound), 3 with external partners
Rollout positionExample: Rollout 1 of 3; later rollouts reuse this review structure
Cutover windowExample: Saturday 06:00 to Monday 06:00

1.2 Decision and timetable

MilestoneTimingPurpose
Dry-run review (Example)T-6 weeksFind gaps while there is time to close them; no formal decision
Formal review (Example)T-14 daysRate every area and decide go, conditional go or no-go for the date
Condition follow-up (Example)T-14 to T-2 daysOwners close conditions; status reviewed twice a week
Confirmation (Example)T-1 (24 to 48 hours before T-0)Confirm conditions closed; feeds GNG-2 in the cutover plan
Last no-go date without external cost (Example)T-10 daysAfter this, partner test slots and contractor bookings are charged

1.3 Review panel

MemberRole in reviewIndependent of delivery?
[@name]Chair, business ownerNo
[@name]Independent reviewer, quality or assurance functionYes
[@name]Receiving service ownerPartly
[@name]Solution architectNo
[@name]Security leadYes
[@name]Finance or controlling representativeYes

2. Criteria and rating method

2.1 Rating scale

RatingMeaningEffect on the decision
ReadyAll criteria met with evidenceNone
Ready with conditionsCriteria not fully met, but a dated, owned action closes the gap before T-0 or an accepted workaround existsConditional go; condition tracked in section 14
Not readyA blocker remains with no credible plan before T-0No-go unless the business owner accepts the risk in writing and the independent reviewer records the dissent
Not assessedEvidence not providedTreated as Not ready

2.2 Blocker definition

A criterion is a blocker when failing it would stop a critical business process, cause loss or corruption of data, breach a legal or contractual obligation, or leave the service without the ability to restore or support it. Mark blockers with B in the criteria tables.

2.3 Evidence rules

  1. Each criterion cites at least one artefact with a location and date.
  2. Test evidence comes from the latest complete cycle, not from a selected earlier run.
  3. Sign-offs name a person, not a team.
  4. A waiver states the reason, the residual risk, the person accepting it and the date it expires.

Criteria IDs use GLR-<area>-NNN, where the area is the section number of this document. The scorecard in section 13 counts ratings by area.

3. Solution scope confirmation

IDCriterionBEvidenceRating
GLR-3-001 (Example)Business processes in scope listed and agreed with process ownersBScope baseline v1.4, signed YYYY-MM-DD[Rating]
GLR-3-002 (Example)Descoped items listed with workaround and target releaseDescope register[Rating]
GLR-3-003 (Example)Customisations, extensions and third-party add-ons in the release are known and supportedRelease content list, support contracts[Rating]
GLR-3-004 (Example)User numbers, sites and legal entities confirmed for this rolloutRollout plan[Rating]
GLR-3-005 (Example)Licences purchased and assignable for all go-live usersBLicence report[Rating]
[GLR-3-NNN][Criterion][B][Evidence][Rating]

4. Test completion

IDTest levelBExit criteria (from the test plan)ResultSigned byRating
GLR-4-001 (Example)System integration testingBAll interface scenarios passed, including partner-down scenarios; no open severity 1 or 2 defects412 of 418 passed; 6 deferred with workaround[@test-manager][Rating]
GLR-4-002 (Example)User acceptance testingBAll in-scope processes passed with migrated data and production roles96 % passed; 2 severity 2 open[@business-owner][Rating]
GLR-4-003 (Example)Performance and volume testingBPeak-hour volume processed within agreed response times; batch window metMet except report R-17[@performance-lead][Rating]
GLR-4-004 (Example)Security testingBNo open critical or high findings; medium findings accepted with dates1 high open, fix scheduled[@security-lead][Rating]
GLR-4-005 (Example)Regression testing of untouched systemsAutomated suite passed on the release baselinePassed[@test-manager][Rating]
GLR-4-006 (Example)Accessibility testing for user-facing screensConformance target met or exceptions recordedExceptions recorded[@ux-lead][Rating]
[GLR-4-NNN][Level][B][Criteria][Result][@name][Rating]

Reference the Test Completion Report (quality/test-completion-report) for detailed numbers. Record any test level not run and why.

5. Operational acceptance

IDCriterionBEvidenceRating
GLR-5-001 (Example)Backup runs on schedule and a restore was performed and timed by operations staffBRestore test record, restore time 3 h 40 min[Rating]
GLR-5-002 (Example)Disaster recovery tested against the agreed recovery time and point objectivesBDR test report[Rating]
GLR-5-003 (Example)Monitoring covers availability, latency, errors, queues and batch jobs; alerts routed to the rotaBAlert routing test, dashboard links[Rating]
GLR-5-004 (Example)Runbooks exist for start, stop, failover, common errors and batch rerunsRunbook set reviewed by operations[Rating]
GLR-5-005 (Example)Batch schedule documented with dependencies, owners and rerun rulesSchedule export[Rating]
GLR-5-006 (Example)Capacity headroom confirmed for the first 12 monthsCapacity plan[Rating]
GLR-5-007 (Example)Certificates, secrets and credentials have owners and expiry alertsSecret inventory[Rating]
GLR-5-008 (Example)Configuration items recorded in the CMDB with relationshipsCMDB extract[Rating]
[GLR-5-NNN][Criterion][B][Evidence][Rating]

The Production Readiness Review (dev/service-readiness) holds the detailed service checks for each component; cite its outcome here instead of repeating it. For recovery design see Disaster Recovery Plan (ops/disaster-recovery-plan).

6. Data migration readiness

IDCriterionBEvidenceRating
GLR-6-001 (Example)At least two full-volume mock loads completed; the latest passed all reconciliationsBMock load reports ML-2 and ML-3[Rating]
GLR-6-002 (Example)Load duration fits the cutover window with contingencyBDress rehearsal timing[Rating]
GLR-6-003 (Example)Business owners signed data quality and reconciliation results per objectBReconciliation sign-off sheet[Rating]
GLR-6-004 (Example)Data cleansing backlog closed or accepted with known impactCleansing tracker[Rating]
GLR-6-005 (Example)Migration scripts and mappings under version control and frozenRepository tag[Rating]
GLR-6-006 (Example)Migration data handled under the data classification rules, extracts deleted after useData handling procedure, deletion log plan[Rating]
[GLR-6-NNN][Criterion][B][Evidence][Rating]

See Data Migration Strategy (architecture/data-migration-strategy) and Data Migration Reconciliation (project/data-migration-reconciliation).

7. Cutover readiness

IDCriterionBEvidenceRating
GLR-7-001 (Example)Cutover plan approved with owners, durations, predecessors and verifications for every stepBCutover plan v1.0[Rating]
GLR-7-002 (Example)Dress rehearsal completed inside the windowBRehearsal result REH-03[Rating]
GLR-7-003 (Example)Rollback procedure rehearsed and its duration measuredBRehearsal result REH-04[Rating]
GLR-7-004 (Example)Go/no-go checkpoints, point of no return and rollback deadline agreed with the business ownerBCutover plan sections 7, 8 and 10[Rating]
GLR-7-005 (Example)Command centre staffed for every shift with named backupsRoster[Rating]
GLR-7-006 (Example)Change record approved for the production windowBChange record [CHG-NNNN][Rating]
[GLR-7-NNN][Criterion][B][Evidence][Rating]

8. External dependencies

IDDependencyBPartyNeeded byConfirmationFallbackRating
GLR-8-001 (Example)Bank payment file channel switched to the new sender ID[Bank]T+32hWritten confirmation YYYY-MM-DDManual payment upload for 2 days[Rating]
GLR-8-002 (Example)Logistics partner accepts new shipment message format[Partner]T+32hPartner test passed; production switch bookedEmail shipment list[Rating]
GLR-8-003 (Example)Tax authority e-invoicing registration for the new systemB[Authority]T-5dRegistration referenceNone[Rating]
GLR-8-004 (Example)Software vendor support available during window and hypercare[Vendor]T-0Support orderEscalation via account manager[Rating]
[GLR-8-NNN][Dependency][B][Party][When][Evidence][Fallback][Rating]

9. Organisational and business readiness

IDCriterionBEvidenceRating
GLR-9-001 (Example)Role-based training completed by at least the agreed share of users per roleBTraining completion report by role[Rating]
GLR-9-002 (Example)Super-users named and available on site for the first two weeksSuper-user roster[Rating]
GLR-9-003 (Example)Changed business procedures and work instructions publishedProcedure library[Rating]
GLR-9-004 (Example)Internal controls and approval limits configured and testedBControl test record[Rating]
GLR-9-005 (Example)Business continuity arrangements for the outage window agreed (manual orders, stock moves)Outage procedure[Rating]
GLR-9-006 (Example)Stakeholder and user communications issued on the T-minus scheduleCommunication log[Rating]
GLR-9-007 (Example)Change readiness survey shows no site below the agreed threshold, or actions are in placeSurvey results[Rating]
[GLR-9-NNN][Criterion][B][Evidence][Rating]

Training needs are best traced from a Training Needs Analysis (education/training-needs-analysis).

10. Support readiness

IDCriterionBEvidenceRating
GLR-10-001 (Example)Hypercare plan approved with duration, rota, severity targets and exit criteriaBHypercare plan v1.0[Rating]
GLR-10-002 (Example)Service desk trained, with categories, scripts and routing rules for the new serviceBService desk briefing record[Rating]
GLR-10-003 (Example)Lines of support (first, second, third, vendor) defined with escalation paths and out-of-hours coverBSupport model[Rating]
GLR-10-004 (Example)Support staff have the access and tools they need, testedAccess test[Rating]
GLR-10-005 (Example)Operations handover plan agreed, with knowledge transfer startedHandover plan, KT attendance[Rating]
GLR-10-006 (Example)Service level targets agreed for after hypercareService level agreement draft[Rating]
[GLR-10-NNN][Criterion][B][Evidence][Rating]

See Hypercare Plan (ops/hypercare-plan), Operations Handover and Knowledge Transfer (ops/operations-handover) and Service Level Agreement (ops/service-level-agreement).

11. Security, privacy and compliance

IDCriterionBEvidenceRating
GLR-11-001 (Example)Production roles follow least privilege; segregation of duties conflicts resolved or acceptedBRole review and conflict report[Rating]
GLR-11-002 (Example)Project and vendor accounts removed, disabled or time-limited for go-liveBAccess plan step in the cutover plan[Rating]
GLR-11-003 (Example)Security logging feeds the monitoring platform and alerts are testedLog source onboarding record[Rating]
GLR-11-004 (Example)Privacy assessment completed where personal data processing changedBDPIA reference[Rating]
GLR-11-005 (Example)Records retention and legal hold rules configured for migrated dataRetention configuration[Rating]
GLR-11-006 (Example)Architecture conformance review passed or deviations acceptedArchitecture compliance assessment[Rating]
[GLR-11-NNN][Criterion][B][Evidence][Rating]

Where privacy assessment is required, use the DPIA (compliance/dpia). For design conformance, use the Architecture Compliance Assessment (architecture/architecture-compliance-assessment).

12. Open defects, risks and workarounds

12.1 Open defects at review date

SeverityOpenAccepted with workaroundFix planned before T-0Fix planned in hypercare
1 Critical (Example)0000
2 High (Example)4121
3 Medium (Example)191234
4 Low (Example)373700

Check that each row adds up: defects accepted with a workaround plus fixes planned before T-0 plus fixes planned in hypercare equal the open count. Count each defect once: "Accepted with workaround" holds defects with no fix planned before hypercare exit, so a defect with a workaround and a hypercare fix date (DEF-0398 in the Example) counts under hypercare. Any severity 1 defect open at T-1 is a blocker.

12.2 Defects and risks that matter for the decision

IDTypeDescriptionBusiness impactWorkaroundOwnerDue
DEF-0412 (Example)Defect, severity 2Credit note print layout misses tax lineCredit notes cannot be sent to FR01 customersManual credit notes from template for up to 5 days[@name]T-3d
DEF-0398 (Example)Defect, severity 2Report R-17 exceeds 10 minutes at peakDaily sales review delayedRun at 05:00 as a scheduled job[@name]Hypercare week 1
RSK-031 (Example)RiskPeak season starts 3 weeks after go-liveLittle time to stabilise before volume risesExtend hypercare to cover first peak week[@name]Decision at review
[ID][Type][Description][Impact][Workaround][@owner][Date]

Keep the full list in the RAID Log (project/raid-log).

13. Readiness scorecard

AreaCriteriaReadyWith conditionsNot readyBlockers not readyArea rating
3 Solution scope (Example)55000Ready
4 Test completion (Example)63300Ready with conditions
5 Operational acceptance (Example)87100Ready with conditions
6 Data migration (Example)66000Ready
7 Cutover (Example)66000Ready
8 External dependencies (Example)43100Ready with conditions
9 Organisational readiness (Example)76100Ready with conditions
10 Support readiness (Example)66000Ready
11 Security and compliance (Example)65100Ready with conditions
[Area][N][N][N][N][N][Rating]

Overall rule: the overall rating is the lowest area rating, and any blocker rated Not ready makes the overall rating Not ready. In the Example, 7 conditions across five areas give an overall rating of Ready with conditions.

14. Decision, conditions and actions

14.1 Decision

FieldValue
Decision[Go / Conditional go / No-go]
StatementExample: Conditional go for Saturday YYYY-MM-DD, subject to conditions GLC-01 to GLC-07 being closed or waived by the T-1 meeting
Decided by[@business-owner] on YYYY-MM-DD
Recommendation of independent reviewerExample: Agree, with concern over the peak season risk RSK-031
Dissent recorded[None / Name and reason]
If no-go: new review dateYYYY-MM-DD

14.2 Conditions

IDConditionSource criterionOwnerDueProof of closureStatus
GLC-01 (Example)Fix and re-test DEF-0412GLR-4-002[@name]T-3dRe-test record[Open / Closed / Waived]
GLC-02 (Example)Close the open high security findingGLR-4-004[@name]T-5dRe-scan report[Status]
GLC-03 (Example)Schedule report R-17 as a 05:00 job and inform usersGLR-4-003[@name]T-2dJob in schedule, user notice[Status]
GLC-04 (Example)Complete the capacity sign-off for the reporting databaseGLR-5-006[@name]T-7dSigned capacity plan[Status]
GLC-05 (Example)Obtain production switch date from logistics partnerGLR-8-002[@name]T-7dWritten confirmation[Status]
GLC-06 (Example)Deliver refresher training for warehouse staff at site 3GLR-9-001[@name]T-4dAttendance list[Status]
GLC-07 (Example)Resolve two segregation of duties conflicts in finance rolesGLR-11-001[@name]T-5dConflict report[Status]
[GLC-NN][Condition][GLR ID][@owner][Date][Evidence][Status]

14.3 Traceability

Decision inputCriteriaConditionsCarried to
Test completion (Example)GLR-4-002, GLR-4-003, GLR-4-004GLC-01, GLC-02, GLC-03Cutover plan entry criteria CUT-EC-001
Operations (Example)GLR-5-006GLC-04Operations handover acceptance criteria
Dependencies (Example)GLR-8-002GLC-05Cutover plan GNG-2
Risk (Example)RSK-031NoneHypercare plan duration and exit criteria
[Input][IDs][IDs][Document and ID]

15. Glossary and references

15.1 Glossary

TermMeaning in this review
Go-liveThe moment users and partners start using the solution for real business
BlockerA criterion whose failure would stop a critical process, lose data, breach an obligation or leave the service unsupportable
Conditional goApproval to proceed provided named conditions close by a stated date
Operational acceptance testing (OAT)Testing by or with operations staff of operability: backup, restore, recovery, monitoring, maintainability and security operations
WaiverWritten acceptance of a residual risk by an accountable person, with an expiry date
HypercarePeriod of elevated support after go-live
T-0Start of the cutover window

15.2 References

ReferenceVersion or date checkedUse
Microsoft Dynamics 365 implementation guide, go-live checklist, learn.microsoft.comPage updated 2026-07-15Area list for sections 3 to 10, paraphrased
Microsoft Dynamics 365 implementation guide, prepare your production environment to go live (go-live readiness review), learn.microsoft.comPage updated 2026-10-15Review timing and purpose
NISTA, Gate Review 4: Readiness for Service, gov.ukFirst published 2021-07-15; HTML version added 2026-08-20Readiness-for-service questions aligned with the Five Case Model; check gov.uk for the current version
AWS Prescriptive Guidance, Project governance playbook for AWS large migrations, docs.aws.amazon.comInitial publication 2022-02-28T-14 checkpoint and T-1 go or no-go timing
ISTQB Glossary, operational acceptance testing, glossary.istqb.orgCheck the current glossary versionMeaning of OAT
[Internal assurance framework][Version][Use]

Standard and licence note

Structure aligned with the go-live checklist areas and the go-live readiness review described in the Microsoft Dynamics 365 implementation guide, with the readiness-for-service gate published by the UK National Infrastructure and Service Transformation Authority (NISTA, Gate Review 4, which replaces the earlier Infrastructure and Projects Authority guidance) and with the go or no-go timing in the AWS Prescriptive Guidance large migration governance playbook. Area names are used for mapping; all criteria are written in original wording and no checklist item, workbook question or template is reproduced. Microsoft, Dynamics 365, Amazon Web Services and AWS are trademarks of their owners; this template is not affiliated with or endorsed by them. UK government guidance is cited by title and date only. This template is original text written for this collection. Check the current official guidance before use. Template licence: MIT.