Procurement Management Plan Template

Make-or-buy analysis, procurement items, contract types, weighted supplier evaluation, timeline, supplier management, approvals

프로젝트 관리표준procurementplanmath

사용법: Use early in planning, because procurement lead times often sit on the critical path. Fill make-or-buy and procurement items first, then fix evaluation weights before bids arrive. Main pitfall: changing criteria after seeing bids. Planning format, not legal advice.

미리보기

Procurement Management Plan: [Project name]

Plan for buying the goods and services the project needs: make-or-buy analysis, procurement items, contract types, sourcing and weighted evaluation criteria, timeline, supplier management, risks and approvals. Based on common project management practice. This is a planning format, not legal or procurement advice: follow your organisation's procurement policy and applicable public procurement law. Replace every [bracketed] value and every row marked Example.

FieldValue
Document ID[PP-PROJECT-001]
Project[Project name]
Version[0.1]
Owner[@project-manager]
Procurement lead[@procurement]
Approved by[@sponsor, @head-of-procurement]
Classification[Confidential]
Last updatedYYYY-MM-DD

1. Scope and policy

This plan covers all external goods and services bought for [Project name] with an estimated total value of [amount]. Procurement follows [organisation procurement policy, version] and, where applicable, [public procurement regulation]. Purchases below [threshold] use the simplified purchase-order process and are not listed individually.

2. Make-or-buy analysis

Each candidate item was assessed for in-house delivery against external sourcing.

ItemMake: cost and timeBuy: cost and timeCapability in-houseStrategic considerationDecision
Example: Onboarding front end260,000 EUR, 7 months140,000 EUR fixed price, 5 monthsLimited (2 front-end developers, both committed)Not a differentiating capabilityBuy
Example: Identity verification400,000 EUR, 12 months0.80 EUR per check, available nowNoneRegulated, specialist serviceBuy (subscription)
Example: Process design8,400 EUR, 2 months30,000 EUR, 2 monthsStrongCore business knowledgeMake
[Item][Make][Buy][Capability][Strategic][Decision]

3. Procurement items

The following items will be procured.

IDItemEstimated valueProcurement methodContract typeNeeded byOwner
PRC-01Example: Front-end implementation services140,000 EURCompetitive tender (3 to 5 bidders)Fixed price with milestonesYYYY-MM-DD[@procurement]
PRC-02Example: Identity verification service48,000 EUR per yearFramework call-offUnit price, 3 yearsYYYY-MM-DD[@procurement]
PRC-03Example: Accessibility audit8,000 EURThree quotesFixed priceYYYY-MM-DD[@pm]
[PRC-nn][Item][Value][Method][Type]YYYY-MM-DD[@owner]

4. Contract types

The project uses the contract types below, chosen according to how well the scope is defined.

Contract typeWhen usedRisk to buyerControls
Fixed priceScope is stable and well specifiedLow cost risk; change requests can be expensiveClear acceptance criteria, milestone payments
Time and materialsScope is uncertain or exploratoryHigh cost riskNot-to-exceed cap, weekly timesheet review
Unit priceRepeatable units (transactions, licences)Volume riskVolume bands, monthly reporting
Cost plus feeRare; specialist work with unknown scopeHighest cost riskAudit rights, incentive fee

5. Sourcing and evaluation

Suppliers are first checked against mandatory requirements, then scored on weighted criteria.

Mandatory requirements (pass or fail): [registration and financial standing, data processing in the EU, ISO/IEC 27001 certification or equivalent, acceptance of standard terms].

CriterionWeightWhat is assessed
Solution fit30%Coverage of requirements, quality of proposed approach
Price25%Total cost over contract term
Delivery capability20%Named team experience, references, plan realism
Security and data protection15%Controls, certifications, incident history
Commercial terms10%Warranty, liability, exit support

Each criterion is scored 0 to 5 by at least three evaluators independently and averaged. The weighted score is:

S=∑i=1nwi⋅si,∑i=1nwi=1S = \sum_{i=1}^{n} w_i \cdot s_i, \qquad \sum_{i=1}^{n} w_i = 1

SupplierFit (30%)Price (25%)Delivery (20%)Security (15%)Terms (10%)Weighted score
Example: Supplier A4.33.54.04.53.03.94
Example: Supplier B3.74.53.34.04.03.90
[Supplier][s][s][s][s][s][S]

6. Timeline

The procurement timeline for the main tender is shown below.

StepDateResponsible
Tender issuedYYYY-MM-DD[@procurement]
Bids dueYYYY-MM-DDSuppliers
Award decisionYYYY-MM-DD[@sponsor]
Contract signedYYYY-MM-DD[@legal]

7. Supplier management

Each contract has a named contract manager who runs performance reviews and approves acceptance before payment.

SupplierContract managerPerformance measuresReview frequencyAcceptance and payment
Example: Front-end vendor[@pm]Milestones on time, defect rate in UAT, named staff retainedWeekly progress, monthly performancePayment per milestone after signed acceptance
Example: Identity service[@tech-lead]Availability 99.9%, response p95 under 1.5 sMonthlyMonthly invoice against usage report
[Supplier][@name][Measures][Frequency][Terms]

8. Procurement risks

Procurement-specific risks:

IDRiskScoreResponseOwner
RSK-020Example: Too few compliant bids, forcing re-tender and 6-week delay9Market sounding before tender; invite 6 suppliers[@procurement]
RSK-021Example: Supplier lock-in through proprietary components8Require source code escrow and exit assistance clause[@legal]
[ID][Risk][n][Response][@owner]

9. Approvals and authority

Procurement decisions are approved according to value.

ValueApproves awardSigns contract
Below [10,000 EUR]Project managerProcurement lead
[10,000 to 100,000 EUR]SponsorHead of procurement
Above [100,000 EUR]Steering committee[Chief financial officer]

10. Contract closure

At contract end the contract manager confirms final acceptance of deliverables, settles open claims and invoices, ensures return or deletion of project data and assets, and records a supplier performance evaluation for future sourcing decisions.

Standard and licence note

Based on common project management practice for procurement planning, make-or-buy analysis and weighted supplier evaluation. This template is a planning format, not legal or procurement advice, and is original text written for this collection. Template licence: MIT.