Daily Site Report Template (Construction)

Construction daily report: weather, labour and hours, plant, progress against programme, deliveries, inspections, safety events, delays

ConstrucciónBrevedailysitereport

Cómo usar: Use it every working day on a construction site. Fill weather times, labour counts and delays with facts and times, the same day. The main pitfall is vague entries that are no use as evidence when a delay or change is assessed later.

Vista previa

Daily Site Report: [Project name], YYYY-MM-DD

A one-day record of a construction site: weather, labour and plant on site, work done against the programme, deliveries, visitors, inspections, health and safety events, delays and instructions received. Based on common construction practice. Daily records are often the main evidence when a delay, change or claim is assessed later, so complete it the same day. Replace every [bracketed] value and every row marked Example.

Document control

FieldValue
Report number[DSR-FHL-0187]
Date and shiftYYYY-MM-DD, [07:30 to 17:00]
Prepared by[Site manager, @name]
Distributed to[Project manager, client representative]

1. Weather and site conditions

TimeConditionsTemperatureWindEffect on work
08:00 (Example)Overcast, dry9 C15 km/hNone
10:20 to 13:45 (Example)Heavy rain8 C30 km/hRoof work stopped; crane lifts paused per lift plan weather limits

2. Labour on site

ContractorTradeWorkersHours eachTotal hours
Quillmere Construction (Example)Management and labourers6954
Roofing contractor (Example)Roofers4832
Steel erector (Example)Erectors5840
MEP contractor (Example)Electricians, fitters12896
Total (Example)27222

3. Plant and equipment

ItemNumberHours workedHours idleReason idle
Mobile crane 50 t (Example)15.53.5Rain 10:20 to 13:45
Telehandler (Example)171

4. Work done and progress

Area or activityProgramme IDWork done todayStatus
Roof zone 2 (Example)3.4.2Rooflight RL-01 opening cut, trimmers fixedBehind 1 day, weather
Level 2 first fix electrical (Example)5.2.1Containment 60% completeOn programme

5. Deliveries, visitors and inspections

TimeTypeDetail
09:10 (Example)DeliveryTwo rooflight units, delivery note DN-55812, checked and stored
14:00 (Example)InspectionScaffold weekly inspection, register signed
15:30 (Example)VisitorClient representative, escorted

6. Health, safety and environment

ItemCountDetail and reference
AccidentsExample: 0
Near missesExample: 1Unsecured cover near roof opening, corrected; NM-FHL-022
Toolbox talks and RAMS briefingsExample: 1RAMS-FHL-011 briefed to roofing team
Environmental eventsExample: 0

7. Delays, instructions and issues

ItemDetailReference
DelayExample: Roof works stopped 3.4 hours for rainProgramme 3.4.2
Instruction receivedExample: Proceed with two extra rooflightsEI-031, VO-007
RFI raisedExample: Drain found at grid A/1RFI-043 (construction/rfi-log)

Standard and licence note

Based on common construction site management practice for daily records. The text is original. Check your contract for any required record format or submission period. Template licence: MIT.