RAID Log Template (Risks, Assumptions, Issues, Dependencies)

Risks, assumptions, issues and dependencies log with probability x impact scoring, owners, due dates, heat map and review cadence

프로젝트 관리표준raidlogmath

사용법: Use throughout the project as the working log reviewed every week. Agree the scoring scales first, then record items with one owner and a due date each. Main pitfall: updating the log only before steering meetings, so it stops driving action.

미리보기

RAID Log: [Project name]

Single log for project Risks, Assumptions, Issues and Dependencies, with scoring, owners, due dates, status and a review cadence. Based on common project management practice. Replace every [bracketed] value and every row marked Example.

FieldValue
Document ID[RAID-PROJECT-001]
Project[Project name]
Owner[@project-manager]
Review cadence[Weekly project board; monthly steering committee]
Last reviewedYYYY-MM-DD
Open items[Risks n, Assumptions n, Issues n, Dependencies n]

1. Scoring scales

Risks are scored on probability and impact, each from 1 to 5.

Score=P×I,1≤Score≤25\text{Score} = P \times I, \qquad 1 \le \text{Score} \le 25

RatingProbability (P)Impact (I): scheduleImpact (I): costImpact (I): quality or scope
1 Very lowBelow 10%Under 2 daysUnder 1% of budgetCosmetic
2 Low10 to 30%2 to 5 days1 to 3%Minor feature degraded
3 Medium31 to 50%6 to 10 days3 to 5%Important feature degraded
4 High51 to 70%11 to 20 days5 to 10%Objective partly missed
5 Very highAbove 70%Over 20 daysOver 10%Objective missed

Impact takes the highest of the applicable dimensions. Thresholds: High 15 to 25, Medium 8 to 14, Low 1 to 7.

2. Risks

Risks are uncertain events that would affect objectives if they occurred.

IDRisk (cause, event, effect)PIScoreResponse typeResponse actionsResidual scoreOwnerDueStatus
RSK-001Example: Because the vendor team is shared with another client, key developers may be unavailable, delaying the front-end build by up to 3 weeks4416ReduceNamed-team clause in contract; weekly staffing check8[@pm]YYYY-MM-DDOpen
RSK-002Example: Because the identity service is changing its API version, integration may need rework, adding 8 days339ReduceBuild against the new version in sandbox now4[@tech-lead]YYYY-MM-DDOpen
RSK-003Example: Opportunity: reuse the group's design system could cut front-end effort by 10%326ExploitConfirm licence and component coverage6[@ux-lead]YYYY-MM-DDOpen
[RSK-nnn][Cause, event, effect][1-5][1-5][n][Type][Actions][n][@owner]YYYY-MM-DD[Open / Closed / Occurred]

3. Assumptions

Assumptions underpin the plan and are validated by the owner before the date shown.

IDAssumptionBasisImpact if falseValidation methodOwnerValidate byStatus
ASM-001Example: Branch staff can be released for 4 hours of training eachHR agreement in principleRollout delayed 2 weeksWritten confirmation from HR director[@change-lead]YYYY-MM-DDOpen
ASM-002Example: Existing customer data is clean enough to migrate without manual correctionSample of 500 recordsData cleansing workstream neededFull data profiling[@data-lead]YYYY-MM-DDValidated
[ASM-nnn][Assumption][Basis][Impact][Method][@owner]YYYY-MM-DD[Open / Validated / Invalid]

4. Issues

Issues are current problems that need action.

IDIssueRaisedPriorityImpactActionOwnerDueStatusResolution
ISS-001Example: Test environment unavailable since Monday; integration testing blockedYYYY-MM-DDP1A05 delayed 3 days so farInfra ticket escalated; temporary environment requested[@tech-lead]YYYY-MM-DDOpen
ISS-002Example: Two UAT testers reassigned to auditYYYY-MM-DDP2UAT capacity minus 40%Replacement agreed with operations head[@test-lead]YYYY-MM-DDClosedTwo testers from QA pool assigned
[ISS-nnn][Issue]YYYY-MM-DD[P1 / P2 / P3][Impact][Action][@owner]YYYY-MM-DD[Status][Resolution]

5. Dependencies

Dependencies link this project to work outside its control.

IDDependencyDirectionCounterpart (project or team)Needed byCounterpart ownerOur ownerStatus
DEP-001Example: Core banking API v3 released to testInboundCore banking upgrade programmeYYYY-MM-DD[@cb-pm][@tech-lead]On track
DEP-002Example: New onboarding data feed for CRM projectOutboundCRM replacement projectYYYY-MM-DD[@crm-pm][@pm]At risk
[DEP-nnn][Dependency][Inbound / Outbound][Counterpart]YYYY-MM-DD[@name][@name][Status]

6. Risk heat map

The heat map shows open risks by probability (rows) and impact (columns). Cells in the High band need steering committee visibility.

P by I12345
5MediumMediumHighHighHigh
4LowMediumMediumHigh: RSK-001High
3LowLow: RSK-003Medium: RSK-002MediumHigh
2LowLowLowMediumMedium
1LowLowLowLowLow

7. Summary and trends

Summary at the last review on YYYY-MM-DD:

CategoryOpenOpened since last reviewClosed since last reviewHigh or P1
Risks[n][n][n][n]
Assumptions[n][n][n]n/a
Issues[n][n][n][n]
Dependencies[n][n][n][n at risk]

Top items for escalation: [RSK-001 vendor staffing; DEP-002 CRM data feed].

8. Review cadence and rules

The RAID log is reviewed as follows.

ForumFrequencyScopeOutcome
Project boardWeeklyAll open itemsUpdated scores, actions, due dates
Steering committeeMonthlyHigh risks, P1 issues, at-risk dependenciesDecisions, risk acceptance
Stage gateAt each gateWhole logConfirm residual risk is acceptable to proceed

Out-of-cycle review is triggered by a new High risk, a P1 issue, or a missed dependency date. Closed items stay in the log, filtered from the default view, for lessons learned.

Standard and licence note

Based on common project management practice for RAID logs and risk scoring with a probability and impact matrix. This template is original text written for this collection. Template licence: MIT.